You are here:
NZLII >>
Databases >>
High Court of New Zealand Decisions >>
2005 >>
[2005] NZHC 1840
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Drillien v Tubberty HC Auckland CIV-2004-404-2873 [2005] NZHC 1840; (2005) 6 NZCPR 470 (15 February 2005)
Last Updated: 5 October 2024
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV 2004-404-2873
|
BETWEEN
|
ANTHONY TAYLOR DRILLIEN AND
MARGARET JOSEPHINE DRILLIEN
|
|
Plaintiffs
|
|
AND
|
PETER THOMAS TUBBERTY
First Defendant
|
|
AND
|
RAKESH CHAND
Second Defendant
|
|
AND
|
AUCKLAND CITY COUNCIL
Third Defendant
|
|
Hearing:
|
8 February 2005
|
|
Appearances: MH Benvie for plaintiffs
JRF Fardell QC and CR Andrews for first defendant
Judgment: 15 February 2005 at 10:45

[on application for summary judgment]
Solicitors: Alexander Dorrington, PO Box 7246, Auckland for plaintiffs
McVeagh Fleming, PO Box 4099, Auckland for first defendant
Drillien & Anor V Tubberty And Ors HC AK CIV 2004-404-2873 15 February
2005
Introduction
[1] The first defendant applies for:
a) leave to seek summary
judgment;
b) summary judgment against the plaintiffs; or, in the alternative,
- an
order striking out the plaintiffs’ pleading against the first
defendant.
- [2] The
application is opposed by the plaintiffs. The third defendant did not wish to
be heard on this application. At a conference
on 21 July 2004 I was advised that
the second defendant had not been served. The second defendant accordingly took
no part in the
application.
- [3] Mr Benvie
advised that the plaintiffs do not oppose the granting of leave to make the
application for summary judgment. Accordingly,
leave is granted in terms of r
138(3) of the High Court Rules.
- [4] The
plaintiffs oppose the application for summary judgment, or, in the alternative,
the striking out of the proceedings. Counsel’s
submissions focussed on the
summary judgment application. Both counsel took the view that there was no
practical distinction, for
the purpose of the outcome, in determining either the
summary judgment application or the strike out application in this case. For
that reason, although the approach which the Court adopts is different in
respect of each type of application, I will consider this
application as
principally an application for summary judgment by the first
defendant.
Background
- [5] Kenview
Homes Limited is a company which was incorporated in November 1986. The first
defendant and his wife were at all material
times the directors and shareholders
of the company. The company ceased trading in 2002. It was
struck
off the Register of Companies on 28 February 2003. The first
defendant estimated that the company purchased, developed and sold approximately
70 residential properties in Auckland in the period between 1986 and 2002.
- [6] The company
acquired a property at 45 Ngapuhi Road, Remuera, Auckland. It removed an
existing dwelling and subdivided the land.
It then constructed a two- level
building on part of the land. To do this it sought, and obtained, a building
consent. It engaged
appropriate contractors, generally on a labour-only basis,
to construct the dwelling in accordance with plans approved by the third
defendant. The third defendant issued a building consent.
- [7] The first
defendant has sworn an affidavit. He said that his relationship with contractors
who worked on Kenview Homes Limited’s
building site goes back many years.
Evidence was also given by affidavits from some of the contractors who were
employed by the company.
In substance, that disclosed that, as a result of the
long- standing relationship, it was not necessary for the first defendant to
carry out any detailed supervision work on behalf of the company. The deponents
in fact say that the first defendant did not carry
out detailed supervision of
building work on the construction site. The company’s only employee was
the son of the first defendant
and his wife. PAYE was paid by the company in
respect of his employment. The first defendant and his wife drew drawings from
the
company on current account. No salary was received by the first
defendant.
- [8] The company,
at any one time, usually had two or three developments under way. At the time
the Ngapuhi Road property was being
constructed the company also had
constructions at East Glen Street, Glen Eden and at New Windsor Road, Blockhouse
Bay.
- [9] The first
defendant has described the practice that he adopted with respect to the
development of 45 Ngapuhi Road as follows:
- 11.1 On behalf
of Kenview I would provide the proposed plans and drawings to Kenview’s
engineers for checking and certification.
- 11.2 I would
complete a building consent application in Kenview’s name, and submit it,
together with the certified
plans and proposed specifications to the relevant city council for a building
consent (in this case the Auckland City Council).
- 11.3 I would
provide a cheque from Kenview in payment of the building consent application
fee.
- 11.4 Once the
consent had been obtained, I would pass the plans to Kenview’s timber
supplier, Pinepac Timber for quotes for
timber quantities, manufacturing of
pre-nail trusses, and so forth.
- 11.5 The same
process would be adopted with Kenview’s other suppliers.
- 11.6 At the same
time I would contact the contractors and let them have copies of the plans, and
let them see any conditions that
the council might have placed on the building
consent.
- 11.7 The usual
arrangement, and that following on 45 Ngapuhi Road, was that the contractors
worked on a labour only basis, and Kenview
paid for and supplied the materials
that they used.
12. Once work had started on site, I spent my time co-ordinating the supply
and delivery of materials and arranging the various
required council inspections
at the appropriate times. Obviously, this meant liasing with the various
contractors concerning the
materials they required, what stage the work was at
so that I could co-ordinate the inspections and also co-ordinate the arrival
of
other trades.
[10] Mr Tubberty said that it had been many years since he
carried out any physical building work for the company. He said that he
did
not build any part of the building at 45 Ngapuhi Road nor, for that matter, did
he do any of the building work on East Glen
Street or New Windsor Road. Rather,
he carried out the matters that are summarised in the preceding paragraph and
also carried out
work on a project at Mt Maunganui.
- [11] In
early 2002, when the construction of the property at 45 Ngapuhi Road was nearing
completion, the company marketed the property
for sale through a real estate
agent, Unlimited Potential Limited. The plaintiffs were apparently introduced to
the property by Unlimited
Potential Limited’s salesman. They asked for a
number of special conditions to be put into a standard ADLS (7th ed) sale and
purchase contract which the land agent duly prepared. Kenview Homes Limited was
shown as vendor on the contract. There was some to-ing
and fro-ing apparently
through the offices of
the real estate agent before the agreement in
final form was acceptable to the parties and executed. The contract was signed
on 5
March 2002.
- [12] It is
significant that the first defendant gave notice to the local authority of
completion of the building works in respect
of the property on 12 March 2002. At
that stage there had been no actual meeting of the plaintiffs and the first
defendant. All negotiations
had been conducted by the land agent.
- [13] The sale
and purchase contract contained four special terms as follows:
- 14.0 The vendor
warrants to complete the property to a professional and workmanlike standard
including the:
(1) installation of the Gas Hobbs, Oven and dishwasher
(2) adjustment of the kitchen pantry cabinets and replacement of the glass
door in the end cabinet.
(3) The repair of the wall behind the handrail going downstairs to repair the
screw holes in the Gib.
15.0 The vendor covenants with the purchaser that it will, at its own cost,
forthwith remedy all the defects or faults which may
have arisen from faulty
workmanship or materials for which written notice has been given to the vendor
within a period of 60, 25 40 days from the
date on which the purchasers enter into possession of the property.
16.0 The vendor Kenview Homes Ltd will do all things necessary to complete the
subdivision and issue a new title for the land herein
described with all due
speed. However, should the new title not be issued by 26/4/02 the purchaser
shall upon payment of the balance
of the purchase price in full be entitled to
have possession of the property. The balance of the purchase price shall be
held undispersed
in the vendors solicitors trust account until title is
available.
[14] The third defendant issued a code of compliance on 9 April
2002. The plaintiffs then settled their purchase with Kenview Homes
Limited and
took possession on 26 April 2002. Subsequent to that time there was a meeting
between the plaintiffs and the defendant
when the matters the subject of special
condition 14 were discussed and actioned.
- [15] I
will return to complete the summary of facts as I discuss the specific issues
which arise in this application. The above background,
however, sets the
position that applies.
The pleadings
- [16] The
plaintiffs filed a statement of claim in this Court on 4 June 2004. It pleads
causes of action against the first defendant
in tort, alleging that the first
defendant personally undertook building work and supervised the construction of
the property at
45 Ngapuhi Road and thereby assumed a personal duty of care to
the plaintiffs as purchasers in respect of the construction of the
dwelling. The
statement of claim pleads that the first defendant, as builder and owner, gave
notice to the third defendant of the
completion of the works on 12 March 2002.
The statement of claim next asserts that the first defendant breached the duty
of care
owed to the plaintiffs and was negligent in that he failed to take
reasonable care to ensure that the building work was undertaken
in accordance
with good workmanlike practices and in accordance with the requirements of the
Building Code. The statement of claim
then alleges a number of defects in the
cladding of the building, the external joinery, the roof, the structural framing
timbers
and then alleges that, as a result, water has entered the building
causing damage to it. It then alleges that the plaintiffs will
suffer economic
loss in respect of the cost of remedial works together with building consultant
fees, accommodation costs, travelling
costs and other consequential costs of the
remedial works. In addition, damages for distress and inconvenience are
claimed.
The Court’s approach to summary judgment
- [17] The Court
of Appeal has given guidance as to the approach which is to be adopted when the
Court considers entering summary judgment
on a defendant’s application
against a plaintiff pursuant to r 136(2) of the High Court Rules. That was
given in Westpac Banking Corporation v MM Kembla (NZ) Ltd [2000] NZCA 319; [2001] 2 NZLR
298 at [58]- [64] and Bernard v Space 2000 Ltd [2001] NZCA 214; (2001) 15 PRNZ 338.
- [18] In
Westpac Banking Corporation v MM Kembla (NZ) Ltd the Court
said:
- [58] The
applications for summary judgment were made under R 136(2) of the High Court
Rules which permits the Court to give judgment
against the plaintiff “if
the defendant satisfies the Court that none of the causes of action in the
plaintiff's statement
of claim can succeed”.
- [59] Since R
136(2) permits summary judgment only where a defendant satisfies the Court that
the plaintiff cannot succeed on any of
its causes of action, the procedure is
not directly equivalent to the plaintiff's summary judgment provided by R
136(1).
- [60] Where a
claim is untenable on the pleadings as a matter of law, it will not usually be
necessary to have recourse to the summary
judgment procedure because a defendant
can apply to strike out the claim under R 186. Rather R 136(2) permits a
defendant who has
a clear answer to the plaintiff which cannot be contradicted
to put up the evidence which constitutes the answer so that the proceedings
can
be summarily dismissed. The difference between an application to strike out the
claim and summary judgment is that strike-out
is usually determined on the
pleadings alone whereas summary judgment requires evidence. Summary judgment is
a judgment between the
parties on the dispute which operates as issue estoppel,
whereas if a pleading is struck out as untenable as a matter of law the
plaintiff is not precluded from bringing a further properly constituted
claim.
- [61] The
defendant has the onus of proving on the balance of probabilities that the
plaintiff cannot succeed. Usually summary judgment
for a defendant will arise
where the defendant can offer evidence which is a complete defence to the
plaintiff's claim. Examples,
cited in McGechan on Procedure at HR
136.09A, are where the wrong party has proceeded or where the claim is clearly
met by qualified privilege.
- [62] Application
for summary judgment will be inappropriate where there are disputed issues of
material fact or where material facts
need to be ascertained by the Court and
cannot confidently be concluded from affidavits. It may also be inappropriate
where ultimate
determination turns on a judgment only able to be properly
arrived at after a full hearing of the evidence. Summary judgment is suitable
for cases where abbreviated procedure and affidavit evidence will sufficiently
expose the facts and the legal issues. Although a
legal point may be as well
decided on summary judgment application as at trial if sufficiently clear
(Pemberton v Chappell [1986] NZCA 112; [1987] 1 NZLR 1), novel or developing points of
law may require the context provided by trial to provide the Court with
sufficient
perspective.
- [63] Except in
clear cases, such as a claim upon a simple debt where it is reasonable to expect
proof to be immediately available,
it will not be appropriate to decide by
summary procedure the sufficiency of the proof of the plaintiff's claim. That
would permit
a defendant, perhaps more in possession of the facts than the
plaintiff (as is not
uncommon where a plaintiff is the victim of deceit), to force on the
plaintiff’s case prematurely before completion of discovery
or other
interlocutory steps and before the plaintiff’s evidence can reasonably be
assembled.
- [64] The
defendant bears the onus of satisfying the Court that none of the claims can
succeed. It is not necessary for the plaintiff
to put up evidence at all
although, if the defendant supplies evidence which would satisfy the Court that
the claim cannot succeed,
a plaintiff will usually have to respond with credible
evidence of its own. Even then it is perhaps unhelpful to describe the effect
as
one where an onus is transferred. At the end of the day, the Court must be
satisfied that none of the claims can succeed. It is
not enough that they are
shown to have weaknesses. The assessment made by the Court on interlocutory
application is not one to be
arrived at on a fine balance of the available
evidence, such as is appropriate at trial.
- [19] This
passage was cited with approval by the Privy Council in Jones v
Attorney-General [2004] 1 NZLR 433 at 437.
Issues
[20] It is apparent from the background and the summary of the
pleadings that I have set out, that the plaintiffs seek to establish
a cause of
action in tort against the first defendant which involves matters which may well
have involved a cause of action in contract
against the company, Kenview Homes
Limited, from which the plaintiffs purchased the subject house.
- [21] Mr
Fardell summarised the specific issues. His summary, by and large, was accepted
by Mr Benvie for the purposes of the examination
I am now undertaking. That
summary provided:
- 6.1 Has the
first defendant demonstrated, on the balance of probabilities, that the
plaintiffs’ entire claim against him cannot
succeed?
- 6.2 Specifically,
and firstly, has the first defendant demonstrated that there is not, or is
unlikely to be, sufficient evidence
to establish an arguable case that there
exist any acts or omissions of the first defendant which have caused loss to the
plaintiffs?
- 6.3 Secondly, if
so, has the first defendant demonstrated that there is not, or is unlikely to
be, sufficient evidence to establish
an arguable case for the plaintiffs that
the first
defendant acted such as to incur a personal duty of care to the plaintiffs,
separate from Kenview, in respect of construction of
the subject dwelling and/or
supervision of that construction.
- Lastly,
does the pleading in the plaintiffs’ statement of claim disclose a
reasonable cause of action, namely the existence
and breach of a personal duty
of care, as distinct from any such duty on the part of Kenview, when merely
pleading inter alia that:
- 7.1 Kenview by
its agents and contractors constructed the subject dwelling.
- 7.2 At all
material times the first defendant was a director and agent of
Kenview.
- 7.3 The first
defendant personally undertook building work and supervised construction of the
subject dwelling thereby assuming a
personal duty of care to the
plaintiffs?
[22] This application puts in issue the liability in tort of a
shareholder/director of a company which has built a residential property,
to the
purchaser from the company of that residential property for defects in the
construction of it. The background which I have
outlined makes it plain that
there was no personal contact between the plaintiffs and the first defendant
prior to actual completion
of the house purchase. The contact only occurred in
relation to the completion of the special conditions and, I infer, in relation
to remedying faults, again pursuant to special condition 15. I will return later
in this judgment to a more detailed examination
of the evidence. It is
important, however, before doing so to examine the principles which are relevant
and which should be applied
in determining whether the first defendant owed the
duty of care contended for.
The test for imposing a duty of care
- [23] The Court
of Appeal in Rolls Royce New Zealand Ltd v Carter Holt Harvey Ltd
CA259/02 23 June 2004 examined this issue. At [58] – [65] the Court
said:
- [58] The
ultimate question when deciding whether a duty of care should be recognised in
New Zealand is whether, in the light of all
the circumstances of the case, it is
just and reasonable that such a duty be imposed. The focus is on two broad
fields of inquiry
but these provide only a framework rather than a
straightjacket. The first area of inquiry is as to the degree of proximity or
relationship
between the parties. The second is whether there are other wider
policy
considerations that tend to negative or restrict or
strengthen the existence of a duty in the particular class of case. At this
second stage, the court’s inquiry is concerned with the effect of the
recognition of a duty on other legal duties and, more
generally, on society. See
South Pacific Manufacturing Co Ltd v New Zealand Security Consultants &
Investigations Ltd[1991] NZCA 551; [1992] 2 NZLR 282, 293-294 (Cooke P), 305-306 (Richardson
J), 312 (Casey J), 316-318 (Hardie Boys J) and Attorney-General v
Carter[2003] 2 NZLR 169 at paras [22] and [30].
- [59] The inquiry
into proximity is concerned with the nature of the relationship between the
parties and is more than a simple question
of foreseeability. It involves
consideration of the degree of analogy with cases in which duties are already
established. This is
because courts should only move gradually into new areas of
liability and also because the examination of factors that have influenced
earlier decisions ensures that any development of the law occurs in a principled
and cohesive manner – Connell v Odlum [1992] NZCA 256; [1993] 2 NZLR 257,
265.
- [60] The
proximity inquiry can be seen as reflecting a balancing of the plaintiff’s
moral claim to compensation for avoidable
harm and the defendant’s moral
claim to be protected from undue restrictions on its freedom of action and from
an undue burden
of legal responsibility. That necessarily involves a
consideration of how close the nexus is between the defendant’s alleged
negligence and the plaintiff’s loss and the degree of harm to the
plaintiff. It also involves considering the burden on the
defendant of taking
precautions against the risk and also whether the consequences to the defendant
may be out of proportion to its
fault - see South Pacific Manufacturing
at 306-308 Richardson J, Stephen Todd (ed) The Law of Torts in New
Zealand(3ed, 2001) 142-151 and John A Smillie “ The Foundation of the
Duty of Care in Negligence” [1989] MonashULawRw 18; (1989) 15 Monash UL Rev 302, 328-330. As
Cardozo CJ said in the oft-cited case of Ultramares Corporation v Touche,
Niven & Co174 NE 441, 444 (NY,1931), the courts are concerned to limit
the risk of exposing defendants to “ a liability in an indeterminate
amount for an indeterminate time to an indeterminate class".
- [61] The extent
to which those in the plaintiff’s position are vulnerable can also be
taken into account. The inquiry may in
this case concentrate on whether a
defendant with special skills has power over a vulnerable plaintiff - see
South Pacific Manufacturingat 296 (Cooke P), 307 (Richardson J) and 317
(Hardie Boys J), Professor Smillie in “ Negligence and Economic
Loss” (1982)
32 U Toronto LJ 231, 236 and Professor Jane Stapleton,
“ Duty of Care Factors: a Selection from the Judicial Menus”
in Peter Cane and Jane Stapleton (eds) The Law of Obligations: Essays in
Celebration of John Flemin(g1998) 59, 79-81. That vulnerability is a
key factor in determining liability was recently noted by the High Court of
Australia in
Woolcock Street Investments Pty Ltd v CDG Pty Ltd [2004] HCA
16 – see the majority judgment at paras 23-24 and McHugh J’s
concurring judgment at paras 80-86, although that factor was
thought to be of
lesser importance in the other concurring judgment of Callinan J (para
224).
- [62] Whether
there are or could realistically have been other remedies for a plaintiff is
relevant to the assessment of vulnerability.
If there are, then this may point
to there having been adequate means for the plaintiff to protect itself and to
there being adequate
deterrence for the defendant - see Jane Stapleton
“Duty of Care: Peripheral Parties and Alternative Opportunities for
Deterrence”
(1995) 111 LQR 301 and the explicit application of this
principle by Richardson J in South Pacific Manufacturingat 308-309.
Professor Todd considers that the focus should be on what steps a person could
reasonably have taken to look after his
or her interests and, in commercial
cases, includes the consideration of bargaining power and market reality –
see Stephen
Todd “A Methodology of Duty” (High Court of Australia
Centenary Conference, Canberra, 11 October 2003) at 12.
- [63] The nature
of the loss can also be taken into account. The courts have been less willing
to impose a duty of care in cases of
economic loss than where there is physical
damage to property or, in jurisdictions other than New Zealand with its accident
compensation
regime, physical injury. As McHugh J explained in Perre v Apand
[1999] HCA 36; (1999) 198 CLR 180, 213-214 this is because claims for economic loss may
result in mere transfers of wealth, so that one person’s
loss is another
gain, whereas harm to a person or property involves a net loss to social wealth.
See also McHugh J’s recent
remarks in Woolcock Street Investments Pty
Ltd v CDG Pty Ltd [2004] HCA 16 at para 21 and Stephen Todd “A
Methodology of Duty” (High Court of Australia Centenary Conference,
Canberra, 11 October
2003) at 10.
- [64] The
statutory and contractual background may also be relevant in defining the
relationship between the parties and can point,
depending on the circumstances,
both towards and away from a finding of proximity. The statutory and contractual
background can raise
wider policy issues and thus the boundary between proximity
and policy can merge. The two stage approach is, however, only a framework
and
no presumptions, rebuttable or otherwise, arise at any stage of the inquiry.
This means that the important object is that all
relevant factors are properly
weighed, not the stage of the inquiry at which they are taken into account
– see the remarks
of Cooke P in South Pacific Manufacturingat 294
and Tipping J in Attorney-General v Carter at 169-170, para 30.
- [65] For
example, in Price Waterhouse v Kwan[2000] NZLR 39, 41 para 6 Tipping J
considered the relevant legislative environment to be of considerable relevance
to the issues
of both proximity and policy and, in South Pacific
Manufacturing,all of the Judges considered that the existence of contractual
remedies against the insurer militated against there being a duty of
care. Casey
J, at 314, treated this factor as being a factor pointing against there being
the requisite degree of proximity. Hardie
Boys J, at 318-319, said that the
existence of alternative remedies was a factor that could point against
proximity being present
but in fact dealt with the contractual remedy against
the insurer as a policy consideration weighing against the imposition of a
duty,
as did all the other Judges. Cooke P, however, (at 301) also referred to the
contractual structure in his discussion of proximity,
approving of the reasoning
in Simaan.
[24] When discussing the case law, the Court considered the
cases involving liability to subsequent owners of domestic dwellings and
said at
[71]:
Liability to subsequent owners of domestic dwellings
for defects in such dwellings has, however, long been a feature of New Zealand
case law, since Bowen v Paramount Builders (Hamilton) Ltd[1977] 1 NZLR
394. This position was upheld by the Privy Council in Invercargill City
Council v Hamlin[1996] 1 NZLR 513, despite a special seven judge panel of
the House of Lords in Murphy v Brentwood District Council[1991] UKHL 2; [1991] 1 AC 398,
retreating from its earlier decisions and denying liability in a similar case.
These cases involved the liability
of a council but it was assumed that the
liability of the builder would have been no less extensive.
And at [73]:
Liability of a professional builder to a subsequent
owner of a domestic dwelling has been upheld in Australia – see Bryan v
Maloney(1995) 182 CLR 690.
[25] The Court next considered a distinction that had been
drawn in some of the cases between commercial and domestic buildings and
noted
that that was not favoured because of difficulty of definition. The Court next
looked at the position in the United States
noting that there was no uniform
position. It also reviewed the Canadian authority and then gave consideration to
the position in
England. The Court noted that the decision Simaan General
Contracting Co v Pilkington Glass Ltd (No 2) [1988] EWCA Civ 15; [1988] 1 QB 758 (CA) had been
widely approved both in New Zealand and in the United Kingdom: [84]. In that
case the Court of Appeal
rejected a claim by the main contractor in tort against
the nominated supplier to a subcontractor for economic loss occasioned by
defects in the quality of the goods supplied, namely the glass.
- [26] The
Court considered the concept of assumption of responsibility and observed at
[100] that:
assumption of responsibility for the task cannot be sufficient in itself, at
least in so far as the negligent construction cases
are concerned. If it were,
then the result in Simaan (which has been so widely approved) could not
be justified, as the subcontractor in that case had clearly assumed
responsibility for
the task of supplying glass that accorded with the
contractual specifications.
[27] The question in Simaan was whether:
the subcontractor had assumed responsibility to the
plaintiffs and the answer given in the case, although not expressed in that
manner,
was that it had not. Any assumption of responsibility was only to the
direct contracting party.
[28] The position of company directors in respect of personal
liability for negligence, must be specifically considered. The Court
of Appeal
had to consider the position in Trevor Ivory Ltd v Anderson [1992] 2 NZLR
571.
- [29] Mr
Fardell helpfully summarised the position in his memorandum, which I
adopt.
- Recognising
the allegations of negligence against company directors involve the usual
general inquiry into the existence of a duty
of care, Hardie-Boys J then
explained the relevance of a company’s separate legal personality to this
field of inquiry (p527):
An agent is in general personally liable for his own tortious acts: Bowstead
on Agency (15th ed, 1985) at p 490. But one cannot from that conclude that
whenever a company's liability in tort arises through the act or
omission of a
director, he, because he must be either an agent or an employee, will be
primarily liable, and the company liable only
vicariously. In the area of
negligence, what must always first be determined is the existence of a duty of
care. As is always so
in such an inquiry, it is a matter of fact and degree, and
a balancing of policy considerations. In the policy area, I find no difficulty
in the imposition of personal liability on a director in appropriate
circumstances. To make a director liable for his personal negligence
does not in
my opinion run counter to the purposes and effect of incorporation.
He continues:
What does run counter to the purposes and effect of incorporation is a failure
to recognise the two capacities in which directors
may act; that in appropriate
circumstances they are to be identified with the company itself, so that their
acts are in truth the
company's acts. Indeed I consider that the nature of
corporate personality requires that this identification normally be the basic
premise and that clear evidence be needed to displace it with a finding that a
director is acting not as the company but as the company's
agent or servant in a
way that renders him personally liable.
... Essentially, I think the test is, or at least includes, whether there has
been an assumption of responsibility, actual or imputed.
- Earlier
in the judgment, His Honour expanded on this ‘identification’
question (p256):
To described a director as the agent of the company can be deceptive. It is a
useful description, for a corporation, being an "abstraction"
(per Lord Haldane
in Lennard’s Carrying Co Ltd v Asiatic Petroleum Co Ltd [1915] AC
705), cannot of itself think, resolve or act, but does so through its directors.
In that sense they are certainly agents;
but in the popular rather than the
strictly legal sense of the word. It is not the case that they are always agents
in the legal
sense. The concept of corporate personality means that for some
purposes the directors and the company are one.
- In
the same judgment the President made the same points as Hardie- Boys J and went
so far as to say that, in the context of dealings
with third parties, if a
person is identified with a company vis-à-vis third parties, it is
reasonable that prima facie the
company should be the only party liable: Cooke P
at p 520.
- He
qualified his point by adding that an officer or servant of a company may in the
course of activities on behalf of the company
come under a personal duty to a
third party: Ibid, lines 20-26.
- However,
His Honour at p 520, lines 40-52, cited Nourse J in White Horse Distillers
Limited v Gregson Associates Limited [1984] RPC 61 at 92, and later in
his judgment (p 523, line 48) expresses agreement with this quotation:
‘it would seem to be irrational that there should be personal liability
merely because the director expressly or impliedly
directs or procures the
commission of the tortious act or conduct. In the extreme, but familiar, example
of the one- man company,
that would go near to imposing personal liability in
every case. As for deliberateness or recklessness and knowledge or means of
knowledge that the act or conduct is likely to be tortious, I think that these
may on examination be found to be no more than characteristic,
perhaps
essential, elements in the director's making the act or conduct his
own.’
- Relevant
to the proximity enquiry, and most particularly to policy factors militating
against the existence of a duty of care, His
Honour concluded, at
p524:
Lines 20-25:
if an economic loss claim depends on establishing a personal duty of care, it is
especially important to consider how far the duty
asserted would cut across
patterns of law evolved over the years in the process of balancing interests.
Lines 28-29:
In the instant case it is patent that the object of Mr Ivory in forming a
limited liability company, an object encouraged by long-established
legislative
policy, would be undermined by imposing personal liability.
Lines 31-37:
I commit myself to the opinion that, when he formed his company, Mr Ivory made
it plain to all the world that limited liability was
intended. Possibly the
plaintiffs gave little thought to that in entering into the consultancy
contract; but such a limitation is
a common fact of business and, in relation to
economic loss and duties of care, the consequences should in my view be accepted
in
the absence of special circumstances. It is not to be doubted that, in
relation to an obligation to give careful and skilful advice,
the owner of a
one-man company may assume personal responsibility. Fairline is an
analogy. But it seems to me that something special is required to justify
putting a case in that class.
[30] Mr Fardell noted that Trevor Ivory had been followed on
numerous occasions. He drew attention to the article by Neil Campbell,
Leaking
Homes, Leaking Companies [2002] CSLB 101 and the suggestion that the Courts, on
occasions, have misapplied Trevor Ivory.
Again, in a helpful summary, he
referred to decisions where he submitted the Trevor Ivory decision had been
correctly applied.
- 31.1 Mahon
v Crockett [1999] NZCA 374; (1999) 8 NZCLC 262,043 – a successful appeal to the Court
of Appeal by a defendant director of several construction and development
companies in regard to judgment against him on claims that he was personally
liable to pay commissions to the plaintiff. The Court
of Appeal considered that
there was a requirement for a clear establishment of an assumption of personal
liability on the part of
the director, as distinct from the companies or
corporate entities which he controlled, and the evidence did not justify the
conclusion
that the director was personally liable.
- 31.2 O’Sullivan
v New Zealand Ostriches (2000) 14 PRNZ 593 – the plaintiffs
unsuccessfully applied to join the defendant company’s director to the
proceeding,
on their allegation that the director owed them a duty of care and
was negligent in setting up, and managing the defendant company’s
ostrich
breeding operation. The plaintiffs had contracted with the company; the
plaintiffs’ ostriches to be agisted at the
company’s ostrich farm,
of which it was alleged that the director was the ‘promoter and
controller’. The application
was declined because the evidence produced
did not support the cause of action against the director, as it fell well short
of establishing
grounds to allege the existence of a duty of care. Potter J
acknowledged that personal liability may be imposed on a company director
in
appropriate circumstances, but it was always necessary to distinguish between
acting in the capacity of a company director and
one’s personal capacity.
It was considered relevant that the director had had not contact with the
plaintiffs at any material
time.
- 31.3 Plypac
Industries Ltd v Marsh (1998) 8 NZCLC – the defendant director
successfully applied for an order striking out the plaintiff’s claim
against him
as disclosing no reasonable cause of action. The plaintiff had
earlier obtained judgment against the director’s company (which
was
subsequently placed into liquidation) on the company’s failure to fulfil
its obligations under a contract with the plaintiff
to design and supply
machinery, and to provide evidence of a current professional indemnity policy.
The plaintiff alleged against
the director a breach of duty of care which it
said the director owed to the company and to itself to make full and accurate
statements
to the company’s insurer, to correctly inform the plaintiff
that appropriate insurance had been obtained, and to ensure that
the company
acted prudently and properly in its dealings with its insurer once the
plaintiff’s claim had been lodged with the
company. In the course of
holding that a director on behalf of a company assumes a personal duty of care
to the company’s client
where special circumstances are shown, which were
not present in this case, and in holding that the only duty owed by the director
was to the company and not to the plaintiff, Master Venning (as he then was)
observed:
(a) the New Zealand authorities dealing with assumption of a personal duty of
care by company directors (including Trevor Ivory and Brookes v New
Zealand Guardian Trust), make it clear that special circumstances must be
shown for the imposition of such a duty of care, and those were not present on
facts in the present case: p 261, 716.
(b) Cooke P’s comments in Trevor Ivory at p 524 were apposite
concerning the director making it plain to all the world that limited liability
was intended, and that this
should be accepted in the absence of ‘special
circumstances’: p 261, 718.
(c) Similarly, there were no circumstances present in Plypac to elevate
the plaintiff’s claim against the director into one of those classes.
Indeed, the plaintiff was apparently concerned
not to rely so much on the
director but addressed its concern solely to the company: Ibid.
(d) Policy considerations pointed against the imposition of a duty: to impose a
duty on a director in the Plypac case would be equivalent to placing the
director in the shoes of an insurer for parties dealing with the company. The
plaintiff and the
company were free, as are other parties to commercial
contracts, to regulate their affairs by contract and to determine the extent
of
the obligations they had to each other: p 261, 719.
- 31.4 Banfield
v Johnson (1994) 7 NZCLC 260,496 – an unsuccessful strike out
application by the director of a building company which had contracted with
the
plaintiff to construct motels. Thorpe J considered the judgements of Cooke P and
Hardie-Boys J in Trevor Ivory and accepted counsel for the
applicant’s submission that, in situations where plaintiffs pursue a claim
in negligence against
the director of a company with which they have been
dealing, ‘a special
case must be established’: p 260, 498. However, recognising the
limitations of the Court’s jurisdiction under HCR 186, and having regard
to the further
particulars provided to the Court in that case in a draft amended
statement of claim, His Honour was satisfied that the respondent
had pointed to
further particulars which were sufficient to require the material facts to be
determined at trial.
[31] Mr Benvie did not take issue with Mr Fardell’s
summary. He drew attention to the following:
a) The duty alleged is a duty to take reasonable care
to ensure that the building work was undertaken in accordance with good
workmanlike
practises and in accordance with the requirements of the New Zealand
Building Code;
b) The fact that a developer delegates the task of building to others does not
relieve the developer of this duty: Mount Albert City Council v Johnson
[1979] NZCA 46; [1979] 2 NZLR 234, 240-241; and
- A
director (or any person or entity acting as agent of the company) can be subject
to a personal duty of care in respect of defective
construction. Two cases
illustrate this: Morton v Douglas Homes Ltd [1984] 2 NZLR 595 and
Callaghan v Robert Ronayne Ltd [1979] NZHC 141; (1979) 1 NZCPR 98.
[32] It is appropriate to record the position of the directors
in Morton. They were the sole individuals who were armed with knowledge
of
important engineering requirements. They assumed control of the process of
constructing the foundations in the absence of any
other party doing so. This
situation was found to create an assumption of personal responsibility and was
the basis upon which liability
was founded. That was specifically observed to be
the position by Cooke P in Trevor Ivory at 523. For reasons which will become
apparent
when I consider the facts in more detail, that situation does not apply
in the instant case.
- [33] In
Callaghan Speight J had to consider a claim against the directors of a
development company. He found that the directors had no personal involvement
in
the building work and thus were not liable. Although that case recognises
the
possibility of a claim against the directors, its factual
circumstances do not assist the plaintiffs in this case.
- [34] I wish to
add yet a further comment on the issue of assumption of responsibility. In the
editorial article by Neil Campbell,
Leaking Homes, Leaking Companies the
author submits that cases subsequent to Trevor Ivory had misconstrued the
requirement that a defendant has assumed responsibility by expanding it to cases
where such an element is not
an element of the actual cause of action.
- [35] Mr Fardell
submitted that that statement goes too far in endeavouring to restrict the
relevance of the assumption of responsibility
inquiry. That is because the
phrase is used in more than one sense. It is relevant to the broader proximity
inquiry in the much wider
class of negligence cases where a duty of care is
asserted against some party other than the party with whom the plaintiff had,
primarily,
been dealing with. In this case, of course, that is the company. Mr
Fardell drew attention to the different senses in which the phrase
is used,
something which was acknowledged by Glazebrook J in Rolls Royce at [96] -
[98].
- [36] Mr Fardell
also drew attention to the fact that the need to consider whether there has been
an express, imputed or imposed assumption
of responsibility was noted in a
number of authorities. As well as those set out at [30], he mentioned the
following.
- [37] In South
Pacific Manufacturing Co Ltd v New Zealand Security Consultants and
Investigations Ltd [1991] NZCA 551; [1992] 2 NZLR 282 at 307 Richardson J said:
Finally, viewed simply in terms of proximity there is a clear parallel with two
categories of cases where a duty of care has been
recognised. One is the duty
owed by a solicitor to a designated beneficiary under a will where the solicitor
has accepted instructions
to prepare the will for execution but has failed to do
so before the testatrix died (Gartside v Sheffield, Young & Ellis
[1983] NZCA 37; [1983] NZLR 37). The other is the duty owed by a receiver appointed by a
debenture holder to the holder of a subordinate security,
the value of which is
adversely affected by the conduct of the receiver (First City Corporation Ltd
v Downsview Nominees Ltd [1990] NZCA 21; [1990] 3 NZLR 265). In those two cases, as here,
the defendant assumes a responsibility to act carefully in undertaking an
activity;
in each there is a similar dependence and power relation between the
plaintiff and the defendant; in each there is a high degree
of likelihood
that careless performance of that responsibility will cause harm to the
plaintiff.
- [38] In
Simaan Bingham LJ said at 781:
Where a specialist sub-contractor is vetted, selected and nominated by a
building owner it may be possible to conclude (as in the
Junior Books
case [1982] UKHL 4; [1983] 1 AC 520) that the nominated sub-contractor has assumed a direct
responsibility to the building owner ... I do not, however,
see any basis on
which the defendants could be said to have assumed a direct responsibility for
the quality of the goods to the plaintiffs:
such a responsibility is, I think
inconsistent with the structure of the contract that the parties have chosen to
make.
[39] In Plypac Master Venning, as he then was, also noted the
need to determine whether there has been an assumption of responsibility
by the
agent of the company to the client. The company was, of course, required to
obtain the insurance cover.
- [40] For
present purposes it is only necessary to make two points as to the scope of the
assumption of responsibility requirement.
- [41] First,
where the liability of directors for breach of a personal duty of care in
negligence is at issue, whether there has been
a personal assumption of
responsibility has particular prominence as the focus of the enquiry, as held in
Trevor Ivory. This extends to cases involving directors’ liability
for defective buildings. At 523 Cooke P referred to Morton, which
involved precisely this situation, and accepted that:
on the particular facts there was an assumption of responsibility.
[42] Secondly, the case law subsequent to Trevor Ivory referred
to by Mr Fardell (as set out at [30]), has affirmed personal assumption
of
responsibility as a requirement of directors’ personal liability in
respect of a variety of duties of care. Notably, in
Mahon v Crockett [1999] NZCA 374; (1999) 8
NZCLC 262,043, the Court of Appeal acknowledged at [9]-[12] that the requirement
of assumption of responsibility, as articulated
in Trevor Ivory, generally
applies to tortious causes of action against directors.
- [43] Assumption
of responsibility in negligent construction cases in respect of the task
undertaken, is not, by itself sufficient
to ground liability. There must be
something further as was explained by Glazebook J in Rolls Royce at
[100].
- [44] I now
return to the specific facts. For the purposes of determining whether there is
the necessary proximity or relationship
between the parties to justify the
existence of the duty of care pleaded, the following points are
relevant:
a) The land on which the house was built was, at all material times, owned by
the company, Kenview Homes Limited;
b) The company applied for and obtained the building consent for the house which
is the subject of this claim;
- The
company ordered and paid for all materials required for the erection of the
house;
d) The company alone contracted with all trades personnel, ie plumbers,
painters, electricians, etc in respect of the building of
the house;
e) The first defendant was not directly involved in the erection of those parts
of the building which are the subject of the complaint.
They were: the fixing of
the cladding, the erection of the external joinery, the construction of the
roof, and the assembly of the
structural framing timbers;
f) The first defendant’s only involvement, accepting without challenge for
the purpose of this application the evidence advanced
by the plaintiffs, was:
- Co-ordinating
the supply of materials and making payment using the company’s resources
for them;
- Arranging
on the company’s behalf for the preparation of plans, the supply of plans
to engineers for checking and
certifying, and the passing of plans
to material suppliers and the trades people who were to carry out the work;
- Completing
on the company’s behalf all matters relating to the building consent. I do
not overlook that one of the forms, the
notice of completion, refers to the
applicant as the first defendant. That is a document forwarded to the Council.
It was obviously
treated by the Council as a notice on behalf of the company and
nobody else;
- Co-ordinating
the supply of materials and paying for same, paying the tradespersons concerned:
all steps undertaken specifically on
the company’s behalf and using the
company’s funds;
- The
evidence of Mr Dent, a neighbour, that:
Peter was definitely ‘hands on’ doing building work until the
framing of the house was put up by other workmen. I saw
Peter digging holes when
the foundation work was being done.
It is significant that none of this work has any bearing on the
areas of complaint that I have earlier made reference to;
- On
the evidence of Mr Simpson, another neighbour, there is reference to the first
defendant directing the operations of an excavator.
Again, there is no specific
evidence of involvement in the areas of construction about which complaint is
made. There is reference
to a discussion concerning leaky buildings but I fail
to see how that specifically adds anything which might found a ground for
finding
a duty in favour of the plaintiffs owed by the first
defendant;
- The
plaintiff, Mrs Drillien, observed that subsequent to the purchase, the first
defendant was involved in the clearing of
drains, repairing a
driveway and, of course, attending to the special conditions. It is difficult to
see how any of that evidence,
however, could found the basis for the duty sought
to be imposed. None of it relates to the work that is the subject of the
complaint.
None of it involves the period in time when the house was being
built.
- [45] No
allegation is made anywhere of direct personal involvement by the first
defendant in the specific areas where complaint is
made. His position can be
contrasted with those directors found liable in Morton. Those directors
were found liable only in respect of the specific areas where they had direct
involvement and, therefore, responsibility.
Even if one ignored the issue of
assumption of responsibility, what is evident on the facts before me is that,
viewed as action taken
by an agent, the first defendant has not, in fact,
carried out the specific tasks which are said to have caused the loss. Further,
I can find no foundation which would suggest that the first defendant was, in
reality, himself the builder or developer in this
case. The facts that I have
listed above simply disclose that that is not the case.
- [46] The
plaintiffs entered into a contract with a company which contained specific
warranties and obligations to be carried out by
the company which owned the
property concerned and which, as I have outlined above, was the developer and
builder.
- [47] The
tradespeople involved, the plumbers, the painters, the electricians, have all
confirmed the first defendant’s account
that he was not involved in the
specific areas which are the subject of complaint in the statement of claim. The
contract was with
the company. That reinforces the view that I have expressed,
that there is simply no foundation in this case for the proposition
that the
defendant was either the builder or the developer of the house
concerned.
- [48] In summary,
there is no evidence to suggest that the first defendant was directly
responsible for the work which is said to be
defective and which leads to the
plaintiffs’ claim. The builder of the house concerned and the developer of
the property were
clearly the company and not the first
defendant.
Conclusions
- [49] I am
satisfied that the evidence discloses that the cause of action pleaded against
the first defendant cannot succeed. All of
the requirements for the entry of
summary judgment in favour of the first defendant which are referred to in the
Court of Appeal’s
judgment in Westpac and to which I referred in
[18] of this judgment are met by the first defendant. Accordingly I enter
summary judgment for the first
defendant.
Judgment
- [50] Judgment is
entered in favour of the first defendant in respect of the plaintiffs’
claim against the first defendant.
Costs
- [51] Normally
costs follow the event. If counsel cannot agree memoranda in support, opposition
and reply shall be filed and served
at seven-day intervals. The Registrar shall
refer same to me when all have been filed for decision if required.
Future of this case
- [52] I schedule
a case management conference by telephone with counsel at 10.10am on 22 March
2005. It will deal with:
a) Any matter arising out of the pleadings as a result of this judgment;
b) Any outstanding interlocutory matter;
- Settlement;
d) Service in respect of the second defendant;
e) Trial time required, the fixing of a trial date, a setting down date and the
making of any trial directions which are appropriate.
Counsel shall file and serve memoranda dealing with these items two working
days before the conference.
JA Faire Associate Judge
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2005/1840.html