|
Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 21 September 2015
IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY
CIV-2014-485-9311 [2015] NZHC 535
|
BETWEEN
|
ASPEC CONSTRUCTION
WELLINGTON LIMITED Plaintiff
|
|
AND
|
ANDREW JAMES FAWCET Defendant
|
|
Hearing:
|
6 October 2014 and 13 February 2015
|
|
Counsel:
|
M J Leggat for Plaintiff
T J Herbert for Defendant
|
|
Judgment:
|
23 March 2015
|
JUDGMENT OF ASSOCIATE JUDGE SMITH
[1] The plaintiff (Aspec) applies for summary judgment against Mr
Fawcet. It asks for an order directing Mr Fawcet to pay
it the sum of
$327,500, plus interest and costs.
[2] Mr Fawcet was late filing his notice of opposition to the summary
judgment application, and was required to file an application
for an extension
of time to oppose the application. Mr Fawcet’s application for extension
of time was heard together with
Aspec’s application for summary
judgment.
Background
[3] Aspec is a construction company. One of its projects was the construction of an apartment development in Evans Bay Parade, Wellington. The developer was a company called Delta Developments Limited (Delta), of which Mr Fawcet was a
director.
ASPEC CONSTRUCTION WELLINGTON LIMITED v ANDREW JAMES FAWCET [2015] NZHC 535 [23
March 2015]
[4] By 2012 some of the apartments had leaks, and a dispute arose
between Aspec and Delta. An arbitration award was delivered
in October 2012
determining the final amount due by Delta to Aspec, and Aspec
subsequently obtained a judgment in this
court requiring Delta to pay it the
amount of $571,182.46 plus interest and costs.
[5] Delta’s liability under the judgment was settled on
terms set out in a settlement deed dated 12 June 2013
(the deed). Mr Fawcet
was a party to the deed. Under the deed, Delta was required to pay Aspec $49,500
by 28 June 2013, and by the
same date it was to procure the delivery to Aspec of
330,000 unencumbered Barter Card Trade Dollars. Those obligations were duly
discharged by Delta.
[6] As their name suggests, Barter Card Trade Dollars (which I will
refer to as “trade dollars”) are a form of alternative
“currency”, which participating members use in member-to-member
transactions for the sale and purchase of goods and services.
The detail of how
the system works need not concern us for the purposes of this judgment, but an
extract from the Barter Card website
which Mr Fawcet produced states that
purchases made with trade dollars allow a company to buy goods and services at
an effective
discount equal to its gross margins, and conserve cash reserves
which would normally be depleted by such purposes. The website
extract says
that one trade dollar is equivalent to $1 NZ for all intents and purposes,
including tax, GST and pricing. That “exchange
rate” has been
accepted by Mr Fawcet in his opposition to the summary judgment
application.
[7] Under the deed, Aspec was free to use the trade dollars to acquire such goods or services as it saw fit. But to the extent it had not used the trade dollars by
18 June 2014, the deed conferred on Aspec the right to “put” part or all of the trade dollars it still had on hand to Mr Fawcet, in exchange for cash. If it wished to exercise that right, it had to do so within a two month “window” commencing on
18 June 2014 and ending on 18 August 2014.
[8] Aspec exercised that right by serving formal notice on Mr
Fawcet on
18 June 2014. It appears that it had used only 2,500 of the trade dollars it had received from Delta; its notice required Mr Fawcet to pay the sum of $327,500 to it
within ten working days, on receipt of which Aspec would transfer 324,257.43
trade dollars to Mr Fawcet.1
[9] Mr Fawcet did not comply with the notice.
[10] Aspec then issued its proceeding in this Court, claiming the New
Zealand dollar equivalent of 327,500 trade dollars.
[11] Under cl 7.2 of the deed, Aspec undertook to take all reasonable
steps to procure that relevant subcontractors (being those
who had provided
relevant warranties of their work) would attend the development to remedy leaks
in four specified units at the development,
within five working days after
notification to Aspec of the details of the leaks in those units. Mr Fawcet
says that Aspec never
did that, and that the discharge of Aspec’s
obligations under cl 7.2 was a condition precedent to its right to call on him
to exchange cash for the trade dollars, which has not been met.
[12] As a second string to his bow, Mr Fawcet contended at the
hearing on
6 October 2014 that Aspec could not obtain judgment for the $327,500 it
claims, because it still has the 327,500 trade dollars, and their value
is equal to (if not slightly greater than) the amount which Aspec now claims.
He argued
that Aspec has suffered no loss.
[13] Aspec denies that there has been any failure on its part to discharge its obligations under cl 7.2. But more simply, it denies Mr Fawcet’s contention that the discharge of those obligations was a condition precedent to its right to call on him to pay cash for the trade dollars. It points out that the clause in the settlement deed under which it was entitled to serve notice on Mr Fawcet requiring him to exchange cash for the trade dollars was not made conditional on Aspec performing its own obligations under cl 7.2. It also relies on a “no set-off or deduction” provision which
was included at cl 5.1 of the settlement deed.
1 Under cl 3.3 of the deed, Aspec was entitled to deduct the 1 per cent fee (expressed in trade dollars) which it would incur on the transfer of trade dollars to Mr Fawcet. The 324,257.43 trade dollars Aspec would transfer to Mr Fawcet represented the balance (99 per cent) of the trade dollars after deduction of the 1 per cent fee.
[14] On the “no loss because Aspec still holds the 327,500
trade dollars” argument, Aspec accepted at the
6 October 2014 hearing
that any judgment entered in its favour should be conditional on it transferring
the equivalent number of
trade dollars to Mr Fawcet on him satisfying the
judgment.
Events subsequent to the 6 October 2014 hearing
[15] On 10 October 2014 I issued a minute in which I granted leave to Aspec to amend the claim for relief in its statement of claim, by substituting for the existing (simple debt) claim a claim for an order directing Mr Fawcet to pay Aspec the sum of $327,500 on receipt of which Aspec would transfer to him 324,256.43 trade dollars in accordance with cl 3.3 of the deed. I noted in issuing that minute that there could be no real doubt about what Aspec was seeking, as its statement of claim referred expressly to its obligation to transfer trade dollars to Mr Fawcet on receipt of his cash payment. I referred to the Court of Appeal decision in
Cegami Investments Ltd v AMP Financial Corporation (NZ) Ltd,2
in which the Court
held that there is no good reason why the ordinary rules as to amendments
of pleadings should not apply in summary judgment proceedings
if the justice of
the case so requires, and if there is no prejudice to the defendant. I allowed
Aspec a period of seven days to
file any amended statement of claim, and made
directions permitting Mr Fawcet to file a further affidavit or affidavits, and
further
written submissions, directed to the new claim for relief. Provision
was made for the filing of reply affidavits and written submissions
by Aspec,
and I directed that if either party wished to make supplementary oral
submissions, they could apply by memorandum for the
allocation of a further
hearing date to hear the supplementary submissions. Aspec filed an amended
statement of claim in response
to that minute, on 17 October 2014.
[16] In his written submissions made following the filing of Aspec’s amended statement of claim, Mr Herbert submitted that the amended claim remained deficient, in that the pleading did not include an averment of Aspec’s ability and willingness to
perform its obligations under the contract. Mr Herbert
submitted that such a
2 Cegami Investments Ltd v AMP Financial Corporation (NZ) Ltd [1990] 2 NZLR 308; (1990) 2
PRNZ 271.
pleading is a necessary requirement in any claim for specific performance.
Aspec responded by filing, on 7 November 2014, a second
amended statement of
claim which included a “ready, willing and able to perform”
pleading. It also filed an amended
interlocutory application for summary
judgment, and a supporting affidavit verifying its second amended statement of
claim.
[17] Mr Fawcet objected to the filing of these further documents, on the
basis that they had been filed without leave. I convened
a telephone conference
to deal with that objection.
[18] By minute dated 2 December 2014, I granted leave to Aspec to file the second amended statement of claim and the further verifying affidavit and amended application for summary judgment. I noted that the leave granted to Aspec on
10 October 2014 had been intended to allow it to properly plead what was clearly its case, namely that it wanted an order directing Mr Fawcet to specifically perform what it alleged was his contractual obligation to pay the requisite sum in New Zealand dollars in exchange for the delivery to him of the appropriate number of trade dollars. I accepted that the terms of the leave to amend given on
10 October 2014 had been too narrow, in that they did not allow amendments to
anything more than the plaintiff’s claim for relief.
The justice of the
case required that the plaintiff should also be permitted to amend its pleading
to include a “ready willing
and able to perform”
averment.
[19] By further directions made on 2 December 2014, I made provision for
the filing of any further affidavits and/or written submission
the parties may
wish to file, and directed that either party may apply for a further hearing to
hear supplementary oral submissions.
[20] Further written submissions were received from counsel, and I heard
further oral argument on 13 February 2015.
Legal principles applicable to summary judgment
[21] The principles to be applied in considering an application for summary judgment have been clearly established through decisions of the Court of Appeal
such as Pemberton v Chappell,3 Grant v NZMC
Ltd4 and Westpac Banking Corporation v M M Kembla New Zealand
Ltd.5 The following broad principles are to be
applied:
(a) The plaintiff must satisfy the Court that the defendant has no
arguable defence to the claim brought against it. The issue
is whether there is
a real question to be tried.
(b) It is generally not possible to determine disputed issues of fact
based on affidavit evidence alone, particularly when issues
of credibility
arise. Issues of law, even though they may be complex, can, however, be
determined in an application for summary
judgment.
(c) Although the Court should adopt a robust approach, summary
judgment may be inappropriate where the ultimate
determination turns on a
judgment that can only properly be reached after a full hearing of all the
evidence.
The issues to be determined
[22] The following issues fall to be determined:
(1) Should Mr Fawcet be granted an extension of time to oppose the
summary judgment application?
(2) On the true construction of the settlement deed, was Aspec entitled
to give written notice to Mr Fawcet requiring him to
pay cash for the trade
dollars, if Aspec had not performed its obligations under cl 7.2?
(3) If the answer to issue 1 is “no”, has Aspec shown, to a standard
sufficient to entitle it to summary judgment, that it has discharged
its clause 7.2 obligations?
3 Pemberton v Chappell [1986] NZCA 112; [1987] 1 NZLR 1 (CA) at 3.
4 Grant v NZMC Ltd [1988] NZCA 135; [1989] 1 NZLR 8 (CA).
5 Westpac Banking Corporation v M M Kembla New Zealand Ltd [2000] NZCA 319; [2001] 2 NZLR 298 (CA).
(4) If Aspec was entitled to give the written notice to Mr Fawcet, is
the appropriate remedy (following Mr Fawcet’s failure
to comply with the
notice) an order for specific performance, directing Mr Fawcet to pay $327,500
to Aspec in exchange for the 324,256.4
trade dollars?
[23] I will consider each issue in turn.
Issue 1: Should Mr Fawcet be granted an extension of time to oppose
the summary judgment application?
[24] I am satisfied that an extension of time should be granted. Mr Fawcet has explained that he was not able to contact one of his witnesses, Mr Charlett, until
25 August 2014, only two days before the notice of opposition was due to be
filed. Mr Charlett had been overseas until 23 August 2014.
Mr Fawcet was unable
to get Mr Charlett’s affidavit completed until 29 August 2014, and
he explains that, because
there was a degree of “interlinking”
between Mr Charlett’s affidavit and his own affidavit, neither affidavit
was
sworn until 29 August 2014. The documents were filed on 1 September
2014.
[25] The last day for filing a notice of opposition was 27 August 2014, being three working days before the first call of the summary judgment application on
2 September 2014.
[26] In my view, the delay in filing has been reasonably explained, and
Mr Leggat has not pointed to any significant prejudice
his client will suffer if
an extension of time is granted. There will accordingly be an order
extending the time for
Mr Fawcet to file his notice of opposition and
affidavits in opposition, to the dates on which those documents were
filed.
Issue 2: On the true construction of the settlement deed, was Aspec
entitled to give written notice to Mr Fawcet requiring him
to pay cash
for the trade dollars, if Aspec had not performed its obligations under cl
7.2?
Relevant Provisions of the Deed
[27] Clauses 3, 5, 7, and 14 of the deed materially provide:
3 Buyback
3.1 If, no sooner than 18 June 2014 and no later than 18 August 2014,
Aspec retains any of the 330,000 [trade dollars] which
were received under
clause 1.2, Aspec may, by written notice to [Mr Fawcet], require [Mr
Fawcet] to exchange the number
of [trade dollars] specified in the notice
for the equivalent number of New Zealand Dollars.
3.2 Upon receiving a notice under clause 3.1, [Mr Fawcet] will, within
10 working days, pay to Aspec the specified sum of New Zealand
Dollars, time being of the essence.
3.3 Upon receipt of payment of the sum required to be paid under the
notice referred to in clause 2.1 above, Aspec will pay
to [Mr Fawcet] the number
of [trade dollars] specified in the notice (minus any [trade dollars] fees that
Aspec may incur as a result
of such transfer).
3.4 For the avoidance of doubt, Aspec may expend [the trade dollars] in
its complete discretion and shall be under no obligation
to spend, or to
endeavour to spend, any or any minimum number of the [trade dollars].
5 No Counterclaim, Set-Off or Deduction
5.1 Neither [Mr Fawcet] nor Delta may make any counterclaim against
Aspec or exercise any right of set-off or deduction against,
or in respect of,
all or any portion of any payment payable by either of them under this
Deed.
7 Release of Aspec under Contract
7.1 Subject to clause 7.2, Delta will have no further claim on Aspec
under the Contract (whether or not the existence of that
claim or possible claim
is known to Delta at the date of this Deed).
7.2 Notwithstanding clause 7.1, Aspec will, promptly, and no later than
five working days after notification of the details
of the leaks in relation to
Units S204, S208, S505 and S506 at the Development (by Aspec or otherwise), take
all reasonable steps
to procure that the relevant sub-contractor (being the
sub-contractor that has warranted any defective work resulting in the leak)
attend the Development to remedy those leaks as quickly as practicable and in a
workmanlike manner.
7.3 Other than as set out above, Delta agrees to indemnify Aspec
against any claims made against Aspec by any owners
of units in the
Development.
9 AJF Guarantee
9.1 Guarantee: This clause shall apply if any notice is served by any official assignee or receiver, manager, liquidator or other personal representative appointed as a result of any insolvency of Delta or any other person entity which seeks to set aside, in whole or in part, the
[$49,000 cash payment made by Delta] or the transfer of [the trade dollars
provided by Delta to Aspec].
9.2 Payment: In the event of a notice such
as referred to in subclause 9.1 being served, AJF will, on demand by Aspec,
pay to Aspec the
amount of the payment or the dollar equivalent of the [trade
dollars] (as the case may be) which is/are sought to be set aside, without
any
deduction, set-off or counterclaim.
9.3 Absolute Liability: It is the intent of
the parties that the guarantee and obligations of AJF under this Deed will be
absolute and unconditional
in any and all circumstances and the liability of AJF
under this Deed will not be abrogated, prejudiced or affected by any covenant
or
obligation of Aspec being unenforceable in any way or by:
...
(b) any omission or neglect;
...
(d) any avoidance for any reason whatever by statute or
otherwise of any payment by or on behalf of Delta or AJF to
Aspec;
...
(f) any failure or breach of any express or implied condition upon
which this Deed is based;
...
(j) any other dealing, matter, event or thing which, but for this
provision, could or might operate to abrogate, prejudice
or affect this
Deed.
14 Entire Agreement
This Deed constitutes the entire agreement between the parties with respect
to the payments now agreed between them.
[28] The reference to “AJF” in cl 9 is a reference to Mr
Fawcet.
Submissions for Mr Fawcet
[29] For Mr Fawcet, Mr Herbert submits that the settlement deed was intended
to involve the following process:
(I) Delta would procure payment of the 330,000 trade dollars
on
28 June 2013.
(II) Aspec was then to use its best endeavours to procure the remedy of
various leaks at the development, using trade dollars
as necessary.
(III) After 18 June 2014, on the basis that Aspec would by then have
satisfied the cl 7.2 condition, Mr Fawcet was required (on
demand by Aspec) to
exchange any remaining trade dollars in Aspec’s possession for the
equivalent number of New Zealand dollars.
[30] Mr Herbert submits that Aspec has failed to show that it
used its best endeavours to procure the remedy of the
various leaks, and on
that basis was never entitled to make demand on Mr Fawcet for the trade
dollars/cash exchange.
[31] In answer to Aspec’s reliance on the “no set-off or
deduction” provision at cl 5.1 of the settlement deed,
Mr Herbert submits
that Mr Fawcet’s defence is not a counterclaim, set-off or deduction. As
he put it in his written submissions,
the deed is “layered”, so that
the obligation to exchange cash for trade dollars is conditional on Aspec
performing its
obligations under cl 7.2. He submits that such an
interpretation makes sense in the context of the deed, because the trade dollars
were needed to pay for the procurement of the sub-contractors to carry out the
repairs. There was no benefit to Delta or to Mr Fawcet
prior to the repairs
having taken place.
[32] In his oral submissions, Mr Herbert addressed the question of the factual matrix in which the settlement deed is to be interpreted. Two of the obvious “background” factors were said to be that the development was known to have leaks, and that Aspec had shortly before the completion of the deed obtained a large High Court judgment against Delta. Against that background, Mr Herbert questioned why the parties provided for a gap of a little over one year before Aspec could serve notice on Mr Fawcet requiring him to pay cash for the trade dollars. His answer was that the gap was intended to allow Aspec time to arrange for the leaks in the four units referred to cl 7.2 to be fixed. A quid pro quo was intended – Aspec fixes the leak, then it is entitled to redeem its trade dollars for cash.
[33] As for cl 9 of the deed, Mr Herbert submits that the
entire clause was intended to apply only in the circumstances
described in
sub-cl 1. None of those circumstances had arisen when Aspec served its notice
on Mr Fawcet. Mr Herbert also submits
that cl 5.1 would be redundant if cl 9
had been intended to apply in all circumstances (i.e. if cl 9 was not limited to
the circumstances
described in sub-cl 1).
Submissions for Aspec
[34] For Aspec, Mr Leggat submits that if Mr Fawcet’s payment
obligation in cl 3.2 was intended to be conditioned on performance
by Aspec of
its obligations under cl 7.2, the deed would have expressly said so. He also
submits that Aspec’s obligations
under cl 7.2 were for the benefit of
Delta, and are not able to be enforced by Mr Fawcet.
Discussion
[35] It seems to me that there is force in Mr Leggat’s submissions on this issue. On its face, the cl 3.1 entitlement of Aspec to serve notice on Mr Fawcet, and his obligation under cl 3.2 to pay the amount set out in the notice, were unconditional (assuming the notice was served within the window of time between 18 June and 18
August 2014). One would have expected that if the intention had been to
make Aspec’s entitlement under sub-cl 3.1 and 3.2
conditional in the
manner for which Mr Fawcet now contends, it would have been a simple enough
matter for the drafts- person to have
said so.
[36] Sub-clauses 3.1 and 3.2 must also be read with cl 5.1, under which neither Mr Fawcet nor Delta were to “exercise any right of set-off or deduction against, or in respect of, all or any portion of any payment payable by either of them under this Deed”. Mr Fawcet’s obligation to pay cash for the trade dollars on receipt of written notice under cl 3.1 would have been a “payment payable” by him under the deed, and the effect of cl 5.1 is that Mr Fawcet was not entitled to deduct or set-off any sum against such a payment.
[37] Mr Herbert submits that the issue is not one of Mr Fawcet seeking to
make a counterclaim, set-off or deduction, but whether
a necessary pre-condition
to Aspec’s right to give the notice had or had not been met.
[38] I accept that submission as far as it goes, but the submission
remains entirely dependent on reading in a “subject
to compliance with its
obligations in cl 7.2” qualification on Aspec’s rights under cl 3.1,
when no such qualification
appears in cl 3 itself.
[39] I am not convinced by Mr Herbert’s argument that the deed was
deliberately “layered” in the sense referred
to at para [31]
above, with the period of approximately a year before Aspec would be
entitled to “put” the trade
dollars to Mr Fawcet being intended to
allow Aspec to expend the trade dollars on the procurement of the subcontractors
to carry
out the repairs. First, the wording of cl 7 of the deed does not
suggest that the parties contemplated that Aspec would be paying any
subcontractor to do remedial work – the clause only required
Aspec to take reasonable steps to procure that
subcontractors who had
warranted defective work which had resulted in the leaks would attend at the
development to remedy their defective
work. Those subcontractors would
presumably have been obliged to cover the costs of the remedial work
themselves.
[40] Secondly, Mr Herbert’s submission does not, in my view, have sufficient regard to the fact that Aspec was fully entitled to use the trade dollars as it saw fit when it received them from Delta in June 2013. It might have used them in July
2013 to purchase goods or services which were entirely unrelated to the development, in which case it would have had no need to “put” any trade dollars to Mr Fawcet in the two month period provided for in cl 3.1 of the deed. Looked at in that way, it can be seen that the intention was that Aspec would receive “full value” under the deed immediately it was paid by Delta, possibly before it received any notice under cl 7.2 setting out details of leaks in the four units. Clauses 3.1 and 3.2 of the deed were only concerned with Aspec’s entitlement to convert all or part of the value it had already received into a different and presumably more liquid form of value, namely cash.
[41] I also accept Mr Leggat’s submission that cl 7 is not
concerned with the relationship between Aspec and Mr Fawcet at
all; it records a
settlement reached between Aspec and Delta. Clause 3, on the other hand, is
concerned only with the relationship between Aspec and Mr Fawcet.
The unqualified obligation on Mr Fawcet to pay on demand, read with
the
specific reference to Mr Fawcet in cl 5.1 and the fact that cl 7.2 appears to be
concerned only with possible claims by Delta against Aspec, leads me to
conclude that Aspec’s right to “put” any remaining trade
dollars to Mr Fawcet was not
qualified in the manner for which he now
contends.
[42] That interpretation seems to me to be consistent with the emphasis in cl 9 of the deed on the obligations of Mr Fawcet being “absolute and unconditional in any and all circumstances” – see cl 9.3, under the sub heading “Absolute Liability”. Even if cl 9 was only intended to operate in the circumstances described in cl 9.1 (and it is common ground that none of those circumstances apply), it is noteworthy that Mr Fawcet’s obligation under cl 9.2 to make payment to Aspec was again not made subject to any condition in respect of the discharge of Aspec’s cl 7.2 obligations. If Mr Fawcet had no ability to delay or defer payment to Aspec under cl
9.2 of the deed on account of alleged failure by Aspec to comply with its cl
7.2 obligations, it is not clear why any different approach
would have been
intended to apply to Mr Fawcet’s payment obligation under cl
3.2.
[43] It is not necessary for me to make any finding on the point, but I note also that the “Absolute Liability” provisions at cl 9.3 of the deed appear on their face to have been intended to apply not just to the guarantee which is included at cl 9.1 (which I accept had no application) but also to the (presumably wider) “obligations of [Mr Fawcet] under this Deed”, and the “liability of [Mr Fawcet] under the Deed”. The draftsperson did not use the expression “under this clause” in the introductory part of cl 9.3. If cl 9.3 were given that broader interpretation, Mr Fawcet’s obligation to pay under cl 3.2 would have been “absolute and unconditional”, and would not have been “abrogated, prejudiced or affected” by ... “(f) any failure or breach of any express or implied condition upon which the Deed is based”. I think that provision would have been broad enough to catch any breach by Aspec of its obligations under cl 7.2.
[44] I conclude, on the plain wording of the deed, that there is no basis for “grafting onto” Mr Fawcet’s cl 3.2 payment obligation any condition relating to performance by Aspec of its cl 7.2 obligations. Neither party has pointed to anything in the background circumstances leading to the execution of the deed which would suggest any different conclusion. The fact that Aspec had obtained an arbitration award (on which it had entered judgment) for a sum significantly in excess of the
$49,000 and 330,000 trade dollars for which Delta agreed to settle the
judgment debt suggests that Aspec was probably holding
most of the cards
in the settlement negotiation, and was thus able to obtain from Mr Fawcet an
unqualified undertaking to “take
out” any remaining trade dollars
Aspec might still hold after a year.
[45] My answer on Issue 2 is “yes”.
Issue 3: If the answer to issue 1 is “no”, has Aspec
shown, to a standard sufficient to entitle it to summary
judgment, that it has
discharged its clause 7.2 obligations?
[46] In view of my findings on Issue 2, there is no need to consider this
question.
Issue 4: If Aspec was entitled to give the written notice to Mr Fawcet, is
the appropriate remedy (following Mr Fawcet’s failure
to comply with the
notice) an order for specific performance, directing Mr Fawcet to pay $327,500
to Aspec in exchange for the
324,256.4 trade dollars?
The parties’ submissions
[47] Mr Fawcet submits that specific performance is not normally available on a claim for payment of a sum of money. He refers to the text Civil Remedies in New Zealand,6 where the authors state that “specific performance will not generally be available to enforce a contractual obligation to pay money, because damages will be adequate”. However, if a purchaser is entitled to specific performance because damages are not an adequate remedy, the vendor will equally be entitled to specific
performance, even though he or she is only entitled to receive a payment
of money.7
6 Andrew McIntyre “Specific Performance” in Peter Blanchard (ed) Civil Remedies in New
Zealand (Thomson Reuters, Wellington, 2011) at 8.7.2.
7 Turner v Bladin [1951] HCA 13; (1951) 82 CLR 463 (HCA), cited in McIntyre above n 5 at 8.7.2, n 57.
[48] Mr Herbert submits that damages will be an adequate remedy in
this case, and that there are no special circumstances which would
overcome what he described
as the “general presumption” that
specific performance will not be available to compel an obligation to pay
money. He submits that there is simply no evidence to support Aspec’s
claim that damages would not be an adequate remedy.
[49] In addition, Mr Herbert submits that Aspec is itself in breach of
contract and has not shown that it has the ability to perform
its obligations
under the deed – he submits that there is no evidence that Aspec
will be capable of procuring the
subcontractors to attend the site to carry
out necessary remedial work.
[50] Mr Herbert further submits that the Court will not
intervene to compel specific performance of only part of the
contract.8
[51] In response, Mr Leggat says that the deed created not simply an
obligation on Mr Fawcet to pay money, but reciprocal obligations
on both
parties. He submits that, in effect, Mr Fawcet is seeking to re-write the deed
by asserting a right to say “no thanks,
you keep the trade dollars”.
Mr Leggat further submits that the deed contains entirely separate and discrete
rights and obligations,
and that Mr Fawcet is neither entitled to the benefit of
Delta’s rights under the deed nor liable for the discharge of
Delta’s
obligations (except in the circumstances provided for in cl 9 of
the deed).
[52] Mr Leggat submits that the “ready, willing, and able”
requirement of an action for specific performance is to
be considered in
substance, rather than on the basis of any “technical”
approach.9 He refers to the affidavit of Aspec’s managing
director, Mr Wendon, in which Mr Wendon confirms Aspec’s readiness and
willingness to perform, and says that that evidence is sufficient.
[53] In response to Mr Herbert’s submission that the Court will not enforce part of
a contract, Mr Leggat submits that Aspec is seeking to enforce all of
Mr Fawcet’s obligations, which are entirely separate from Delta’s
rights and obligations under the
9 Referring to Hurrell v Townend [1982] 1 NZLR 536 (CA) at 550.
deed. Any reluctance of the Courts to order specific performance of only certain obligations under a contract (which is not a rigid rule anyway) has no application where a contract is divisible. The Court may even order specific performance of separate obligations between the same parties.10 Mr Leggat submits that no issue can arise where all of the obligations between two parties to a tripartite agreement are being ordered to be performed, and the other obligations contained in the
agreement are not between those two parties and are different in
nature.
[54] Mr Leggat confirms that Aspec will submit to an order being made
against itself to the effect that it will, upon receipt
of the $327,500 for Mr
Fawcet, transfer the 324,256.43 trade dollars to Mr Fawcet.
[55] If I should find that Aspec is not entitled to specific performance,
Mr Leggat submits that judgment against Mr Fawcet should
be entered for
liability, with a later hearing to determine the appropriate remedy.
Discussion and conclusions
[56] In an appropriate case, the Court may order specific performance for the payment of a sum of money. The decision of the House of Lords in Beswick v Beswick is an example of such a case.11 In that case, Mr Beswick Sr., when he was in his seventies and in poor health, made an agreement with his nephew that he would transfer the goodwill and trade utensils of his coal business to his nephew. Part of the consideration for this was the agreement that the nephew would, on the
death of Mr Beswick Sr., pay to Mr Beswick Sr.’s widow a sum of 5 pounds per week for life. When Mr Beswick Sr. died, the newphew paid the widow one sum of
5 pounds, then refused to pay any further sum. The widow brought actions in her capacity as administrator and in her personal capacity for specific performance of the agreement. The House of Lords found in the widow’s favour because (inter alia) specific performance was the most appropriate outcome in the circumstances. Specific performance was more convenient than an action for arrears of payment,
followed by separate actions as each sum fell due. Further,
the parties to the
10 Citing Laws of New Zealand, Specific Performance (online ed) at [21]; John McGhee (ed) and
Snell’s Equity (32nd ed, Sweet & Maxwell, London, 2010) at [17-025].
11 Beswick v Beswick [1967] UKHL 2; [1968] AC 58.
agreement were intending an annuity for a widow; a lump sum of damages did
not accord with this.12
[57] Mr Herbert refers to a general presumption that specific performance
will not be available in cases where a party seeks to
compel performance of an
obligation to pay money, but I do not think the cases support the view that
there is a presumption to that
effect (although damages will no doubt often be
considered an adequate remedy in such cases). In the end, I think it depends on
what is most appropriate in the circumstances of the particular
case.
[58] In Butler v Countrywide Finance, Hammond J
stated:13
[...] the law of civil remedies in this the country is, as it should be,
steadily evolving into a regime in which what is required
of a Court is a
context- specific evaluation of which remedy is the most appropriate in the
circumstances of a given case, rather
than doctrinaire or a priori solutions.
The problem then becomes one of informed remedial choice.
[59] Considerations which may be relevant in determining whether specific
performance is the most appropriate remedy include among
others
:14
(a) Plaintiff autonomy. Generally speaking, a plaintiff as the
injured party should have first choice of remedy.
(b) Economic efficiency. The debate on the efficiency of specific
performance versus damages is not concluded, but is nonetheless
a relevant
factor.
(c) The relative severity of the remedy on the parties.
(d) The moral view to be attached to the interests at stake. (e) The conduct
of the parties.
12 Beswick v Beswick, above n 10 at [88] per Lord Pearce.
13 Butler v Countrywide Finance [1993] 3 NZLR 623 at 631.
14 At 632-633.
[60] In this case, the first of the factors listed by Hammond J in
Butler (plaintiff autonomy) clearly favours Aspec. The fourth factor
(the moral view to be attached to the interests at stake) arguably
also favours
Aspec. One of the very purposes of the regime set out at cl 3 of the deed
appears to have been to relieve Aspec of
the burden of finding a market for any
trade dollars it wished to be rid of, and that purpose would be defeated if Mr
Fawcet were
permitted to fall back on a “damages is an adequate
remedy” argument.
[61] As for the second and third potentially relevant considerations
identified by Hammond J in Butler (economic efficiency, and the relative
severity of the remedy on the parties), there is not enough evidence for me to
determine how
these factors may affect the question of whether specific
performance is the appropriate remedy. It may be that if the evidence were
available these factors would be seen to favour Mr Fawcet. On the
“severity” issue, if I made an order for specific
performance, Mr
Fawcet would be at risk of a contempt finding if he failed to comply with the
order. And, relevant also to the economic
efficiency issue, it may be that the
evidence would show there is a ready market for the trade dollars. If that were
the case, there
would be little to be gained by making an order which would put
Mr Fawcet at risk of a contempt finding in the event of default,
when Aspec
could easily secure the cash it wants by simply selling the trade dollars. In
such a case, I think it would also be clear
that damages would be an
adequate remedy.
[62] Weighing the various considerations, I am not satisfied on the
evidence that Aspec has shown that damages would not be an adequate
remedy, or that specific performance is the appropriate remedy for some other
reason. I accordingly decline to enter
summary judgment for specific
performance.
[63] It is not strictly necessary for me to make any findings on Mr Herbert’s other submissions in opposition to the claim for specific performance, but I add that I would not have been inclined to accept his submissions based on the proposition that the Court will not enforce only part of a contract. Delta has substantially discharged its obligations under the deed in this case, and if specific performance had been an appropriate remedy against Mr Fawcet there would seem to be no reason why
specific performance would not have been available to compel performance of
the
(as yet unperformed) obligations of the third party to the deed.
[64] My findings so far on Issue 4 do not mean that Aspec should not
succeed on its summary judgment application as far as liability is
concerned. Indeed, I think it must succeed on liability, as I have found that
Aspec was entitled to issue the notice it issued
under cl 3.1, and Mr Fawcet
acted in breach of contract in failing to pay the sum demanded within the
allowed period of ten working
days. At the very least, Aspec must be entitled
to nominal damages for breach of contract. There will accordingly be judgment
for Aspec on liability.
[65] The next question is whether judgment should be entered on
Aspec for liability, with damages to be assessed at
trial, or whether it should
remain open to Aspec to seek an order for specific performance at trial (or
damages if specific performance
cannot be had).
[66] Rule 12.3 of the High Court Rules provides that the Court may give
judgment on the issue of liability, and direct a trial
on the issue of amount,
if the party applying for summary judgment satisfies the Court that the only
issue to be tried is one about
the amount claimed. The rule does not appear to
contemplate the entry of summary judgment on liability while leaving it open to
the plaintiff to pursue remedies other than damages, such as an order for
specific performance. Under r 12.3, the only issue which
may be left over for
assessment at a later trial is whether the plaintiff is entitled to “the
amount claimed”.
[67] In Ghent v Brinkman, the Court would have declined to accede to the application for judgment on liability, as there was no clear dichotomy between issues affecting liability on the one hand, and damages on the other. The plaintiff’s claims for aggravated and exemplary damages in that case appeared to open up virtually the whole field of the conduct of the respective parties, necessarily leading to an examination of all aspects of the relationship between them. In those circumstances the Court would have had to examine and pronounce upon the same issues at the assessment of damages stage as (by virtue of the summary judgment on liability) would have been presumed to have been decided in favour of the plaintiffs. Not only
would that mean that the summary judgment procedure would have conferred
little advantage from the point of view of saving expense
and time, but it would
put the Court in the position where it might make findings which would not
readily be reconciled with a holding
that there was no tenable defence.
15
[68] I think similar considerations apply in this case. To enter
judgment on liability and leave it open to Aspec to pursue
its claim for
specific performance (or damages in the alternative) would run the risk of
opening up all matters which might in equity
be considered as a bar to an award
of specific performance (including, conceivably, the issue of whether Aspec had
discharged its
liability under cl 7.2 of the deed). I think the better course
is to dismiss the claim for specific performance, but enter judgment
for
liability in favour of Aspec, with damages to be assessed at trial. There will
be orders accordingly.
Results
(a) Mr Fawcet’s application for an extension of time to file his
notice of opposition and affidavits in opposition is
allowed. The time is
extended to the date or dates on which the notice of opposition and affidavits
in opposition were filed.
(b) Aspec’s application for an order for specific performance of
Mr Fawcet’s obligations under cl 3.2 of the deed is dismissed.
(c) Summary judgment is entered for Aspec on liability, with
the quantum of damages to which Aspec is entitled to be
assessed at
trial.
(d) Aspec is directed to file a further amended statement of claim, setting out its claim for damages, within 28 days of the date of this
judgment.
15 Ghent v Brinkman HC Wellington CP 379/87, 11 September 1987 at 12-13.
(e) Mr Fawcet is to file a statement of defence to Aspec’s
further amended statement of claim, within 14
days after the
further amended statement of claim has been served on him.
(f) A case management conference is to be allocated for the
first available date after 1 June 2015.
(g) Costs are reserved.
Associate Judge Smith
Solicitors:
Ford Sumner, Wellington for applicant
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2015/535.html