|
Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 26 January 2018
For a Court ready (fee required) version please follow this link
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2010-404-003231 [2012] NZHC 1695
BETWEEN GHP PILING LIMITED Plaintiff
AND LEIGHTON CONTRACTORS PTY LIMITED
First Defendant
AND DOWNER EDI WORKS LIMITED Second Defendant
Hearing: 11-15 June 2012
Counsel: SJB O'Brien and RP Chandra for Plaintiff
CJ Booth and ACF Lee for Defendants
Judgment: 13 July 2012
JUDGMENT OF ASHER J
This judgment was delivered by me on Friday, 13 July 2012 at 5pm pursuant
to r 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Solicitors/Counsel:
Fortune Manning, DX CP 21503, Auckland 1140.
Email: sarah.obrien@fortunemanning.co.nz and Rachael.chandra@fortunemanning.co.nz
Kensington Swan, DX CP 22001, Auckland 1142.
Email: chris.booth@kensingtonswan.com
and anita.lee@kensingtonswan.com
GHP PILING LT V LEIGHTON CONTRACTORS PTY LTD HC AK CIV-2010-404-003231 [13 July 2012]
Table of Contents
Para No
Introduction [1] The claim [22] Was there a preliminary contract? [27] Commercial background [39] The request for tender document [42] The response [45] Discussion of the “offer” [49] Discussion of the “acceptance” [62] Comparison with other processes [67] Conclusion [74]
Damages
Introduction [75]
The add-back of the contingency sum [85]
Analysis of damages claimed
The add-back of half the contingency figure [91]
The oscillators [94] On-site management [97] Financing costs [98] Off-site overheads [99] Overview [101]
Result [106]
Costs
[107]
Introduction
[1] The plaintiff, in response to an invitation from the defendants,
submitted a tender for a significant piling contract.
The plaintiff
claims that a preliminary contract was created by this exchange requiring the
defendants to deal only with those
who made offers in accordance with the
procedure specified in the invitation. The plaintiff claims that the
defendants, in
awarding the contract to another contractor, did not follow
that procedure and breached the preliminary contract. It claims
significant
damages arising from the loss of its chance to gain a profit on the
job.
[2] The defendants deny that a preliminary contract was created or that they were bound to follow any particular procedure. They further dispute the quantum of damages.
[3] While the exact events that related to the creation of the alleged
contract will need to be examined closely, the broad
facts may be stated quite
briefly.
[4] The plaintiff, GHP Piling Ltd (“GHP”), is a specialist
piler practising in Auckland and has been in business
since 1944. Its core
business has been civil construction. John Colborne Yonge is one of two
directors and the managing
director. Mr Yonge has been employed by
GHP since 1983 and has been its managing director since 1987.
[5] On 26 June 2006 a joint venture known as “Leighton
Works” contracted with Transit New Zealand (“Transit”)
which is part of the New Zealand Transport Agency, on behalf of
Ontrack for the construction of a four lane motorway
in Manukau linking
State Highway 1 to State Highway 20. The two principals of Leighton Works are
Leighton Contractors Pty Ltd and
Downer EDi Works Ltd (now called Downer New
Zealand Ltd). The contract between Leighton Works and Transit will be
referred
to as the head contract.
[6] The head contract included the Manukau Rail Link enabling works
(“the Ontrack variation”). Those works involved
earth works
which would enable a railway track to be laid parallel to the new motorway in
the future. The decision was made
by Transit New Zealand to give the Ontrack
variation works to Leighton Works. They were to get that work without a
further competitive
tender in relation to the new works, but this was subject to
the agreement of price. Leighton Works had to keep Transit involved
in the
Ontrack works and obtain Transit approval to prices and subcontractors’
prices.
[7] Part of the Ontrack variation included piling works and the
construction of secant pile walls. Piling works are the initial
works that are
undertaken in a major construction which involves the provision of foundations
and retaining.
[8] In February 2009 Leighton Works sought prices and information from GHP in respect of two different piling options for the Manukau rail link station box; a ground anchor design and a sheet pile design. GHP quoted on those options, but ultimately they were not proceeded with. In early April 2009 the decision had been
made by Leighton Works against sheet piling and ground anchor options in
favour of a secant piling solution.
[9] In April 2009 Leighton Works started to consider a piling
wall solution known as secant piling. Secant piling
involves bored tiles which
are intersected, to be used primarily as a waterproof ground retention wall. A
series of piles are drilled
and constructed out of weaker concrete without
reinforcement and drilling rigs are used to drill down between those softer
piles
to create a space for “hard” piles to be constructed between
them. The hard piles are filled with reinforced concrete
and intersect the
soft piles.
[10] Neil Craig Kelly is an estimator employed by Leighton Contractors
Pty Ltd, one of the two joint venturers. He was the lead
estimator for the
Manukau rail link price negotiation on the State Highway contract and the
railway station variation. He took the
lead role for Leighton Works in seeking
tenders for the piling for the Manukau rail link enabling works.
[11] Initially, following the decision not to proceed with sheet piling
or ground anchors, Mr Kelly had been unaware that GHP
had the capability to
undertake secant piling, but Mr Yonge informed him that it could. On 7 April
2009 Mr Kelly sent to GHP and
two other companies, Civil Works Ltd/Seatek and
Hauraki Piling Ltd (“Hauraki Piling”), a set of preliminary drawings
and ground condition parameters for the secant piling options. The information
was also sent to two other companies. Mr Kelly was
seeking indicative
costs.
[12] On 15 April 2009 GHP submitted various secant piling alternative
concepts. On 4 May 2009 Mr Stewart informed the potential
contractors that a
final secant pile design had been provided by the designer. The phrase that he
used was “the [d]esign has
landed ...”.
[13] On 7 May 2009 a document which may be called neutrally a “request for tenders” document was sent by Leighton Works to various contractors who included GHP, Hauraki Piling, Civil Works/Seatek, Contract Landscapes Ltd and Hiway Stabilizers Environmental Ltd. GHP submits that this was the offer in the
preliminary contract. On 7 May 2009 the time for filing for GHP to provide
the tender return was extended to 12 May 2009. On 11
May 2009 a revised
enquiry document with a revised tender return date of 19 May 2009 was
circulated.
[14] A tender submission was then provided by GHP on 20 May 2009. GHP
submits that this was the acceptance of the offer, and
resulted in there being a
preliminary contract. The quote was for $9,467,123 for a two rig, 22 week
option, and $9,892,153 for a
three rig, 15 week option. In addition, there were
two prices for hold down piles of $276,250 and $349,050. Contract Landscapes
filed their tender on 19 May, Hauraki Piling on 20 May, Civil Works/Seatek on
21/22 May and a revised offer was put in by Hauraki
Piling on 22 May
2009.
[15] On 22 May 2009 Leighton Works had a tender review meeting in which
the piling subcontractors were discussed. At that point
the possibility was
raised of checking prices with another piling contractor Brian Perry Civil
(“Brian Perry”). Brian
Perry was part of Fletcher Construction Co
Ltd which itself was a competitor in New Zealand and Australia with the partners
of Leighton
Works. Brian Perry had not, up to that point, been invited to
provide a tender.
[16] Leighton Works held meetings with the piling contractors in
contention. It is common ground that GHP was the lead bidder.
[17] At some stage at around 23 May 2009, Transit’s consultants
indicated that they would have preferred more candidates
for the secant piling
subcontract in line with their best value for money approach. They asked if
Leighton Works had considered
requesting a price from Brian Perry. When they
were told that such a request had not been made, the consultants recommended
that
Leighton Works consider requesting a quotation from Brian
Perry.
[18] On 25 May 2009 Mr Kelly became aware that there had been a discussion between the New Zealand manager of Leighton Contractors Pty Ltd and Andrew Drummond of Brian Perry. He sent a copy of the request for tenders document and supporting information to Brian Perry on 25 May 2009. There were then various
exchanges between Mr Kelly and GHP and the other parties that had submitted
quotes.
[19] On 17 June 2009 GHP submitted a revised price which was considerably reduced, following a request to do so by Mr Kelly. The quote was reduced to
$8,455,523 for a two rig, 22 week option, and $9,397,153 for a three rig, 15
week option. There was no change to the hold down pile
option.
[20] On 17 June 2009 Brian Perry submitted a tender for the secant piling
for
$6,035,253, some $2,700,000 cheaper than GHP’s revised tender. On 22
June 2009 there was a Leighton Works internal email
indicating that Brian
Perry was the preferred subcontractor for the work. However, there were still
communications going on
with GHP. At between 24 June and 28 July 2009, a
standard form of subcontract was sent to Brian Perry. A revised quotation was
sought from Brian Perry on 6 July 2009. In the meantime GHP had been following
up inquiries from Mr Kelly as to progress.
[21] On 2 October 2009 Brian Perry entered into the secant piling
subcontract with Leighton Works. Its final tender price was
$7,466,947.66. GHP
had failed to get the job. After correspondence it issued these
proceedings.
The claim
[22] GHP asserts that the 7 May 2009 request by Leighton Works (revised
on
11 May 2009) for tenders and the submission of a conforming tender on 20
May
2009 constituted an offer and acceptance creating a preliminary agreement.
It claims that Leighton Works was bound to conduct the
evaluation process in
accordance with the terms and procedure expressed in the request for tender, and
that Leighton Works was bound
to deal with tenderers in a fair, equal and
equitable fashion. It asserts that the preliminary agreements contained the
following
implied terms:
(a) that Leighton Works would act fairly and equally in its decision as to which party would be awarded the tender;
(b) that only tenders submitted in accordance with the requirements of
the tender documents would be considered; and
(c) that Leighton Works in evaluating the tenders were bound by the
terms they had imposed as well as by the requirements of
fairness and
equity.
[23] They assert that Leighton Works breached those implied terms
by:
(a) considering a non-conforming and later tender from Brian
Perry;
(b) dealing with Brian Perry in preference to GHP and Hauraki Piling;
and
(c) misrepresenting to GHP that it was dealing with GHP and Hauraki
Piling only.
[24] GHP claims that as a consequence of these breaches it suffered a loss of profit. It claims that GHP would have realised a profit of $884,820 plus half of the contingency allowance being $147,854, the total claim for damages being
$1,032,674.
[25] Leighton Works responded that the request for tenders document
issued on
7 May 2009 was no more and no less than an invitation to treat by which GHP,
along with other piling subcontractors, was invited to
submit a quotation
without any contractual obligation arising. They say alternatively that, even
if the Leighton Works request
and GHP’s quotation did give rise to a
tender process contract, there was no breach by Leighton Works as alleged,
because at
all times Leighton Works treated tenderers who had submitted a
quotation for the work in a fair and equal manner.
[26] Leighton Works also takes strong issue with GHP’s loss of profit claim and say that any loss of profits is far less than claimed.
Was there a preliminary contract?
[27] It is necessary first to consider whether a contract was formed as
pleaded. If it was not, the claim fails.
[28] Although there were some differences in aspects of the evidence
there are not in my view any significant factual disputes.
The issue is what
interpretation can be placed upon the undisputed exchanges that took place
between the parties. Mr Kelly was
criticised during the trial for keeping GHP
involved in the tender process when Brian Perry was almost certain to get the
job, and
for preparing artificial papers setting out the contract sequences
after the claim was made. Neither criticism is relevant to the
issue of
whether a preliminary contract was formed. I record that I was not satisfied
that Mr Kelly had deliberately tried
to create a misleading document.
The sequences were clearly his own reconstruction of events.
[29] The question of whether a contract was formed can be approached from the traditional position where the language of offer, acceptance and consideration is employed. In this case Ms O’Brien for GHP asserts that the offer was the invitation of 7 May 2009 and the acceptance was the submission of GHP on 20 May 2009. The question is whether, when the relevant evidence is viewed as a whole and objectively, a concluded agreement can be discerned. The principle stated in Eccles
v Bryant1 and quoted in Carruthers v Whitaker2
is applicable:
Parties become bound by contract when, and in the manner in which, they
intend and contemplate becoming bound. That is a question
of the facts of each
case ...
[30] An analysis purely in terms of offer and acceptance will be unrewarding. The test is rather whether, viewed as a whole and objectively, the exchanges between the parties show a concluded agreement.3 Nevertheless, a consideration of the terms and circumstances of the claimed offer and acceptance is central to determining whether
the parties became bound.
1 Eccles v Bryant [1948] Ch 93 (CA) at 104.
2 Carruthers v Whitaker [1975] 2 NZLR 667 (CA) at 673.
3 Boulder Consolidated Ltd v Tangaere [1980] 1 NZLR 560 (CA) at 563; Wilmott v Johnson
[2002] NZCA 309; [2003] 1 NZLR 649 (CA) at [37]–[40].
[31] In carrying out the exercise I bear in mind the “two
contract” approach that has been widely applied in tender
cases. The test
in New Zealand goes back to the decision of Markholm Construction Co Ltd v
Wellington City Council4 applying the Canadian Supreme Court
decision in The Queen in right of Ontario v Ron Engineering &
Construction Eastern Ltd.5 The approach in Ron Engineering
was adopted in Pratt Contractors Ltd v Palmerston North City
Council6 where Gallen J quoted also from Bingham LJ’s
judgment in Blackpool and Fylde Aero Club Ltd v Blackpool Borough
Council.7 Both the Ron Engineering decision and Bingham
LJ’s dicta in Blackpool and Fylde Aero Club were relied on by
McGrath J in the Court of Appeal tender decision of Transit New Zealand v
Pratt Contractors Ltd.8
[32] The two contract analysis was referred to in Ron Engineering
by Estey J.9 A first contract was formed when an
invitation to bid was responded to by a conforming tender, and a second
contract
when the principal contract came into being. He observed:
The principal term of contract A is the irrevocability of the bid, and the
corollary term is the obligation on both parties
to enter into a
contract (contract B) upon the acceptance of the tender. Other terms include
the qualified obligations of
the owner to accept the lowest tender, and the
degree of this obligation is controlled by the terms and conditions established
in
the call for tenders.
[33] Subsequently Bingham LJ in Blackpool and Fylde Aero Club Ltd
made the following more nuanced comment on the tendering
process:10
A tendering procedure of this kind is, in many respects, heavily weighted in
favour of the invitor. ... The risk to which the tenderer
is exposed does not
end with the risk that his tender may not be the highest or, as the case may be,
lowest. But where, as here, tenders are solicited from selected parties all
of them known to the invitor, and where a local authority's invitation
prescribes a clear, orderly and familiar procedure—draft contract
conditions available for inspection and plainly not open
to negotiation, a
prescribed common form of tender, the supply of envelopes designed to preserve
the absolute anonymity of tenderers
and clearly to identify the tender in
question
4 Markholm Construction Co Ltd v Wellington City Council [1984] NZHC 232; [1985] 2 NZLR 520 (HC).
5 The Queen in right of Ontario v Ron Engineering & Construction Eastern Ltd [1981] 1 SCR
111.
6 Pratt Contractors Ltd v Palmerston North City Council [1995] 1 NZLR 469 (HC).
7 Blackpool and Fylde Aero Club Ltd v Blackpool Borough Council [1990] 1 WLR 1195 (CA).
8 Transit New Zealand v Pratt Contractors Ltd [2002] 2 NZLR 313 (CA) at [63]–[80].
9 At 122–123.
10 At 1201–1202.
and an absolute deadline—the invitee is in my judgment protected
at least to this extent: if he submits a conforming tender before the deadline
he is
entitled, not as a matter of mere expectation but of contractual right, to
be sure that his tender will after the deadline be opened
and considered in
conjunction with all other conforming tenders or at least that his tender will
be considered if others are. Had
the club, before tendering, inquired of the
council whether it could rely on any timely and conforming tender being
considered along
with others, I feel quite sure that the answer would have been
“of course”. The law would, I think, be defective if
it did not
give effect to that.
(emphasis added)
[34] McGrath J, having considered these decisions, and quoted this
extract from Bingham’s LJ’s decision, commented
in Transit New
Zealand v Pratt Contractors Ltd:11
Whether a request for tenders gives rise to a process contract, once a
conforming tender is submitted, is in all cases a question
of whether all the
elements of contractual formation are made out at that point. Analysis of the
terms of the invitation to tender
is the starting point. Where the request
makes no express commitment concerning the manner in which tenders received will
be addressed, that may indicate
the invitation was no more than an offer to
receive them. On the other hand, as Blackpool and Fylde Aero Club
indicates, the rigorous and comprehensive expression of requirements to be
complied with by tenderers may give rise to an implied
promise by the invitor to
consider a conforming tender if others are considered. The law does
not, however, have a policy which inclines towards enforcement of implied
promises by invitors, even if they
are public bodies, and whether there has been
a binding promise as to process is to be ascertained by applying general
principles
of contract law concerning contract creation and implied
terms.
(emphasis added)
[35] In Prime Commercial Ltd v Wool Board Disestablishment Co Ltd12 the Court concluded that no preliminary contract for tender for the purchase of a property had been entered into. This was for two reasons. The first was that the defendant could not be said to have agreed either explicitly or implicitly to any process in relation to a prospective purchase, and secondly there was a lack of certainty as to how the
specific terms of any putative contract were to be determined. It could
not be said
11 At [77]. Subsequently affirmed by the Privy Council in Pratt Contractors Ltd v Transit New
Zealand [2005] 2 NZLR 433.
12 Prime Commercial Ltd v Wool Board Disestablishment Co Ltd [2006] NZCA 295; (2006) 7 NZCPR 697 (CA).
that a sufficient consensus existed between the parties for a preliminary
contract to have arisen.13
[36] It is clear therefore that in certain circumstances a preliminary
tender contract will be found to exist, and the Court may
imply terms in that
contract that require the invitor to follow a certain process. There is no
policy which leans either for or
against the finding of such preliminary
contracts. A Court will not assume that the submission of a tender in
conformity with a
tender process has created a preliminary contract. That
submission may, rather, be an initial tender offer that has followed a process
of negotiation. In all cases it comes down to a question of fact, and orthodox
contract law principles must be applied to
the preliminary exchange to
discern whether a contract was created at that point. Features that in my view
indicate a formal
contract process at the initial stage include:
(a) A requirement for registration of tenders; (b) A requirement that tenderers pay a deposit;
(c) Detailed specifications for tender that must be complied with; (d) A stated methodology for processing tenders;
(e) Stated criteria for evaluating tenders;
(f) An express or implied commitment to accept the tender that best meets
the criteria.
(g) In general, formality and prescription in the tender and evaluation
procedures;
[37] It is necessary therefore to examine the broad factual background
and then the actions of the parties to discern whether
a contract was
formed.
13 At [19].
[38] I bear in mind that an absence of formal contractual language is not
fatal to a finding that there is a preliminary contract,
and that it is
customary even in those cases where preliminary contracts have been found, for
the language not to be of formal offer
and acceptance, but rather of invitation
and tender.
Commercial background
[39] Ms O’Brien for GHP states that the claim to a contract coming
into existence must be seen in context and in the commercial
matrix of facts
that existed at the time. She emphasised that the subcontract at issue was part
of a project funded by a public
entity. She submitted that there are
extensive government procedures ensuring that fair processes are undertaken
during
tendering, and that although these do not apply directly to
subcontractors, they are indicative of a reasonable expectation
that fair
dealing clauses in relation to tendering are likely to be applied into
subcontracts. I have to say that the evidence presented
did not satisfy me that
this was the case, and I am unable to infer any particular expectation on the
part of the parties as to fair
dealing beyond that which can be anticipated in
any commercial negotiation.
[40] I accept, however, her submission that it is relevant that
this was a subcontract and not a head contract. The
head contract process,
particularly when a government entity is involved and the work is a public work,
is likely to be the subject
of formal procedures that are fully set out in
preliminary documents. The subcontract process, because the sums involved will
necessarily
be smaller and less in the public eye, can be expected to be less
formal. This is reflected in the actual process adopted here where
there was a
formal head contract, but a much less formal process followed in relation to the
subcontracts. I accept also GHP’s
submission that it would be customary
for a head contractor to have preliminary discussions with potential
subcontractors on design
and pricing information before moving to a more formal
tender process.
[41] It is also relevant as Mr Booth submitted that Ontrack required Leighton Works’ pricing of the Ontrack variation to be conducted on an “open book” basis. The price that Leighton Works developed and put forward for the Ontrack variation
work was open to examination by Transit and Ontrack to ensure and encourage
“best value for money practices” and might
be disapproved. A
consultant company, Bond Construction Management Ltd had been employed
specifically to oversee this process.
Leighton Works as a head contractor was
in the unusual situation of being directly supervised in relation to costs on
the Ontrack
variation. Mr Yonge acknowledged that he was aware of the open
book pricing, and that the contractor would “seek competitive
tenders for
subcontracts and present the best of these for the client’s
approval”. Leighton Works could be expected
to be cautious about
entering into a preliminary contract where it was bound to accept a particular
tender, and run the risk of that
subcontract being unacceptable for one reason
or another to Transit, and GHP knew this. Leighton Works would want
flexibility.
This is a background factor indicating an objective basis that a
preliminary contract was unlikely.
The request for tender document
[42] The document sent on 7 May 2009 which GHP claims was the offer that
it in due course accepted, was a standard form Leighton
Works document. It was
accompanied by a letter stating: “Following our previous correspondence,
please find attached our enquiry for the SH20–1 variation [Ontrack]
Main Works Phase, Secant Piling Package” (emphasis added). It had no
header, and
was from a base template into which insertions could be typed, and
it could be emailed. There was a header logo in colour with “Leighton
Works” on it and the email was from Neil Kelly addressed to John Yonge of
GHP. At the outset it contained these standard words:
We invite you to submit a quotation for the tender and scope of works
described below. Your quotation should be based on the information
given below
and in attachments, if any. Please provide your nominated outputs and
availability to the schedule items. Please contact
the writer ASAP if you have
any queries or do not intend to price the package. Your quotation is to be
valid for 90 days and exclude
GST. A full set of tender documents are available
in our office should you wish to view them.
[43] It then set out a tender return date which was 12 May 2009 at 4pm. It referred to the scheme (the Manukau rail station), the client (Ontrack/ARTA/Transit NZ) and the scope of the work, which was a secant pile wall and certain
specifications. There was then some detailed information set out under the
following
headings:
General Contract Information
The contract is divided into two separable portions.
Description of Contract Works
Due Date for Completion
Contract Data
Liquidated Damages
Health and Safety
General Requirement
Payment Retention
Insurance +
Bond
Variations
Confidentiality Agreement
[44] There was varying detail under the various headings. In relation
to the “Description of Contract Works”
there was reference
to the overall works but nothing specific. The due date for completion was
stated to be:
Phase 1, Pre-Construction – End Apr 09 to End June 09
Phase 3, Station Box – End June 09 to End Jan 10
The contract data was described beside “Conditions” as “Leighton Works standard Contract Conditions”. The contract type was stated to be “Target Cost with Risk” and the defects liability period to be 52 weeks. For liquidated damages it was stated that they were to be advised. There was a general and presumably standard form reference to health and safety. Under the “General Requirement” heading it was said that the contract works, including materials and workmanship, shall comply “with the enclosed specifications. Otherwise your services and goods provided shall be fit for purpose”. There were no specifications attached. In relation to payment retention, the reference was to the total sums retained being “TBC”. That meant
effectively that they were to be advised in due course. There were some
detailed references to the insurance and bond requirements
and it was stated
that Leighton Contractor Pty Ltd’s preference is to go back to back with
subcontractors but that this could
be negotiated on a case by case basis.
There was also a reference to variations having to be ordered by the engineer,
and a specific
“Confidentiality Agreement” was referred to placing
a confidentiality obligation on tendering parties.
The response
[45] Mr Yonge responded to Mr Kelly on the same day stating that
preparing a price by the following Tuesday was a “pretty
big ask”
and asking effectively for more time. Mr Kelly replied on the same day asking
when he could realistically put in
a price.
[46] On 11 May 2009 Mr Kelly sent to Mr Yonge a second request for
tenders document in the same form as the earlier document,
but with the tender
return date being shown as 4pm on 19 May 2009. If the 7 May 2009 request for
tenders document was an offer,
this was a revised offer. There was a revision
in the scope description which was summarised under the heading “Rev 1
issue”
with some differences in particulars. On 19 May 2009 Mr Kelly sent
some further information to tenderers. Mr Yonge of GHP sat down
and prepared
his proposal with detailed pencil pricing calculations that have been
produced.
[47] On 20 May 2009 Mr Yonge forwarded GHP’s quote to Mr Kelly.
His letter began “Manukau rail station – piling
quotation” and
then stated:
We have pleasure in confirming our remeasure quotations, GST exclusive for
these works on the following conditions.
We have based our quotation on the documents provided.
This tender shall remain valid for a period of one month from the date
hereof.
Mr Yonge then set out the details of the secant piles, hold down piles and a wall that was to be constructed. He referred to the programme and equipment, reinforcing, general issues, insurance and payment and dispute resolution.
[48] It is at this point that Ms O’Brien submits a contract was
formed. The offer was the tender forwarded on 7 May 2009
(varied on 11 May
2009), and the acceptance of the quotation of 20 May 2009.
Discussion of the “offer”
[49] Leighton Works in their request document of 7 May 2009 used the word “invite” asking parties to submit “a quotation” which was for “the tender”. It was described as an “enquiry” in the accompanying letter. Mr Yonge’s response of
20 May 2009 reflects that wording in that his response was a “piling
quotation”. Giving these words their natural meaning,
the 7 May 2009
request is not expressed in the language of an offer capable of acceptance. The
language used is one of an invitation
to quote. The response of GHP does not
contain any language indicating acceptance of the preliminary contract offer.
It is in the
language of a quote. Thus, the words in themselves are not
consistent with there being an offer and acceptance, or, to look at them
objectively and in the round, a contract.
[50] There was a good deal of focus in submissions by the plaintiff on
the use of the word “tender”. Indeed, the
word “tender”
or “tenderer” is used seven times in the request for tender
document. However, the fact that
the word “tender” is used does not
assist, particularly in the ascertainment of whether there was a contract.
Indeed,
the use of the word “tender” when it is a
“request” for tender tends to signify the start of a process leading
to an offer rather than there being already a concluded contract. It is used in
the request for tenders in the sense that the quote
that is being sought will be
the tender. The word is used in the request for tender document
interchangeably with the word “quotation”.
[51] However, this analysis of the words used is far from conclusive. Undoubtedly the parties had in mind the main contract which would be formed if a tender was accepted, and this was reflected in their language. It can be expected that the preliminary contract might not contain the usual offer and acceptance terminology.
[52] Some matters arguably point to the request of 7 May 2009 being an
offer. These are:
(a) The use of the word “tender” (given that the
tender process on occasions is known to give rise to
preliminary contracts).
There can be no doubt that GHP’s quotation of 20 May 2009 was a
“tender” in the sense
of it being an offer to supply a
service;14
(b) The smallness of the group invited to tender, which
supports an inference that a particular mode of dealing is
being
promised;
(c) The requirement of confidentiality, which involves acceptance of an
obligation by GHP to Leighton Works;
(d) The insertion of a specified tender return date, which is
consistent with there being a contractual offer; and
(e) The requirement that the quotation be valid for 90 days, which
would be said to involve an acceptance of an obligation by
the
tenderer.
[53] In relation to the use of the word “tender”, as
observed, that word in itself has no magic. The invitation to
tender on its
face means just that; an invitation to quote. It does not indicate that the
invitation to tender itself is
an offer capable of
acceptance.
[54] As to the requirement of confidentiality, although it
is headed “Confidentiality Agreement”
I accept Mr Booth’s
submission that it is really no more than a notice to a prospective tenderer of
the confidentiality obligation,
which in any event existed at equity in the
absence of a contract.15
[55] While the quotation is stated to be valid for 90 days, this can be
seen as no more than a requirement that the offer, constituted
by the quote that
is to follow, will
14 See the definition of “tender” in the New Zealand Oxford Dictionary as including “an offer, esp.
an offer in writing to execute work or supply goods at a fixed price”.
15 Coco v AN Clark (Engineers) Ltd [1968] FSR 415 (Ch) at 419; Attorney General for the United
Kingdom v Wellington Newspapers Ltd [1987] NZHC 377; [1988] 1 NZLR 129 (CA) at 140–141.
remain open for that period. It is commonplace for quotes to be stated to be
open for a set period, and this does not signify that
a contract is created in
itself by the request and the initial offer.
[56] Other factors point to this not being a contract, and the request
for tender document of 7 May 2009 not being an offer capable
of acceptance.
These are:
(a) The absence of any registration requirements;
(b) The absence of a requirement for a deposit from tenderers (such a
deposit being required in Pratt Contractors Ltd v Palmerston North City
Council);
(c) The absence of a requirement for a formal tender procedure, such as
the provision of an envelope or quotation method for
tenderers (an official
envelope was considered relevant in the tender case of Quay Stevedoring
Services Ltd v ENZA Ltd);16
(d) The tender documents were not detailed in relation to the
conditions of the construction contract. The New Zealand Standards
Institute
NZS3910:2003 “Conditions of contract for building and civil engineering
construction” might have been expected
to be prescribed, but were not.
Mr Yonge accepted that he knew nothing of the defendants’ standard terms.
It is clear
indeed that the proposed contract with Leighton Works would
involve standard conditions that were different from the New Zealand
standard.
The tenderers would not know what standard conditions would apply;
(e) Under the heading “General Requirement” the statement is made that the contract works “shall comply with the enclosed specifications” but no specifications are listed. There was evidence from Mr Drummond, a Brian Perry civil estimator, that specifications would usually
accompany a request for a quotation;
16 Quay Stevedoring Services Ltd v ENZA Ltd CA214/00, 15 November 2001 at [19].
(f) The preference that the terms of the Leighton Works
contract be consistent with the terms of the subcontract was
signalled, and it
was stated that “this can be negotiated”. This is not the language
of an offer capable of acceptance,
and of contract formation. It is the
language of negotiation;
(g) A number of important terms that it could be expected would be
defined in the preliminary contract were not defined. In
particular, the issues
of whether there could be liquidated damages and if so, how much, and whether
there could be payment retentions
and if so, how much, were left for further
negotiation. This is again consistent with the parties being in a state of
negotiation,
rather than having agreed to a strict contractual format in a
preliminary contract which could lead then to a binding main
contract;
(h) The request for tender document did not specify that tenders would
be evaluated in terms of the lowest price conforming
method, or any method, or
in accordance with any other criteria. It could be expected that there would be
a set and enforceable
procedure that was to be followed if a preliminary
contract was being formed. Otherwise, the terms on which any offer would be
processed
were left uncertain. This is why GHP has been obliged to suggest
implied terms governing its right to be awarded the tender. There
was therefore
no term indicating how or on what basis the contract would ultimately be awarded
to the successful tenderer. This
lacuna is more consistent with the parties
being in a process of negotiation rather than forming a preliminary
contract;
(i) There was no commitment to accept a tender that complied best with
any criteria.
[57] I accept that the fact that not all the terms of the final contract are settled in the preliminary contract is not fatal to a contract being formed. Nevertheless, the greater the areas of uncertainty as to the tender process ahead, the less likely it is that
there was a preliminary contract. Objectively, it can be expected that the
parties will set out a detailed and settled process if
they intend to create a
contract.
[58] If, for instance, GHP had offered the lowest price, and a tender
with a far more expensive price was successful, the question
that arises is
whether that would that be a breach. What was the term of the preliminary
contract as to how tenders were to be processed?
Ms O’Brien submitted
that it could be implied that the tender which was clearly the best in terms of
“relative value
and credibility” would be the tender that had to
succeed under the contract. The vagueness of the language indicates
a
problem with this submission. How is relative value and credibility to be
evaluated? This crucial term is uncertain and would
be most difficult to apply
if there was a breach.
[59] Similarly, what would happen if Leighton Works insisted on a very
high sum for liquidated damages, or a very high sum for
retentions? What process
would there be in the preliminary contract for dealing with such an impasse?
How could GHP adjust its price
to reflect this adverse term? In fact nothing
could be done if negotiations were over and there was a contract, and GHP would
be
presumably bound by potentially unreasonable terms. This uncertainty
indicates an absence of a preliminary contract, and a state
of affairs
consistent with an invitation to quote in an ongoing negotiation.
[60] It is also significant that Mr Kelly was quite willing to extend the
tender return date. Although the tender return date
appears to have been
extended to all parties, it signifies an element of informality inconsistent
with there being a preliminary
contract.
[61] For these reasons the request for tenders does not have the mark of
an offer capable of acceptance, even in terms of a preliminary
contract.
Discussion of the “acceptance”
[62] Further, the so called “acceptance”, GHP’s quote
of 20 May 2009, did not
correspond to the terms of the request for tender. The request for tenders had
specified a 90 day period of validity. The GHP quote differed in a material way, providing that it remained valid only for one month from 20 May 2009. In the language of offer and acceptance, the offer and acceptance did not conform. An acceptance is only effective if the accepting person agrees to be bound by the terms proposed in the offer.17 The need for conformity of the tender with the terms and
conditions of the request was emphasised both in the Ron Engineering
decision18 and
in Coco Paving 1990 Inc v Ontario (Transportation)19 where
the Ontario Court of
Appeal held that any bid to be valid had to be
“compliant”.
[63] Such a lack of correspondence between the offer and the acceptance is
particularly telling if the so called acceptance contains
a difference which
works against the interests of the offeror. This is the case here, where
GHP’s insertion of a shorter time
period during which its tender would
remain open worked to the disadvantage of Leighton Works.
[64] The provision of a “tagged” (technically non-conforming)
tender is common in the industry. This was put forward
by the plaintiff as
indicating that the difference between the offer and the acceptance was not
material. However, while tagged
tenders may be common in terms of industry
practice, there is every possibility that in all the quotes where this occurs
there is
no preliminary contract formed.
[65] Mr Yonge explained that it was common for tenderers to tender for no
more than one month because of the obvious practical
problems in holding a
tender out for too long. That may be so, but this may mean that it is common in
these subcontract situations
for there to be no preliminary contract. The fact
that Mr Yonge felt free to depart from the terms of the request for tender and
insert a shorter period for the validity of the quote is another indication
that, looking at the matter objectively, no contract
was formed.
[66] The parties’ subsequent conduct does not indicate that a preliminary contract was entered into, as it does not indicate that the parties regarded the tender
framework as settled following GHP’s initial offer. Mr Yonge felt
able to submit a
17 Reporoa Stores Ltd v Treloar [1958] NZLR 177 (CA).
18 Ron Engineering, above n 5, at 122.
19 Coco Paving 1990 Inc v Ontario (Transportation) (2009) ONCA 503 at [4].
substantially reduced tender on 17 June 2009. Another contractor, Hauraki
Pilling, also submitted a revised quotation on that date
with Civil Works/Seatek
being invited to go to a further meeting the following day. This is an
indication that the parties did not
regard themselves as bound by a
process whereby they had to provide a quotation by the date specified,
which would then
be processed and responded to within the time specified. The
position was flexible, consistent with the parties being in a state
of
negotiation rather than a contract.
Comparison with other processes
[67] It is useful to compare this request for tenders document to the earlier request for documents sent by Leighton Works to GHP on 9 February 2009, which resulted in the first offer by GHP to provide piling services. The initial wording of the request for tenders was exactly the same. The scheme and client details were the same and the quotation requested section was filled in with the date of 15 February
2009. The scope, rather than secant pile walling, was sheet piling, and
specific details were given. The same details were given
for general contract
information and the description of contract works. There were different dates
for the due date of completion.
The conditions of the contract data were the
same. The liquidated damages were also to be advised. The health and safety
and
general requirements were the same. The payment retention was filled out in
the 9 February 2009 request, the amount to be retained
being 10 per cent of the
value to completion and five per cent for the duration of the defects liability
period. The insurance and
bond period was filled out in the same way, as were
the variations and the confidentiality agreement portions.
[68] It is significant that the parties did not treat the 9 February 2009
request for tender and the offer in response from
GHP of 18 February 2009
as creating a contract. If the parties at that point did not consider
themselves bound, it is less
likely that they were bound by the later similar
process.
[69] Mr Yonge denied ever having received the defendant’s enquiry document for the sheet piling option, but given that there is no suggestion that at that point a preliminary contract was formed, this is irrelevant. The relevance of the exchange is
that the parties used similar documentation to record a position
which neither thought was contractually binding.
[70] The wording of Mr Yonge’s written quote was also the same
wording on
20 May 2009 as that used when he responded to the initial tender request for
the original sheet pile driving proposal on 18 February
2009. He commenced by
saying “We have pleasure in confirming our ...” and then setting out
the price. In that earlier
offer he also stated that the quotation would be
valid for one month and gave some detail of the work to be done. It contained
a similar reference to dispute resolution at the end. This being an exchange
that Mr Yonge does not suggest led to a contract is
again an indication that the
20 May 2009 offer was a step in a long negotiation, rather than an acceptance of
a preliminary contract.
[71] Mr Anthony Dean, an experienced quantity surveyor and building and
construction dispute consultant called by GHP, expressed
the view that on his
interpretation of the documents, there was a tender process in place. That was
clearly the case but begged
the question whether a contract was formed, a matter
on which Mr Dean was not in a position to give an opinion.
[72] Ms O’Brien submitted that the enforcement of the basic
provisions of tendering was essential for subcontractors
in the construction
industry. That undoubtedly would be so where preliminary contracts are formed,
and where a procedure for awarding
tenders is articulated. However, I do not
consider that this argument means that the usual threshold for discerning
whether a contract
has been formed can in some way be lowered, and that a
contract should be found to exist where none was intended. And given the greater
inherent informality, it is less likely that preliminary contracts will be found
to exist where the main contract is a subcontract,
and not a head
contract.
[73] Finally it must be observed that it is very difficult to see how a term could be implied, even if there was a contract, that precluded Leighton Works from seeking further lower quotations at a later point should it choose to do so. That would be incompatible with the right of Transit to disapprove a subcontractors’ price for the Ontrack variation. If, as may well have been the case here, Transit did not wish to
have any of the tenderers as subcontractors, why should it not be open to Leighton Works to seek further quotations? Leighton Works intervened and obtained a price that was much better as it might have been expected it could do so. In terms of the traditional test in relation to implied terms, it is not so obvious that it goes without saying that no further tenders could be sought in such a circumstance, or indeed that a prohibition on further tenders was necessary to give the contract “commercial
efficacy”.20
Conclusion
[74] Viewing the evidence as a whole and objectively, no concluded
agreement can be discerned. No corresponding offer and acceptance
can be
discerned. The parties’ actions do not indicate that they intended to be
bound. The exchange as it was left relevant
matters unresolved and unclear. I
conclude that GHP has failed to prove that any preliminary contract was
formed.
Damages
Introduction
[75] Having found that there was no preliminary contract, this disposes
of the claim. However, I will now briefly consider the
claim for
damages.
[76] The plaintiff claims that if it had not been for the
defendants’ breach it would have succeeded in its bid and been
awarded the
contract. It claims it would have made a profit of $1,032,674 from that
contract. The defendants did not contest that
the measure of damages was the
profit lost to GHP as a consequence of it not being awarded the
subcontract.
[77] I am satisfied on the evidence that, but for the acceptance of the late Brian Perry bid, GHP would have been awarded the secant piling subcontract. Although a claim for damages by a tenderer will generally proceed on the basis of a loss of a chance, given the effective concession on the part of the defendants that GHP was
clearly the leading bidder prior to the involvement of Brian Perry, I
conclude that
GHP would have succeeded in its tender bid but for that
development.
[78] The defendants, while accepting that GHP was the leading tenderer
prior to the involvement of Brian Perry, nevertheless
strongly contested
the quantum of damages claimed. The defendants did not submit an alternative
figure, but rather focused on
specific aspects of the claim and argued that they
were considerably overstated.
[79] The claim refers to the secant piling works being undertaken on the basis of the 17 June 2009 offer21 for an overall price of $8.45 million using two rigs over 22 weeks, or $9.4 million for three rigs over 15 weeks. Although the two options were given, the claim itself is based on the cheaper 22 week option being successful. A component of those works related to hold down piles tendered for $408,000. The plaintiff’s claim is based on penciled working calculations prepared by Mr Yonge for the tender. I agree with the comment made by a consultant to the Australian piling industry called by Leighton Works, Mr Mark Johnson, that the working papers are
difficult to follow and understand. They do not provide an internally
consistent profit calculation, but rather working notes made
at the time to help
prepare the tender.
[80] It is necessary to set out a breakdown of the plaintiff’s claim for loss of profits. This has not been easy, as Mr Yonge’s notes where he calculated the GHP profit did not set out what was cost and overhead and what was profit. I did not find his evidence on how he calculated the lost profit he claims as easy to follow, but I was assisted by Mr Dean’s efforts to rationalise the claim. My general impression is that Mr Yonge genuinely thought, and still thinks, that GHP would have made a good profit, but that he is not sophisticated when it comes to preparing his costings for quotes, and even now has difficulty in breaking down the calculation of the expected profit.
[81] Of the total sum claimed, $147,854 was half of a contingency
allowance of
$295,708 which Mr Yonge claimed to have included in his 17 June 2009 revised
quotation price.
[82] The approach of Mr Johnson, and an accountant called for the
defendants, Mr John Cregten, has been to consider aspects of
the damages claim
and to query the assumptions made by Mr Yonge and Mr Dean in putting forward
that claim. The first issue to be
considered is the suggestion put forward by
the defendants that the significance of this job (involving the receipt of sums
over
four times GHP’s revenue earned in the proceeding year) was such that
there were significant risks as to GHP’s ability
to carry out the work.
Mr Cregten in particular emphasised the strain on GHP’s physical and
financial resources if it was
to complete the project on time, given that it was
by far the largest job it had had in recent years.
[83] I do not accept that GHP would have been unable to do the work if it
had been awarded the contract. Having heard Mr Yonge
and considered the history
of the company and its accounts over recent years, I consider that he would have
found a way to put together
the resources to fund and complete the work. While
the accounts for 2009 showed declining receipts, and recent history a lack of
very big jobs, the company appears to be solvent and Mr Yonge to be resourceful.
I am satisfied that he would have found a way to
get the job done. GHP would,
however, have been stretched to its limit in terms of funding and
resources.
[84] It is necessary now to consider the specific items of challenge to
the damages claim.
The add-back of the contingency sum
[85] GHP’s breakdown of the secant pile tender price of $8,455,523
(the sum on which damages was calculated) was broken
down as
follows:
Plant and equipment costs $1,975,393
Material and supply costs $4,172,634
Labour costs $821,060
P & G (site overheads) $341,958
Margin for profit and risk $848,770
Contingencies $295,708
Tendered sum $8,455,523
[86] GHP’s breakdown of the hold down pile tender price of $408,940
was as
follows, this being the amended figure put forward by Mr Dean:
Plant and equipment costs $109,192
Material and supply costs $191,644
Labour costs $43,676
P & G (site overheads) $28,378
Margin for profit and risk $36,050
Total $408,940
[87] The margin for profit and risk were therefore $848,770 for the
secant wall and $36,050 for the hold down piles. The total
was $884,820 to
which was added half of the contingency of $295,708.
[88] Mr Johnson, who I am satisfied is an expert in the piling industry
and able to comment on New Zealand conditions, contested
the add-back of the 50
per cent contingency. He also asserted that there should have been a
contingency for unknown
factors of $100,000 and a deduction for the financing
of GHP’s plant based on a recovery of all costs of $300,000. There should
have also been a sum deducted for off-site overheads.
[89] Mr Cregten, an experienced forensic accountant called by the
defendants, had other criticisms. He said that there would
be other costs that
would have been incurred in the course of the job that had not been taken into
account, being:
(a) the preparation of a detailed financial proposal to the bank including
supporting accounting forecasts etc;
(b) valuation fees in respect of the business assets securing the loan and possibly over the personal assets required to shore up the security;
(c) legal fees to re-document the facility; (d) bank establishment fees; and
(e) interest charged until such time as loans were repaid.
[90] Mr Cregten also stated that there would have been a three per cent
change in variable costs amounting to $264,000, and interest
at 14.4 per cent
for five months on equipment worth $1.6 million, the figure being $96,000. If
an eight per cent rate was used the
sum would have been $50,000, or if 10 per
cent was used, $62,500.
Analysis of damages claimed
The add-back of half the contingency figure
[91] The allowance fee of $295,708 is not found anywhere in Mr
Yonge’s working papers. It appears to be a derived rate
and is to be
found in Mr Dean’s summary sheets. It is made up of the amounts of
$10,588 for concrete, $202,400 for hard piling,
$55,000 for soft piling and
$27,720 for excavators, the total being $295,708. The contingency allowance
claimed is a notional and
assumed figure lacking the support of hard evidence.
I also accept Mr Booth’s submission that it is illogical to allow for
a
contingency for unknown factors at the beginning of a job, and then to assert
when the job is not performed that only half of it
would have been
used.
[92] Mr Johnson in his evidence stated that he did not think that Mr Dean
could reasonably predict that only 50 per cent of the
contingency would have
been used and that the other 50 per cent would have been converted into profit.
Mr Johnson thought that the
contingency figure could just as easily have been
twice the amount allowed.
[93] I am not satisfied on the balance of probabilities that there was any precise contingency allowance for the amount claimed in the original estimate, and I am also not satisfied to the required standard that 50 per cent of any contingency would not have been required. I consider that the contingency allowance that I have no doubt
Mr Yonge would have loosely factored into his calculations would not have
been unduly generous. The bid on which his claim is based
was, after all, a
pared down bid. He would not have been unnecessarily generous in his allowance
for contingencies. I reject this
aspect of the claim.
The oscillators
[94] In his original estimate for the secant piling works Mr Yonge
allowed for the purchase of two oscillators to be used to assist
in the
drilling. In a second estimate for the revised quotation on 17 June 2009 both
oscillators were removed from the pricing.
It was Mr Johnson’s opinion
that this was an ill-advised move and left GHP exposed if the drill rig had not
been able to drill
to the required level of efficiency. In his opinion GHP
should have allowed for the cost of at least one oscillator on the job.
Therefore,
this should have been deducted from the profit which GHP otherwise
claims would be made on the project. The sum involved for the
hire of an
oscillator was $330,000 being 110 days hiring the oscillator at $3,000 a day
(110 days was the estimated duration of the
contract).
[95] Mr Yonge maintained that when he re-calculated for his second quote,
he realised that he would not need the oscillators.
However, Mr Dean accepted
in cross-examination that it would have been prudent to have had at least one
oscillator on site to boost
the drilling ability of GHP’s machines. I am
satisfied that this is so.
[96] However, the full deduction of $330,000 seems to me excessive. It
is not clear that the oscillator would have been required
to have been on site
the whole time. In the circumstances I consider it appropriate to allow for
half of the deduction claimed for
the oscillator being $165,000.
On-site management
[97] Mr Johnson considered that $50,000 should have been deducted to take into account the costs of on-site management. Mr Yonge claimed that on-site management which would have been conducted by him and his son was already built in to his costings. In my view this is the sort of allowance that it could be expected
Mr Yonge would have taken into account in calculating his plant and labour
daily rates. I am satisfied that no extra deduction is
required on this
count.
Financing costs
[98] Mr Johnson also argued that there should be a deduction for
financing costs in relation to the excavator. Mr Yonge maintained
that those
costs had been built into his calculation, and I accept that
evidence.
Off-site overheads
[99] Mr Johnson was of the view that a contribution should be made for
off-site overheads. Mr Dean asserts this is normally 20–33
per cent. Mr
Yonge claimed that this had already been taken into account in his calculations.
I note Mr Cregten’s criticisms
of a lack of provision for fees and
interest. At an eight per cent interest rate Mr Cregten allowed a sum of
$50,000 for the funding
of those overheads including the repayment of
loans.
[100] I consider in all the circumstances that deduction to be fair. I
therefore deduct $50,000 on account of overheads/interest
not included in Mr
Yonge’s calculations.
Overview
[101] The following deductions must be made therefore from the estimate of
lost profit of $1,032,674:
Contingency allowance $147,854
Oscillator $165,000
Overheads/interest $50,000
Total $362,854
[102] In my view the lost profit that resulted from GHP not obtaining the
Leighton
Works contract came to this figure of $669,820.
[103] This is a net return of 7.92 per cent on the contract sum. It is
somewhat less than the 10 per cent that it was indicated
in evidence could be
the expected profit margin in a contract of this size. On the other hand, as I
have stated, I am satisfied
that in general terms GHP was going to be stretched
in doing this job and would have had to borrow money and was likely to strike
particular difficulties because of the unusual scale of work it was facing. I
am satisfied on an overview, taking into account Mr
Dean and Mr Cregten’s
general comments that this figure for loss is fair and appropriate.
[104] I put to one side the much lower tender offer which was ultimately
successful made by Brian Perry. The sum there was $7,466,947.66.
However,
Brian Perry is associated with Fletcher Building Ltd and it could well be that
there were economies of scale, and equipment
and skills available which would
not have been available to GHP.
[105] Therefore, if I had found for the plaintiff on liability I would have
awarded damages of $669,820.
Result
[106] The plaintiff’s claim is dismissed.
Costs
[107] There seems to be no reason why costs should not follow the event and
be at a 2B basis. However, in case there are factors
that I am not aware of, I
reserve the issue of costs. If necessary parties are to file submissions on
costs, the defendants within
14 days and the plaintiff within a further 14
days.
...................................
Asher J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2012/1695.html