|
Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 11 November 2015
IN THE HIGH COURT OF NEW ZEALAND WHANGAREI REGISTRY
CIV-2014-488-94 [2015] NZHC 2777
|
BETWEEN
|
OLIVIA WAI YEE LEE
Plaintiff
|
|
AND
|
WHANGAREI DISTRICT COUNCIL Defendant
ROBIN FREDERICK LITTLEJOHN Third Party
|
|
Hearing:
|
8 June 2015
|
|
Appearances:
|
Plaintiff in person with Therese Connor (McKenzie friend) F Divich and H
Waldron for Defendant
A G Jackson for Third Party
|
|
Judgment:
|
10 November 2015
|
JUDGMENT OF ASSOCIATE JUDGE R M
BELL
This judgment was delivered by me on 10 November 2015 at 3:30pm
pursuant to Rule 11.5 of the High Court Rules
............................................................
Registrar/Deputy Registrar
Solicitors:
Heaney & Partners (Frana Divich/HollyWaldron), Auckland, for Defendant
Perkinson Law (S W Perkinson), Whangarei, for Third Party
Counsel:
Anthony G Jackson, Whangarei, for Third Party
LEE v WHANGAREI DISTRICT COUNCIL [2015] NZHC 2777 [10 November
2015]
TABLE OF CONTENTS
Paragraph
The legal test for accrual of a cause of action in negligence
in a leaky building case [8]
Admissibility of reports and notices [14] Events up to 22 May 2008 [15] Events after 22 May 2008 [37] The adjudication under Construction Contracts Act 2002 [38]
Application for assessor’s report under the
Weathertight Homes Resolution Service Act [41]
The proceeding in the Weathertight Homes Tribunal [42]
Proceeding by Composite Cladding and Signage Manufacture
and Installations Ltd [43]
Arbitration by Rob Littlejohn Builders Ltd [45]
The Gill Report [46]
Ms Lee’s response to the Council’s summary judgment
application [48] Beattie reports
[49] The application for an assessor’s report
[50] Fresh defects identified by Mr Gill
[56]
Result [70]
[1] The defendant, the Whangarei District Council, applies for summary judgment against the plaintiff, Ms Lee, on the ground that her proceeding is statute- barred under s 4(1)(a) of the Limitation Act 1950. Ms Lee started this proceeding on
21 May 2014.1 Accordingly the District Council needs to show
that Ms Lee’s cause
of action against it accrued earlier than 22 May 2008. Opposing, Ms Lee says
that the proceeding is within time.
[2] This is a leaky building case. Ms Lee sues the District Council
for alleged negligence in inspection while her house at
183 Sandford Road,
Ruakaka, was under construction between 2006 and 2008. Ms Lee moved into the
house in late 2007. She accepts
that by early 2008 she was aware that there were
defects in the workmanship but says that that knowledge was not enough for the
cause
of action against the Whangarei District Council to have
accrued.
[3] On a defendant’s application for summary judgment under r
12.2 of the High Court Rules, the court applies the principles
in Westpac
Banking Corporation v M M Kembla New Zealand Ltd:2
The applications for summary judgment were made under R 136(2) of the High
Court Rules which permits the Court to give judgment against
the plaintiff
“if the defendant satisfies the Court that none of the causes of action in
the plaintiff's statement of claim
can succeed”.
Since R 136(2) permits summary judgment only where a defendant satisfies the
Court that the plaintiff cannot succeed on any of its
causes of action, the
procedure is not directly equivalent to the plaintiff's summary judgment
provided by R 136(1).
Where a claim is untenable on the pleadings as a matter of law, it will not
usually be necessary to have recourse to the summary judgment
procedure because
a defendant can apply to strike out the claim under R 186. Rather R 136(2)
permits a defendant who has a clear
answer to the plaintiff which cannot be
contradicted to put up the evidence which constitutes the answer so that the
proceedings
can be summarily dismissed. The difference between an application to
strike out the claim and summary judgment is that strike- out
is usually
determined on the pleadings alone whereas summary judgment
1 Ms Lee says that she began the proceeding on 19 May 2014. The Registrar has stamped the statement of claim as received on 21 May 2014. In the circumstances of the case, nothing turns on the difference.
2 Westpac Banking Corporation v M M Kembla New Zealand Ltd [2000] NZCA 319; [2001] 2 NZLR 298 (CA) at
[58]-[64].
requires evidence. Summary judgment is a judgment between the parties on the
dispute which operates as issue estoppel, whereas if
a pleading is struck out
as untenable as a matter of law the plaintiff is not precluded from
bringing a further properly
constituted claim.
The defendant has the onus of proving on the balance of probabilities that
the plaintiff cannot succeed. Usually summary judgment
for a defendant will
arise where the defendant can offer evidence which is a complete defence to the
plaintiff's claim. Examples,
cited in McGechan on Procedure at HR
136.09A, are where the wrong party has proceeded or where the claim is clearly
met by qualified privilege.
Application for summary judgment will be inappropriate where there are
disputed issues of material fact or where material
facts need to be
ascertained by the Court and cannot confidently be concluded from
affidavits. It may also be inappropriate
where ultimate determination turns on a
judgment only able to be properly arrived at after a full hearing of the
evidence. Summary
judgment is suitable for cases where abbreviated procedure and
affidavit evidence will sufficiently expose the facts and the legal
issues.
Although a legal point may be as well decided on summary judgment application as
at trial if sufficiently clear (Pemberton v Chappell [1986] NZCA 112; [1987] 1 NZLR 1),
novel or developing points of law may require the context provided by
trial to provide the Court with
sufficient perspective.
Except in clear cases, such as a claim upon a simple debt where
it is reasonable to expect proof to be immediately available,
it will not be
appropriate to decide by summary procedure the sufficiency of the proof of the
plaintiff's claim. That would permit
a defendant, perhaps more in possession of
the facts than the plaintiff (as is not uncommon where a plaintiff is
the victim
of deceit), to force on the plaintiff's case prematurely before
completion of discovery or other interlocutory steps and before the
plaintiff's
evidence can reasonably be assembled.
The defendant bears the onus of satisfying the Court that none of the claims
can succeed. It is not necessary for the plaintiff to
put up evidence at all
although, if the defendant supplies evidence which would satisfy the Court that
the claim cannot succeed,
a plaintiff will usually have to respond with credible
evidence of its own. Even then it is perhaps unhelpful to describe the effect
as
one where an onus is transferred. At the end of the day, the Court must be
satisfied that none of the claims can succeed. It is
not enough that they are
shown to have weaknesses. The assessment made by the Court on interlocutory
application is not one to be
arrived at on a fine balance of the available
evidence, such as is appropriate at trial.
[4] I emphasise these matters:
(a) On a summary judgment application the legal onus remains on the
defendant throughout to show that none of the plaintiff’s
causes of action
can succeed.
(b) It is not enough that the plaintiff’s case may be weak.
(c) The decision is not made on a fine balance of the evidence.
[5] The starting point for limitation defences for claims arising from
building work or inspection of work under the Building Act 2004 is s
393:
Limitation defences
(1) The Limitation Act 2010 applies to civil proceedings against any
person if those proceedings arise from—
(a) building work associated with the design, construction, alteration,
demolition, or removal of any building; or
(b) the performance of a function under this Act or a previous
enactment relating to the construction, alteration, demolition,
or removal of
the building.
(2) However, no relief may be granted in respect of civil proceedings
relating to building work if those proceedings are brought
against a person
after 10 years or more from the date of the act or omission on which the
proceedings are based.
(3) For the purposes of subsection (2), the date of the act or
omission is,—
(a) in the case of civil proceedings that are brought against a territorial authority, a building consent authority, a regional authority, or the chief executive in relation to the issue of a building consent or a code compliance certificate under Part
2 or a determination under Part 3, the date of issue of the consent,
certificate, or determination, as the case may be; and
(b) in the case of civil proceedings that are brought against a person
in relation to the issue of an energy work certificate,
the date of the issue of
the certificate.
[6] Subsection (2) provides a longstop bar on proceedings “10 years or more from the date of the act or omission on which the proceedings are based.” The council does not rely on that provision in this case. It accepts that all its actions in relation to the house took place within 10 years before the proceeding started. Instead, it relies on the limitation provision in subs (1). The Limitation Act 2010 came into force on 1 January 2011. It repealed the Limitation Act 1950, but the
1950 Act continues to apply to proceedings based on acts or
omissions before
1 January 2011.3 Accordingly, Ms Lee’s
cause of action in tort against the council
3 Limitation Act 1950, s 2A; Limitation Act 2010, ss 57 and 59.
for its acts and omissions before 1 January 2011 is subject to the six year
limitation in s 4(1)(a) of the Limitation Act 1950:
(1) Except as otherwise provided in this Act ... the following actions
shall not be brought after the expiration of 6 years
from the date on which the
cause of action accrued, that is to say, -
(a) actions founded ... on tort; ...
[7] Under Part 2 of the Limitation Act 1950 limitation periods may be
extended in various cases, including fraud and mistake,
but Ms Lee does not say
that any of the cases for extension apply in this case.
The legal test for accrual of a cause of action in negligence in a leaky
building case
[8] In Invercargill City Council v Hamlin, McKay J said:
4
The ordinary time limit for an action in contract or in tort is thus
calculated from the date on which the cause of action accrued.
The phrase
“cause of action” has been defined as meaning every fact which it
will be necessary for the plaintiff to
prove, if traversed, in order to
support his right to the judgment of the court: Cook v Gill (1873)
LR 8 CP 107 at p 116 and Read v Brown (1888) 22 QBD 128 (CA).
....
In an action in tort based on a wrongful act which is actionable per se
without proof of actual damage, the cause of action will accrue
at the time the
act was committed. Where the claim is based on negligence, however, damage is
an essential part of the cause of
action, and until the damage has occurred the
cause of action is not complete.
[9] In Hamlin, a local authority was sued for negligence in inspection when the foundations of a house were found to be defective. In the Privy Council, the plaintiff’s loss was held not to be physical damage to the structure, but economic loss which arose only when defects were discovered:5
Once it is appreciated that the loss in respect of which the plaintiff in the
present case is suing is loss to his pocket, and not
for physical damage to the
house or foundations, then most, if not all the difficulties surrounding the
limitation question fall
away. The plaintiff’s loss occurs when the
market value of the house is depreciated by reason of the defective foundations,
and not before. If he resells the house at full value before the
defect is discovered, he has suffered no loss.
Thus in the common
case the occurrence of the loss and the discovery of the loss will
coincide.
4 Invercargill City Council v Hamlin [1994] 3 NZLR 513 (CA) at 536.
5 Invercargill City Council v Hamlin [1996] 1 NZLR 513 (PC) at 526.
But the plaintiff cannot postpone the start of the limitation period by
shutting his eyes to the obvious. In Dennis v Charnwood Borough Council,
a case decided in the Court of Appeal before Pirelli reached the House of
Lords, Templeman LJ said at p 420 that time would begin to run in favour of a
local authority:
“... if the building suffers damage or an event occurs which reveals
the breach of duty by the local authority or which would
cause a prudent
owner-occupier to make investigations which, if properly carried out, would
reveal the breach of duty by that
local authority.”
In other words, the cause of action accrues when the cracks become so bad, or
the defects so obvious, that any reasonable homeowner
would call in an expert.
Since the defects would then be obvious to a potential buyer, or his expert,
that marks the moment when
the market value of the building is depreciated, and
therefore the moment when the economic loss occurs. Their Lordships do not think
it is possible to define the moment more accurately. The measure of the loss
will then be the cost of repairs, if it is reasonable
to repair, or the
depreciation of the market value if it is not. ...
[10] Accordingly, a discoverability test is applied in a claim for
building defects. Where limitation turns on accrual of a cause
of action, such
as negligence, in which damage is a component, time does not run against the
owner of a defective building until
the defects are discovered, or could with
reasonable diligence be discovered. It is also necessary to note that the
defects must
cause a loss in value, for otherwise the owner will suffer no
economic loss. In a claim against a local authority for negligence
in carrying
out functions under the Building Act, the defects must relate to compliance with
the Building Code or other requirements of the Building Act, for which a local
authority has a regulatory responsibility.
[11] In Murray v Morel & Co Ltd the Supreme Court reviewed the “reasonable discoverability” test.6 The majority upheld the traditional approach that the test for accrual of a cause of action is based on occurrence rather than discoverability, but held that the decision in Hamlin was consistent with this because damage occurred at
the time a defect was discovered, not earlier.7
The test in Hamlin still
applies.
6 Murray v Morel & Co Ltd [2007] NZSC 27, [2007] 3 NZLR 721.
7 At [42].
[12] In North Shore City Council v Body Corporate 188529 the
Supreme Court confirmed that a cause of action accrued when damage was
discovered or could have been discovered with reasonable
diligence.8
[13] Accordingly, for Ms Lee’s claim to be time-barred
under s 4 of the Limitation Act 1950, the council will
need to show that
before 22 May 2008 Ms Lee knew or could with reasonable diligence have
discovered that the house had construction
defects that resulted in water
ingress. In deciding whether Ms Lee’s claim is barred under 4(1)(a) of
the Limitation Act
1950, it does not matter how weak or strong her claim is.
The court cannot adjust the limitation period according to its view of
the
merits.
Admissibility of reports and notices
[14] The evidence for the council’s application is largely documentary, much of it obtained on discovery. Both sides have included in their evidence notices and reports made by building inspectors and reports made by building consultants. Neither side objected to them going in evidence. Insofar as those documents are relied on to show that Ms Lee became aware of the condition of the house, a hearsay question arises. Insofar as the documents are used to prove the defects, they are hearsay, as their authors have not given evidence. All the documents relied on to
prove the defects are business records under s 16(1) of the Evidence
Act9 as their
authors were under duties to make the reports and their authors had personal knowledge of the matters in them. Given that the existence of the documents is not in dispute, in the circumstances of this case it is unnecessary for either side to have
the authors of those documents make affidavits. Undue expense would be
caused by
8 North Shore City Council v Body Corporate 188529 [2010] NZSC 158, [2011] 2 NZLR 289 at
[63]-[75].
9 Evidence Act 2006, s 16(1):
business record means a document—
(a) that is made—
(i) to comply with a duty; or
(ii) in the course of a business, and as a record or part of a record of that business; and
(b) that is made from information supplied directly or indirectly by a person who had, or may reasonably be supposed by the court to have had, personal knowledge of the matters dealt with in the information he or she supplied.
requiring each author to give an affidavit. The various reports are
accordingly admissible as business records under s 19 of the
Evidence
Act:
Admissibility of hearsay statements contained in business
records
(1) A hearsay statement contained in a business record is admissible
if—
(a) the person who supplied the information used for the composition of
the record is unavailable as a witness; or
(b) the Judge considers no useful purpose would be served by requiring
that person to be a witness as that person cannot reasonably
be expected (having
regard to the time that has elapsed since he or she supplied the information and
to all the other circumstances
of the case) to recollect the matters dealt with
in the information he or she supplied; or
(c) the Judge considers that undue expense or delay would be caused if
that person were required to be a witness.
Events up to 22 May 2008
[15] In August 2006 Ms Lee applied for a building consent for the house.
The District Council granted her consent on 26 October
2006. Building work
began in January 2007. The builder was Rob Littlejohn Builders Ltd,
which apparently worked under
a labour-only contract. The third party
is its director. Other contractors who worked on site included Composite
Cladding
and Signage Manufacture and Installation Ltd (a cladding contractor),
Altherm Aluminium Northland Ltd (a joinery installer), Northland
Waterproofing
Solutions Ltd, Design Metal Roofing Ltd, and K J Fong (a draughtsman). Ms Lee
had engaged a civil engineering practice
on some geotechnical, structural and
design matters at the consent stage but it does not appear that any
professionals had any later
involvement in the project.
[16] During construction the council carried out a number of inspections, including two of significance on 18 June 2007 and 26 June 2007. The inspection on
18 June 2007 was a pre-clad inspection. The inspectors required further information for assessment before cladding could be installed. The council returned on 26 June
2007 to deal with questions relating to the cladding system and details surrounding this. The exterior cladding for the building was a material Ms Lee had imported
from China. It is now accepted that it did not by itself provide adequate
protection against water penetration.
[17] In October 2007 and again in November 2007 Ms Lee observed leaking
at the top of the internal staircase. On the second occasion
she drew this to
the builder’s attention.10 Ms Lee moved into the house in
December 2007.
[18] By January 2008 Ms Lee was in dispute with Rob Littlejohn Builders
Ltd. The contractor was asking for payment. She
was not satisfied
with the workmanship. In January 2008 Ms Lee emailed Mr Littlejohn, taking
issue with his workmanship. Amongst
other things she stated:
I believe what is remaining is more serious than can be remedied in the
maintenance period.
She enclosed a cheque, but made deductions. She sought legal advice on 26
January
2008.
[19] In February 2008 Ms Lee engaged Mr Ian Beattie of Kaimamaku Consultancy Ltd to provide an assessment of the house including on matters of weathertightness issues. Mr Beattie describes himself as a “property and building consultant”. On his business letterhead he is described as a building surveyor, weathertightness and cladding specialist and as having qualifications in construction. In comparison with other reports on Ms Lee’s house, Mr Beattie’s report of 5
February 2008 to Ms Lee’s lawyers is relatively short. All the same,
while noting a
number of deficiencies in the work, the report includes this:
The exterior cladding is a unique system that introduces numerous
challenges within the complex inter-change of walls, joinery
and soffits. Most
of the exterior would not meet the requirements of the New Zealand Building
Code in either durability,
weathertightness or alignment. Resolution
will necessitate the removal of extensive sections of cladding, after which a
close
assessment of the construction will quantify the extent of the remediation
necessary.
In
later proceedings, Ms Lee acknowledged having received Mr Beattie’s
report.11
[20] On 12 March 2008, Ms Lee’s lawyer wrote to the builder’s
lawyer. Although the letter is said to be “without
prejudice - except as
to costs” Ms Lee has not claimed privilege for it and it was put in
evidence without objection. The
letter was sent following a further technical
survey by Mr Beattie. It said that this survey had established that numerous
constructional
elements were deficient and had not been constructed in
accordance with consent plans. The letter proposed mediation as an alternative
to protracted litigation.
[21] The council carried out a final inspection on 26 March 2008. The
house failed that inspection.
[22] Following the inspection on 26 March 2008, the council’s inspector sent a field advice notice to Ms Lee on 2 April 2008, identifying a number of matters requiring attention. (The council issued a further field advice notice on 18 June
2008, in which it required sill flashings to be installed as per the approved
building consent drawings). In this proceeding, the
council refers to these
matters in the March notice as particularly relevant:
(a) Spouting required to upper roof as per consented drawings.
(b) Internal gutters not lined with materials as noted on consent
drawings.
Provide proper information for assessment as to suitability for end use and
compliance with NZBC (E1, B2). Plans will need to be
amended to reflect these
changes (if approved).
(c) Roof gutters (internal) require overflows to be sized as per consented
documents.
(d) Rainwater heads required as per consented
documents.
11 Lee submissions dated 11 May 2009 in CIV-2009-488-192 Rob Littlejohn Builders Ltd v Olivia
Lee DC Whangarei CIV-2008-088-332..
(e) Vent/drain holes are required to the lower end of the parapet
cladding area and the lower end of the cladding over
the windows (water
entrapment).
(f) The timber used for the external staircase on the south eastern
face is not as per the consent drawings. Ms Lee was asked
to provide
information that verifies compliance with the code: B2 (durability) and B1
(structure).
(g) Confirmation is required that:
(a) the balcony membrane fully extends under the aluminium handrail channel
at upper deck level (clear detail required);
(b) the decking membrane is suitable for this possibly flooded
situation, and fully protects the structure below from water
entry (E2)
and
(c) the method of fixing the aluminium channel through the
membrane maintains the water proof situation which continues
to satisfy E2
– clear details required.
(h) A producer statement from both the membrane installer and
the barrier installer is required for the respective
situations.
(i) The council required a producer statement (PS3) for the
installation of external cladding to ensure compliance with E2
of the building
code.
[23] The council did not issue a code compliance certificate.12 Ms Lee’s case
accordingly alleges negligence in inspections, not negligence in
issuing a code compliance certificate.
12 That by itself is not necessarily fatal to Ms Lee’s claim: North Shore City Council v Body Corporate 188529, above n 8, at [60]-[62]. A duty is owed at the inspection phase. Whether the council breached the duty in this case is another matter.
[24] In an affidavit in opposition to the council’s security for
costs application in
this proceeding, Ms Lee said: 13
The discovery of the house leaking was not long after the final
inspection.
[25] In a statement of evidence she gave in a District Court proceeding
against the cladding contractor,14 Ms Lee says that on 28 April 2008
she saw water dropping down from the ceiling at the stairway area; water
dropping internally
from the ground floor windows and doors, and from the top
of the wall linings in the lounge on the north and east faces; water dropping
internally from the eastern and southern windows, doors and tops of walls on the
ground floor in the night lounge; and on the north
side of the night lounge
water dropped internally from the windows and
doors.15
[26] On 29 April 2008, Ms Lee took photographs showing leaks around
windows, doors, from the ceiling and top of walls, near an
internal stairwell
and in a lounge.
[27] By the end of April 2008, Mr Beattie made a further report for Ms
Lee, called “Assessment of Construction of Dwelling”.
Mr
Beattie’s invoice for the report is dated 30 April 2008. The report
includes the following statements:
Most of the structure is totally obscured by exterior cladding and the roof.
However, interior walls displayed sufficient misalignment
to cast doubt on the
acceptable tolerances of alignment and plumb of the entire structure. ... Most
of the exterior would not meet
the requirements of the New Zealand Building
Code in either durability, weathertightness or alignment. Resolution
will
necessitate the removal of extensive sections of cladding, after which a
close assessment of the construction will quantify the extent
of the remediation
necessary.
At paragraph 1.10 this appears:
Of particular concern to the owner was the weathertightness of the roof
installation and deficiencies evident in the balcony structure
adjoining the
north east elevation.
13 Lee affidavit of 5 November 2014 at [10].
14 Composite Cladding & Signage Manufacture and Installations Ltd v Lee DC Whangarei CIV-
2008-088-562, at paragraph [76].
15 I add from my own memory that there was very heavy rainfall on 28 April 2008. It caused widespread flooding and landslips on the east coast of Northland. It was reputedly a one in a hundred year event.
[28] The report considers roof drainage, the north-east balcony and the
south-east balcony. Mr Beattie found defects in all these
areas. The drainage
system in the roof was found to be inadequate and did not cater for storm events
required by AS/NZS 3500.5:2000.
The north-east balcony was found to have been
modified significantly from that detailed on the consent drawings, with
insufficient
fall provided, preventing adequate drainage and drying. This was
said to introduce a number of high risk aspects to the integrity
of the
structure. The south-eastern balcony was found to have been built with
insufficient cross-fall to a purpose-made outlet
and had a deficient drainage
system.
[29] The conclusion to the report stated that significant elements of construction of the dwelling did not comply with the New Zealand Building Code and associated standards. It said that the roof drainage system was entirely inadequate for catchment and remediation needed to be addressed with some urgency. The north- east balcony did not comply with consent documents and the modifications compromised the integrity of the structure and the adjoining dwelling, with remediation to be addressed quite urgently. A qualification was added (at paragraph
6.6):
This assessment report and estimates are to be qualified by the limited
access that could be made available to concealed elements
within the structure.
It may be found that the concealed downpipes are of sufficient capacity but
should this not be the case then
extensive redesign and re-estimation may be
necessary to completely replace the sub-terrain elements across to the water
tanks.
[30] Ms Lee referred to this report in an email to Composite Cladding
& Signage Manufacture and Installations Ltd on 18 May
2008. Her email
refers to attachments, “the Whangarei City Council report and the
independent building consultant
reports,” and states:
According to the report from independent builder consultant, the cladding
need to removal.
[31] On 19 May 2008, Ms Lee signed a letter prepared by her lawyer addressed to Rob Littlejohn Builders Ltd, giving a notice of dispute/adjudication under the building contract of 27 November 2007. In briefly describing the dispute, the notice stated that the house had not been built in accordance with the contract, the Building
Act and the Building Code. Because of these breaches, the notice said that
moisture and water ingress had entered into the dwelling
which was defective and
required extensive remediation. The notice referred to the assessments made by
Mr Beattie and included this:
Most of the exterior would not meet the requirements of the New Zealand
Building Code in durability, weathertightness or alignment.
Resolution will
necessitate removal of the existing cladding.
Deficiencies are evident in respect of the weathertightness of the roof
installation and the balcony structure adjoining the north-east
elevation
– both of which will require extensive remediation.
[32] The notice gave particulars of alleged defects in
workmanship. It also alleged breach of duty of care to carry
out work in
accordance with the Building Act and the Building Code.
[33] For its summary judgment application, the council can rely only on
matters arising before 22 May 2008 to show that a cause
of action against the
council had arisen then.
[34] There is one further matter the council relies on – Ms Lee’s decision not to file a claim under the Weathertight Homes Resolution Services Act 2006 at that stage. It shows her knowledge that the defects causing water ingress had reduced the value of the house. In her submissions of 11 May 2009 in a proceeding against Rob
Littlejohn Builders Ltd,16 Ms Lee outlined the relevant history.
Between a paragraph
recording the leaking she saw on 28 April 2008 and service of a summary
judgment application on 9 May 2008, she stated this:
Regent Law suggested defendant go to Weathertight Home Resolution Services at
that time, after defendant had read all the details
of WHRS noticed that that
service will diminish house values. What defendant wants was to have family
house to live and
can carry on her business. So defendant just want
plaintiff come back to fix his defective work problem and move on the
life.
[35] The council relies on all the above facts to submit that:
1 Ms Lee knew that the house had been built with significant
defects.
16 Rob Littlejohn Builders Ltd v Lee DC Whangarei CIV-2009-488-192, 11 May 2009.
3 The defects resulted in a loss of value.
[36] On those facts, the council submits that the cause of action had
already accrued before 22 May 2008. Ms Lee does not contest
the facts, only
whether they go to show that the cause of action had already accrued. She says
that time did not start to run until
later: from 12 August 2008 when she applied
for an assessor’s report under the Weathertight Homes Resolution Service
Act, or
from 6 April 2011 when Mr Gill, another building expert, found a defect
in construction that had not been identified until then.
Events after 22 May 2008
[37] Ms Lee cannot be accused of lethargy over the six years before she
started this proceeding. Instead disputes over the construction
of her house
seem to have dominated her life. There has been an adjudication under the
Construction Contracts Act 2002, an attempted
proceeding in the Weathertight
Homes Tribunal and an unsuccessful appeal from its decision, a hearing in the
District Court, a successful
appeal from that court’s judgment, a
rehearing and an unsuccessful appeal, and an arbitration. For some of that time
Ms Lee
has represented herself, at other times she has had a lawyer. She has
obtained more information about the defects in her house.
The adjudication under Construction Contracts Act 2002
[38] On 6 June 2008, Ms Lee signed an application to nominate an
adjudicator under the Construction Contracts Act 2002, the other
party to the
dispute being Rob Littlejohn Builders Ltd. Ms Lee alleged defective work by the
builder and relied on information showing
weathertightness failure.
[39] In July 2008 there was an adjudication under the Construction Contracts Act. The decision made on the papers went against Ms Lee, with the adjudicator rejecting Ms Lee’s counterclaim, drawing a distinction between defective work on the one
hand and defects appearing after the work had been completed on the other.
He held that the fact that defects became apparent after
the work was completed
by Rob Littlejohn Builders Ltd was not of itself evidence of defective work by
the builder which would have
entitled Ms Lee to claim reductions in the
price.
[40] Ms Lee appealed against that decision, but that was put on hold
while the dispute with Rob Littlejohn Builders Ltd on the
entire merits went to
arbitration.
Application for assessor’s report under the Weathertight Homes
Resolution Service
Act
[41] On 12 August 2008, Ms Lee applied for an assessor’s
report under the
Weathertight Homes Resolution Service Act. The assessor inspected the
property on
16 and 17 August 2008 and made a report on 20 October 2008. The report found
that the house met the eligibility criteria under s
14 of the Weathertight Homes
Resolution Services Act. The assessor listed the parties who were potentially
liable, including the
Whangarei District Council as building certifier and as
the territorial authority which issued the building consent and undertook
all
site inspections. The assessor estimated the remedial cost at $430,000. The
report recorded that the assessor had interviewed
Ms Lee. The report records
information she gave him as to the house suffering leaks and ensuing
damage.
The proceeding in the Weathertight Homes Tribunal
[42] Ms Lee lodged a claim in the Weathertight Homes Tribunal. The respondents were the District Council, Mr K J Fong (a draughtsman), Altherm Aluminium Northland Ltd, Northland Waterproofing Solutions Ltd and Design Metal Roofing Ltd. The tribunal held in March 2013 that Ms Lee was barred from making a claim in the tribunal under s 60(5) of the Weathertight Homes Resolution Service Act because the subject matter before the tribunal was also the subject of other proceedings. Ms Lee tried to appeal against the decision of the Tribunal. As
she was out of time she needed leave, but Wylie J dismissed her
application.17 He
17 Lee v Whangarei District Council [2014] NZHC 1002.
gave his decision on 14 May 2014. Ms Lee began this proceeding very shortly
afterwards.
Proceeding by Composite Cladding and Signage Manufacture and Installations
Ltd
[43] Composite Cladding and Signage Manufacture and Installations Ltd
sued Ms Lee in the District Court for the unpaid balance
of the contract price.
Ms Lee counterclaimed, alleging defective workmanship. In October 2009, Judge
David Harvey gave judgment
in favour of Composite Cladding and Signage
Manufacture and Installations Ltd and dismissed Ms Lee’s counterclaim,
making strong
findings against Ms Lee. Ms Lee did not have legal representation
in that proceeding.
[44] She appealed - this time, with legal assistance. Rodney Hansen J allowed her appeal, primarily on procedural grounds, and directed a re-hearing.18 Ms Lee was represented this time. Judge Sharp dismissed Ms Lee’s counterclaim and again made findings adverse to Ms Lee. While Judge Sharp accepted that there were watertightness defects, she held that Ms Lee had not shown that Composite Cladding and Signage Manufacture and Installations Ltd was responsible for them. Ms Lee appealed against the decision of Judge Sharp. She applied for leave to adduce further evidence but Wylie J dismissed that application.19 Woodhouse J heard the
appeal and dismissed it.20
Arbitration with Rob Littlejohn Builders Ltd
[45] Ms Lee’s dispute with Rob Littlejohn Builders Ltd went to arbitration. That resulted in an award on 8 November 2014. Against her run of losses, Ms Lee had a win. She obtained an award of over $700,000 against Rob Littlejohn Builders Ltd.
That appears however to have been a barren
remedy.
18 Lee v Composite Cladding and Signage Manufacture and Installations Ltd HC Whangarei, CIV-
2009-488-828, 16 December 2010.
19 Lee v Composite Cladding and Signage Manufacture and Installations Ltd [2012] NZHC 3189.
20 Lee v Composite Cladding and Signage Manufacture and Installations Ltd [2013] NZHC 354.
The Gill report
[46] In March 2011, Auckland lawyers acting for Ms Lee commissioned a further weathertightness report by a Mr Gill, a registered building surveyor. The report of
6 April 2008 is thorough and wide-ranging. It was prepared for the various cases then in progress: with Composite Cladding and Signage Manufacturing Installations Ltd, with Rob Littlejohn Builders Ltd, and the claim in the Weathertight Homes Tribunal. The significance of this report is that it found defects that had not been identified by earlier consultants. One of those defects is that plywood pre-cladding had not been sealed and joints were not taped.21 He said that as a result the barrier between the precladding and cladding was not effective and wind-driven moisture penetrated the building envelope. Ms Lee described the exterior cladding, an
aluminium composite panel, as a “rain screen”.
[47] In May 2013 the Weathertight Homes Resolution Service assessor made
an addendum to his report, which confirmed the findings
by Mr Gill. A full
reclad was recommended.
Ms Lee’s response to the council’s summary judgment
application
[48] Against the council’s unchallenged evidence that by 21 May
2008 she knew that her house had construction defects, that
it had not been
built in accordance with the Building Code, that the house leaked, that she had
taken legal advice about these problems,
had obtained advice from a consultant
on leaky buildings and was aware that the defects affected the value of the
house, Ms Lee says:
(a) The reports by Mr Beattie of Kaimamaku Consultancy Ltd can be disregarded because they were commissioned to deal with a dispute as to workmanship with Rob Littlejohn Builders Ltd, not a leaky
building claim.
21 Another is “the north-east balcony deck joined with the north wall of office 2, and that north-
east balcony deck was not built according to the approved plan”.
(b) Time stopped running when she applied for the WHRS
assessor’s
report on 12 August 2008.
(c) She is suing for the new defects identified by Mr Gill in his report, not
for defects identified earlier.
Beattie reports
[49] As to the reports by Mr Beattie, the reason for obtaining the
reports is not relevant. What counts is that through those
reports Ms Lee was
made aware of the defects in construction, including those going to water
ingress. Moreover, his reports were
only one source of her knowledge. She
also knew from observing leaks herself.
The application for an assessor’s report
[50] Ms Lee’s application on 12 August 2008 for an assessor’s
report under s 32 of the Weathertight Homes Resolution
Services Act is important
for limitation purposes under that act. Section 37 of the Weathertight Homes
Resolution Services Act says:
Application of Limitation Act 2010 to applications for assessor's report,
etc
(1) For the purposes of the Limitation Act 2010 (and any other enactment
that imposes a limitation period), the making of an application
under section
32(1) has effect as if it were the filing of proceedings in a court.
...
[51] Under s 9 of the Weathertight Homes Resolution Services Act a
person brings a claim in respect of a dwellinghouse when
they apply for an
assessor’s report under s 32.
[52] For Ms Lee’s proceeding in the Weathertight Homes Tribunal,
the effect of
s 37 is that time stopped running when she applied for the assessor’s
report on
12 August 2008. She contends that it also stopped running for this proceeding, even though the Tribunal struck out her claim under s 60(5).
[53] Cases have held that s 37 applies only to claims under that act, not to proceedings in other courts (unless they are transferred under s 119). In Bunting v Auckland City Council a claim had been found to be ineligible, but the claimants were not able to use the time of the application for an assessor’s report to say that their later proceeding in this court was in time.22 The court approved this submission
by the council:23
The respondent submits that the present case is analogous with the
circumstances that prevail when a civil proceeding is discontinued
before the
expiry of the relevant limitation period or what used to occur when the
procedural rules relating to non suit were in
force. In those circumstances, a
plaintiff could commence a second proceeding but time for the purposes of the
Limitation Act ran
from the filing of the second proceeding. A plaintiff could
not rely on the date of filing the original proceeding (once
discontinued) in order to avoid any subsequently filed proceeding being time
barred. Here the respondent contends that the application
has been extinguished
by the claim being ineligible so that any subsequent claim or proceeding (which
would include the struck out
proceeding) must qualify on its own account under
any relevant limitation period. There is no possibility of relating a later
claim
or proceeding back to the time of the filing of the original
application.
[54] In Osborne v Auckland Council the Supreme Court was invited to rule on the question, but declined to do so.24 Bunting accordingly continues to apply. It seems implicit in the judgment of the Court of Appeal in Osborne that an application for an assessor’s report under the act could not apply to a later proceeding in this court.25
In the light of these authorities it is not open to Ms Lee to rely on the
application for
an assessor’s report to say that this proceeding is in time.
[55] Ms Lee also contended that Osborne v Auckland Council helped her. The decision of the Supreme Court is primarily about eligibility criteria in the Weathertight Homes Resolution Services Act, especially s 14(a). It does not help
Ms Lee.
22 Bunting v Auckland City Council HC Auckland CIV-2007-404-2317, 13 August 2008.
23 At [22].
24 Osborne v Auckland Council [2014] NZSC 67, [2014] 1 NZLR 766 at [15].
25 Osborne v Auckland City Council [2012] NZCA 199, (2012) 21 PRNZ 76 at [10].
Fresh defects identified by Mr Gill
[56] Ms Lee argues that she is suing only in respect of the defects
identified by Mr Gill in 2011. She is not suing in respect
of the defects
identified by Mr Beattie or in the assessor’s eligibility report of 20
October 2008. Indeed, the only defect
her statement of claim alleges is that
the plywood ridged backing was not sealed and joints were not taped. She claims
that this
was discovered only in April 2011.
[57] Woodhouse J described the new defect in Lee v Composite Cladding
and Signage Manufacture and Installations Ltd, Ms Lee’s appeal from
Judge Sharp’s District Court judgment:26
As indicated in the introduction to this judgment, the aluminium cladding
panels are fixed to what is called pre-cladding. There is
a cavity between the
aluminium cladding and the pre-cladding. The cavity is maintained between the
cladding and the pre-cladding
by the installation of packers which sit between
the cladding and the pre-cladding.
The aluminium pre-cladding is intended to be a rain screen only. It is not
intended to be impermeable to all water. It is accepted
that some water will get
behind the cladding. I am satisfied from the evidence in this case, as was the
Judge in the District Court,
that the pre-cladding may be described as the
primary line of defence against water ingress which might cause damage to the
structure
of the house. Water that could penetrate the pre-cladding does get
into the cavity. The pre-cladding for this house was
required to be
impermeable to water. The pre-cladding is plywood panels. The pre-cladding
specifications to ensure impermeability
to water ingress are that, amongst other
things, the panels are to be treated and sealed plywood and the joints between
the pre-cladding
panels are to be sealed with tape. The evidence is that the
joints between pre-cladding panels are not sealed and there is some suggestion
of other defects. As earlier recorded CCS had no responsibility for the
pre-cladding. The design of the pre-cladding, as just described,
is intended to
prevent ingress of water that gets into the cavity before it drains away or
evaporates. The aluminium cladding is
also required to be designed and installed
in ways which will enable water that does get into the cavity to drain
away.
[58] In September 2014, Ms Lee prepared an amended statement of claim but that was not filed in court. The defects in that draft pleading are more extensive. They include defects identified by Mr Beattie and in the assessor’s eligibility report. It is
open to a plaintiff facing a summary judgment application to amend a
statement of
claim to show a viable case. But Ms
Lee’s proposed amended pleading does not help for the present point, given
that she is
relying on the late discovery of additional defects by Mr
Gill.
[59] The question is whether time under s 4(1)(a) of the Limitation Act
1950 can be deferred because not every defect is identified
at the time of
discovering damage.
[60] In Pullar v R (acting by and through the Secretary for Education), the Ministry of Education sued for weathertightness defects in Ruatoki School.27 The work was completed during 1996. In October 1997 the ministry’s architects wrote to the contractors regarding leaking windows, plaster and paintwork. In 1998 the ministry asked a consultant to provide a report as to defects in the building. The ministry received that in late December 1998. The ministry commissioned a follow- up report in 1999. It issued a proceeding in May 2005, suing the building contractors and the architects in tort. On the building contractors’ summary judgment application, the Court of Appeal held that the claim was time-barred,
applying the Hamlin test. The court suspected that any cause of action in negligence had accrued in October 1997 when the architect requested the contractor to return to
fix leaking windows and other damage. It went on to
say:28
And:29
But, even if we are wrong about that, there can be no doubt whatever that a
cause of action had definitely accrued by the time of
Mr Barnett’s
inspection and report of December 1998. We do not need to ask, in Hamlin
terms, whether “any reasonable [building] owner” would or should
have called in “an expert” by then: the
Ministry after all had
called one in. The defects were obvious. So was the remedial action
required.
...It is not necessary, in order for time to start running, to be able to
pinpoint with precision the exact cause of every defect.
Indeed, that would
frequently mean time could not start running until the remedial work was under
way! That would in turn mean that
the building owner could not sue the builder
in advance of the repair work as no cause of action would have by
then
accrued. That is not and never has been the law. What one is concerned to
ascertain is when economic loss occurred: when was the
market value of the
building affected? We suspect the market value of this building was affected
back in 1997. But it was clearly
affected by the time the Barnett report was
prepared in December 1998.
27 Pullar v R (acting by and through the Secretary for Education) [2007] NZCA 389.
28 At [16].
29 At [19].
[61] Similarly in this case, it is unnecessary to enquire whether the
building owner should have called in an expert, because
in this case, with legal
advice, Ms Lee did call in a consultant who held himself out as having expertise
in weathertightness and
building quality issues. From the time of Mr
Beattie’s report of 30 April 2008 if not earlier, Ms Lee had discovered
actionable
damage. Time started to run from then, if not earlier. On the basis
of Pullar, the later discovery of further defects by Mr Gill does not put
back the point when time starts running under s 4(1)(a).
[62] In response Ms Lee referred to Burns v Argon Construction
Ltd.30 That is a case of intermittent damage in a leaky
building case. Pullar was not followed. Asher J set aside a decision of
the Weathertight Homes Tribunal striking out a claim on the ground that it was
barred
under s 4 of the Limitation Act 1950. Defects had been identified and
repairs carried out, but later the defects in the house were
found to be more
serious, going to design as well as construction. The discovery of the more
serious problems was held arguably
to give rise to a new cause of action, so as
to bring the claim within time. The limitation question could not be decided
on the
pleadings.
[63] Intermittent damage is to be distinguished from one-off
damage and continuous damage in limitation cases. In Bowen v Paramount
Builders (Hamilton) Ltd Cooke J said:31
I agree with the President and Woodhouse J that the mere fact
that a purchaser was later in the chain than the present
plaintiffs, or that a
much longer time went by before damage occurred, should not automatically rule
out a cause of action against
the builder. Causation would always have to be
proved, and a reasonable expectation of adequate intermediate examination would
always
be a defence. In practice those two difficulties would militate against
successive actions, which are certainly not to be encouraged,
but in principle I
would adopt as applicable the following passage in Salmond on Torts:
"Where the act of the defendant is actionable per se, there is no doubt that
all damage, both actual and prospective, may and must
be recovered in one
action. But where the act of the defendant is not actionable per se, but is
actionable only if it produces actual
damage, and it produces damage twice at
difference times, is there one cause of action, or are there two? If, for
example, the defendant
by an act of negligence has created a source of
danger which on two
30 Burns v Argon Construction Ltd HC Auckland CIV-2008-404-7316, 18 May 2009.
31 Bowen v Paramount Builders (Hamilton) Ltd [1977] 1 NZLR 394 (CA) at 424.
successive occasions causes personal harm to the plaintiff, is the plaintiff
barred from recovery for the second harm because he has
already recovered
damages or accepted compensation for the first? Both on principle and on
authority it seems that when an act is
actionable only on proof of actual
damage, successive actions will lie for each successive and distinct accrual of
damage. But where
the damage sued for in the second action is not in reality
distinct from that sued for in the first, but is merely a part of it or
consequential upon it, it cannot be recovered. For it is clear that the second
damage in order to be recoverable in a second action
must arise directly from
the wrongful act of the defendant ant [sic.] not indirectly through the damage
already sued for. In other
words, compensation for the first damage includes
compensation for all the ulterior consequences of that damage whether already
accrued
or not, but it does not include compensation for entirely distinct
damage accruing from the defendant's act independently of the
damage first sued
for".
That principle may be quite easily workable when the plaintiff has suffered
personal injuries from the same cause on different occasions.
Its application is
less straightforward when property suffers damage more or less continuously. In
cases of interference with the
natural support of land it is well settled that
each further slip creates a fresh cause of action: Morris v Redlands Bricks
Ltd, per Lord Upjohn. Salmond speaks of that kind of case as one of
"intermittent" damage. In Maberley v Henry W Peabody & Co of London
Ltd, a nuisance case and the main authority cited in Salmond for the passage
already set out, Stable J went as far as to say:
"It may well be that a fresh cause of action arises as each brick topples
down, and that there is a continuing cause of action until
the root of the
trouble is eradicated . . ." (ibid, 194).
Presumably, however, it is a question of fact and degree whether damage is
sufficiently distinct to result in a separate cause of
action. On the evidence
in the present case it seems to me that the damage suffered by the building was
not truly continuous; and
that between the slight damage during the McKays'
ownership and the considerable damage after the Bowens bought there were a
difference
and an interval marked enough to justify treating the latter damage
as distinct.
(Citations omitted.)
[64] In S v G Gault J said:32
Separate and distinct damage may give rise to a separate cause of action in
negligence: Bowen v Paramount Builders (Hamilton) Ltd, Mount
Albert Borough Council v Johnson, and where the cause of action is in
respect of sufficiently separate and distinct damage or injury the reasonable
discoverability
test might be applied to that.
(Citations omitted)
32 S v G [1995] 3 NZLR 681 (CA) at 687.
[65] The courts have found separate causes of action in some cases of successive ownership where a subsequent owner has sued: Bowen v Paramount Builders (Hamilton) Ltd and Mt Albert Borough Council v Johnson,33 but that is not a test for distinct causes of action and, in any event, that aspect is not present here. In some cases, a separate cause of action has been found when initial damage has been repaired, but it is later found that the cause of damage is more deep-rooted: Mt Albert Borough Council v Johnson and Burns v Argon Construction Ltd. But the test for a separate and new cause of action cannot turn on whether intermediate
repairs have been carried out. The fact that Ms Lee has not carried out
intermediate repairs does not count conclusively against
her.
[66] A better way to assess the matter is to consider the effect of
upholding Ms Lee’s submission. On her argument,
she could still
not sue for damage discovered more than six years before she sued the
council, but she could sue for the plywood
ridged backing not being sealed and
joints not taped. Those are the only relevant defects discovered inside the six
years. Such
a claim would not allow her to claim for damage to the house from
defects in other parts of the house. But if the damage she says
she can sue
for as a newly-discovered defect was discoverable more than six years before she
began this proceeding, her claim is
still statute-barred. It is not a case of
saying that she ought to have known. Such a finding is likely to require a
fuller hearing
with expert evidence. It cannot be made in this summary judgment
application.
[67] But there is unchallenged evidence that she was on notice that the
defects in construction would require the replacement
of cladding, the matter
she now raises as a new matter. In her affidavit in opposition to the
council’s security for costs
application, she said:34
It was at the final inspection, the inspector showed me that exterior flash
around openings require to be installed to tape further
down. (Please see the
photocopy below). This is the exterior, it can be fixed very easy. And the
exterior cladding (joints, corner),
the exterior cladding is “rain
screen” only. The importance of requirement is the plywood ridged
backing have to be sealed and joints taped with approved tape
to form
rigid air barrier to perform the function of weathertightness. The exterior
cladding (joints,
33 Mt Albert Borough Council v Johnson [1979] NZCA 46; [1979] 2 NZLR 234 (CA).
34 At [11].
corner) is the nature of this kind of the cladding installation. It has
been noted in the suspension letter about the building consent
application from
WDC.
[68] Mr Beattie’s report of 5 February 2008 advised her that most of the exterior would not meet Building Code requirements in weathertightness and resolution would require removal of extensive sections of cladding.35 He repeated this in his
report of 30 April 2008. 36 Her email of 18 May 2008 to
Composite Cladding and
Signage Manufacture and Installations Ltd shows that she understood
this.37 Her lawyer’s letter of 19 May 2008 to Rob Littlejohn
Builders Ltd claimed that defects would require reinstating all “cladding
and soffits”.
[69] It may be that by 21 May 2008 Ms Lee’s knowledge of the
cladding defects was not as full as it is now, but she did
know enough to
realise that the value of the house was adversely affected by defects in the
cladding system. What she found out
from Mr Gill’s report did not change
that damage or point to fresh damage. This is a continuous damage case. Mr
Gill’s
report did not show a new cause of action.
Result
[70] The council has shown by a strong margin that Ms Lee
discovered the damage to her house before 21 May 2008.
She knew that it had
defects, that it did not comply with the Building Code, that those defects
caused the house to leak and that
they lowered the value of the house. She also
knew that the defects went to the weathertightness of the cladding system.
None
of the matters that she has raised change the fact that her cause of action
against the council arose more than six years before
she began this
proceeding. Accordingly the council succeeds in its application. That
brings this proceeding to an end.
[71] I make these orders;
(a) I grant summary judgment to the Whangarei District
Council.
35 At [19] above.
36 At [27] above.
37 At [30] above.
(b) I award costs to the council against Ms Lee. If the parties cannot agree
costs, memoranda may be filed.
.......................................
Associate Judge R M Bell
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2015/2777.html