|
Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 16 February 2017
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2016-404-001649 [2017] NZHC 55
|
BETWEEN
|
AUCKLAND ELECTRICAL
SOLUTIONS LIMITED Appellant
|
|
AND
|
THE WARRINGTON GROUP LIMITED Respondent
|
|
Hearing:
|
(On the papers)
|
|
Counsel:
|
N Tabb for the Appellant
S Gazley for the Respondent
|
|
Judgment:
|
1 February 2017
|
COSTS JUDGMENT OF DOWNS J
This judgment was delivered by me on Wednesday, 1 February 2017 at 3 pm
pursuant to r 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Solicitors/Counsel: N Tabb, Auckland.
Steindle Williams Legal, Auckland.
AUCKLAND ELECTRICAL SOLUTIONS LTD v THE WARRINGTON GROUP LTD [2017] NZHC 55 [1
February 2017]
[1] On 22 September 2016 I dismissed an appeal against a refusal of the
District Court to grant summary judgment.1 I invited the parties
to reach agreement in relation to costs. They have not been able to do so. The
respondent seeks costs. The appellant
resists. The relevant facts can be stated
briefly.
[2] The respondent engaged the appellant to provide electrical
works. The appellant sent the respondent invoices
totalling $83,599.57. The
respondent paid the appellant $62,214.39; it declined to pay five invoices.
Further payment by the respondent
and credit notes in its favour left only
$8,659.83 outstanding. The case was originally before the Disputes Tribunal.
The appellant
then sought summary judgment in the District Court. The District
Court declined summary judgment on the basis witness credibility
was in issue.
The parties offered competing versions of what each said were the correct
invoices: the appellant’s invoices
referred to the Construction Contracts
Act 2002 and the respondent’s did not. That Act governed the dispute.
Invoice reference
to the enactment may be determinative. I upheld the District
Court’s determination:2
Against this background, Judge Lovell-Smith was unquestionably correct to
dismiss the summary judgment application insofar as it relied
upon original
service of the April, May and June invoices. If Mr Mettam is correct, the
invoices did contain reference to the Construction
Contracts Act as required by
that enactment. But if Mr O’Connell is correct, the original invoices did
not. Moreover, there
are two possibilities in relation to their evidence. The
first, and happy possibility, is that one of the men is mistaken. The
second,
unhappy possibility is that one of the men has been other than candid in order
to “win”. These stark choices,
which could only be resolved through
cross-examination at trial, serve to highlight the unsuitability of this aspect
of the claim
to summary judgment.
[3] I also concluded the evidence implied other invoices were provided
as copies of an antecedent payment claim rather than
a fresh claim under the
Act, which entitled the respondent to a further 20-working day period for a
payment schedule.
[4] The respondent’s actual costs were $8,752.42, a smaller sum than 2B scale costs: $9,366. It, however, seeks $10,865.55 on the basis increased costs are warranted under r 14.6 of the High Court Rules. The appellant resists costs as the
“respondent appears to have succeeded on a technical
argument”.
1 Auckland Electrical Solutions Ltd v The Warrington Group Ltd [2016] NZHC 2245.
2 At [16].
[5] Costs in a summary judgment context are normally fixed after trial but the rule is not immutable.3 Costs—and modestly increased costs to a total of
$10,865.55—are proper here because:
(a) The respondent succeeded.
(b) The case ought to have been determined in the Disputes Tribunal, a
point foreshadowed in my original judgment:4
Events subject to the August meeting need not be recorded here. It is
sufficient to observe common sense did not prevail:
a modest dispute
which should have been resolved in the Disputes Tribunal—if not settled
outright—resulted in summary
judgment proceedings in the District Court
and this appeal when that application was dismissed.
It follows the appellant pursued an unnecessary step in instituting summary
judgment proceedings in the District Court and
then pursuing those on
appeal.5
(c) Credibility was always going to be an impediment to
summary judgment. So, contrary to the appellant’s submission,
that
application and the associated appeal lacked merit.6
(d) As observed in the original judgment, the case ought to have
settled.
On 16 August 2016, and hence approximately five weeks before the hearing of the appeal, the respondent offered to pay $4,500 to the appellant in full and final settlement. The amount in issue was
$8,659.83. There is no evidence as to why the appellant did not accept the
offer. It is difficult to conceive a reasonable justification
for its
stance.7
[6] The respondent also sought an order that costs be awarded against a non-
party, Mr John Campbell of Law Debt Collection
Ltd, on the basis he
was
3 NZI Bank Ltd v Philpott [1990] 2 NZLR 403 (CA).
4 Auckland Electrical Solutions Ltd v The Warrington Group Ltd, above n 1, at [14].
5 High Court Rules, r 14.6(3)(b)(ii).
6 High Court Rules, r 14.6(3)(b)(ii).
7 High Court Rules, r 14.6(3)(b)(v).
responsible for the appellant’s conduct (in prosecuting meritless
proceedings). I am not satisfied that is so on the evidence,
or that the case
is sufficiently exceptional to warrant a non-party costs
order.8
[7] The appellant engaged Mr Campbell’s company to pursue the
respondent for its debt, but that without does not establish
he was behind this
action. Nor does the mere fact Mr Campbell swore an affidavit in support of the
proceedings. In any event,
while the proceedings involved
“overkill”, they did not involve bad faith or
impropriety.
[8] The appellant must pay the respondent (increased) costs of
$10,865.55.
...................................
Downs J
8 Dymocks Franchise Systems (NSW) Pty Ltd v Todd (No 2) [2004] UKPC 39, [2005] 1 NZLR
145.
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2017/55.html