|
Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 8 June 2017
IN THE HIGH COURT OF NEW ZEALAND NAPIER REGISTRY
CIV 2016-441-102 [2017] NZHC 773
|
BETWEEN
|
MILLSTONE GRAZING LIMITED
Plaintiff
|
|
AND
|
MYOAK HOLDINGS LIMITED Defendant
|
|
Hearing:
|
22 March 2017
|
|
Appearances:
|
J D Haig and H Gordon for the plaintiff
P W Ahern for the defendant
|
|
Judgment:
|
24 April 2017
|
JUDGMENT OF MALLON J
Table of contents
Introduction
.......................................................................................................................................
[1] The facts
.............................................................................................................................................
[3] The settlement agreement
...............................................................................................................
[35] The Buy Back Agreement
...............................................................................................................
[41] The Subdivision Land
.....................................................................................................................
[47] The parties’ respective positions
....................................................................................................
[52] My assessment
.................................................................................................................................
[54] Result
................................................................................................................................................
[73]
Introduction
[1] This claim concerns an option to purchase land. The plaintiff (Millstone), a company associated with Heughan Gordon, considers it is entitled to exercise that option. The defendant (Myoak), a company associated with John O’Connor, considers it is not. Which position is correct depends on the proper construction of
the terms of the option.
MILLSTONE GRAZING LIMITED v MYOAK HOLDINGS LIMITED [2017] NZHC 773 [24 April 2017]
[2] Millstone has pleaded three causes of action. Its primary cause
of action pleads that Myoak failed to perform its obligation
in the option and
seeks specific performance. The other two causes of action plead equitable
estoppel and rectification and seek
the same relief.
The facts
[3] The parties provided an agreed statement of facts. The following
paragraphs are largely from that agreed statement. Additional
evidence adduced
at the hearing is also incorporated. Before discussing the agreed facts
and evidence I note two matters:
(a) Both parties adduced evidence as to what they understood or
intended when they agreed to the option. They did so on the
basis that
rectification had been pleaded. It is accepted this evidence is
otherwise irrelevant.
(b) Counsel for each party submitted that, where the evidence of Mr
Gordon and Mr O’Connor was in conflict,
I should prefer the
evidence of their client. However the only material respect in which their
evidence differed concerned what
they understood or intended by the option they
agreed to. As that evidence is irrelevant to the first two causes of action, and
fails
to establish the existence of a mutual mistake for the third cause of
action, it is not necessary to prefer the evidence of one over
the other.
Moreover I regarded both Mr Gordon and Mr O’Connor to be honest
witnesses, doing their best to accurately
recall events as they saw
them.
[4] This proceeding has its genesis in an arrangement entered
into between entities with two family groups:
(a) The Gordon interests comprise the trustees of the Heughan Gordon Family Trust, Timoti Limited and Millstone Grazing Limited (referred to generally as the “Gordon interests” or, where applicable, “Millstone”).
(b) The O’Connor interests comprise Silverfern Vineyards Limited
(Silverfern), Seamar Investments Limited and Myoak Holdings
Limited (referred to
generally as the “O’Connor interests” or, where applicable,
“Myoak”).
[5] Mr Gordon is a farmer. Prior to 2009 he ran a farm near Pahiatua. He was looking for a change when, in March 2009, he saw an advertisement for the sale of a
260 hectare (approximately) farm property in Waimarama, Hawke’s Bay
which interested him. The property was owned by the O’Connor
interests.1 The property comprised about 250 hectares to the west
of Waimarama Road (Lot 14) and about 9 hectares to the east of that road (Lot
13) (the Farm Land). It also comprised a further smaller parcel of land (Lot
58), also to the west of Waimarama Road, which was
on a separate certificate of
title.
[6] On approaching Mr O’Connor, Mr Gordon learned of complications. The Farm Land was part of a larger area of land, in total 320 hectares, owned by the O’Connor interests (the Original Land). The Original Land was comprised of 11 titles. It was subject to a Resource Consent dated 8 January 2009 permitting its subdivision. The Resource Consent enabled the O’Connor interests to subdivide the Original Land into the Farm Land and the Subdivision Land, and the Subdivision
Land to be further subdivided.2 The Resource Consent
contemplated the subdivision
being carried out in one stage. Because the subdivision had not been
carried out, separate titles were not yet available for the
Farm Land and it
therefore could not be sold at this time.
[7] In light of this complication, negotiations took place in about June 2009. The negotiations led to an arrangement pursuant to which the O’Connor interests3 transferred the title to the Original Land to the Gordon interests.4 The Gordon
interests contemporaneously entered into an agreement to transfer the
Subdivision
1 Silverfern.
2 The Resource Consent enabled subdivision of the existing 10 rural sites to create eight rural lifestyle sites and two balance rural sites and to adjust the boundaries of two existing lifestyle sites. The consent conditions required lots 12 and 15 to be held on the same title, lots 13 and 14 to be held on the same title and lots 1 and 16 to be vested in the Council as roads.
3 Silverfern.
4 The Gordon Trust.
Land back to the O’Connor interests once separate titles were
available. This
arrangement was documented as follows:
(a) an Agreement for Sale and Purchase dated 27 June 2009 pursuant to
which the O’Connor interests5 transferred to the Gordon
interests6 the Original Land and Lot 58 (the First Agreement);
and
(b) an Agreement for Sale and Purchase dated 27 June 2009 pursuant to
which the Gordon interests7 agreed to the transfer of the
Subdivision Land to the O’Connor interests8 on issuing of new
titles (the Buy Back Agreement).
[8] The First Agreement contained provisions concerning a water source
on the property (Lot 14). The parties acknowledged the
O’Connor interests
held a resource consent to abstract water for certain water recipients and was
entitled to do all things
necessary to register an easement to implement the
water scheme from the water source.9 The Gordon interests agreed
to provide water for up to eight lifestyle lots until the water scheme was
commissioned.
[9] The Buy Back Agreement provided for completion of the subdivision, who would own what land on completion of the subdivision and acknowledgements and requirements for implementing the water rights. Settlement of the Buy Back Agreement was to occur 10 working days after notification by the O’Connor interests of the deposit of the subdivision plan and the titles issuing for the Subdivision Land. The Buy Back Agreement did not contain any timeframe for the subdivision to take place, nor what was to happen if the subdivision did not take
place.10
[10] Mr Gordon became concerned about the delay in progressing the
subdivision.
His expectation, based on his discussions with Mr
O’Connor, was that the
5 Silverfern.
6 The Gordon Trust.
7 Timoti Limited and the Gordon Trust.
8 Seamar Investments Limited (Seamar).
9 The water rights resource consent was dated 15 June 2007.
10 The provisions of the Buy Back Agreement are discussed in more detail below.
subdivision would take about two years. He wished to obtain separate title
for his farm and to remove the O’Connor interests’
caveat which
protected their interest in the Subdivision Land.11 He was
concerned to have the ability to deal with the Farm Land if he needed to, for
example if he was in injured in an accident on
the farm and needed to sell it.
Additionally, the O’Connor interests were permitted to carry out works on
the farm for the
water rights. This had the potential to cause disruption and he
did not want the matter to drag on.
[11] Mr O’Connor was initially unaware of any concerns about the
delay in the subdivision. Although he had discussed a possible
time frame for
the subdivision, he had provided no assurance about that. From his
perspective the delay did not disadvantage
the Gordon interests because the
purchase price for the Original Land and Lot 58 only reflected the value of the
Farm Land and Lot
58, and the Gordon interests also received grazing rights over
the Subdivision Land for which the only cost was paying the rates.
He did not
wish to advance the subdivision because of concerns about the lifestyle market
during this period and the cost of carrying
out the full subdivision relative to
that market. It was put to Mr O’Connor that he did not proceed because he
could not due
to financial difficulties. He maintained the issue was
uncertainty about a satisfactory return in light of the market at that
time.
[12] The Resource Consent was to lapse on 7 January 2014.12
Mr O’Connor still needed to obtain separate titles for the Farm Land
and the Subdivision Land. He therefore decided to apply
to vary and extend the
Resource Consent. Mr O’Connor says he discussed his intentions with Mr
Gordon in June 2013. He understood
Mr Gordon to be happy because the changes
did not impact upon the Farm Land.
[13] The application to vary and extend the Resource Consent was made in
July
2013. It was granted to Myoak on 19 November 2013 (the Varied
Resource
Consent). The varied resource consent extended the expiry date for two years
until
7 January 2016 and enabled completion of the subdivision in four
stages.
[14] Stage one involved subdivision of the Original Land into three
titles, namely:
11 A caveat was lodged by Seamar on 24 August 2009.
12 Resource Management Act 1991, s 125.
(a) one title for the Farm Land comprising Lots 13 and 14; and
(b) two titles for the Subdivision Land: one comprising Lot 5 (2.44
hectares), and one comprising lots 12, 15 and 16 (about
59
hectares).
[15] The following shows the location of these lots in relation to each
other:
[16] Stage two involved:
(a) vesting Lot 16 in the Council as a road; and
(b) creating four new lots within lot 12 (lots 6 to 9) with lots 8, 12 and 15
to be held in the same title.
[17] Stage three involved creating three new lots within lot 15 (lots 1 to 3), with lots 8, 12 and 15 remaining on the same title. Stage four involved creating two further lots within lot 15 (lots 4 and 10), with lots 8, 12 and 15 remaining on the
same title. Lot 1 was to be vested in the Council as a road at either Stage
three or four, whichever occurred first.
[18] Following the application to vary and extend the Resource
Consent, the Gordon interests’ lawyers advised the
O’Connor
interests’ lawyers of their concerns. Communications between the lawyers
continued after the Varied Resource
Consent was granted. The Gordon interests
considered it was unacceptable that the Varied Resource Consent extended the
time for
completing that part of the subdivision which would provide separate
title for Lots 13 and 14 (Stage one), the title for the Farm
Land, for up to
another two years. They proposed a much shorter extension for this part. The
Gordon interests threatened to object
to the Varied Resource Consent. They also
considered it was not appropriate to consider draft water scheme rules or a
revised schedule
of easements until the Farm Land titles were issued.
Some proposals about these matters were made providing Stage one proceeded
with
urgency.
[19] The O’Connor interests responded that the work for
Stage one was progressing and, if all went smoothly, documentation
could be
with LINZ by late January/early February 2014. The O’Connor interests
were also concerned with the Gordon interests’
approach to the water
scheme rules and the easements in light of their obligations under the Buy Back
Agreement. The O’Connor
interests, through their lawyers, sought and
received an assurance that the Gordon interests were not seeking to unjustly
enrich
themselves.
[20] Shortly before Christmas 2013 the Gordon interests applied to remove
the O’Connor interests’ caveat registered
over the Original Land.
With their lawyers’ office closing over Christmas, the O’Connor
interests did not receive notice
of this until mid-January 2014, by which stage
the time for applying to sustain the caveat had passed. The Gordon interests
had
given no warning of this intended action and Mr O’Connor could not
understand why they had taken this action.
[21] There were further exchanges between the respective lawyers in January and February 2014. The O’Connor interests assured the Gordon interests that work was progressing on Stage one. The Gordon interests remained concerned about progress.
The parties disagreed over the required water rights easements and
encumbrance changes. In February 2014 Millstone was incorporated
and the title
for the Original Land was transferred to it.13 No deed of covenant
was entered into on the same terms as the Buy Back Agreement therefore this was
contrary to the agreement.14
[22] On 28 February 2014 Silverfern, an O’Connor entity, gave notice to a meeting of creditors to consider a compromise proposal. This proposal indicated Silverfern’s very poor financial position. However it neither had an interest in the Subdivision Land under the Buy Back Agreement15 nor under the Varied Resource Consent.16 Mr O’Connor maintained this was not an impediment to his subdivision plans because of the different entities involved, resolution of the financial issues of
the entities under strain was achieved, and a bankruptcy application against
him was settled.
[23] On 17 March 2014 the lawyers for the Gordon interests gave notice
that the Buy Back Agreement was at an end. The patience
of the Gordon
interests’ was said to be exhausted after five years of delay. Mr
O’Connor was “completely shocked
and bewildered” by this. He
could not see how the Gordon interests could purport to retain the Subdivision
Land when they
only ever held it on trust for the O’Connor interests.
Further correspondence ensued. The O’Connor interests gave
notice of
their intention to issue proceedings.
[24] On 31 March 2014 the O’Connor interests, pursuant to their
interest under the Buy Back Agreement, lodged a caveat over
the Original Land.
By this time the Gordon interests in the Original Land had been transferred to
Millstone. Millstone subsequently
applied for the caveat to lapse.
[25] On 21 May 2014 the O’Connor interests commenced proceedings in the High Court. This proceeding alleged the Gordon interests had breached by the Buy Back Agreement by refusing to take steps to enable the subdivision to proceed, wrongly
purporting to treat the Buy Back Agreement as at an end, and
transferring the title of
13 From the Gordon Trust. This was the entity which held this interest prior to the transfer to
Millstone.
14 Refer below at [42](c).
15 This interest was held by Seamar.
16 Myoak held the interest under the Varied Resource Consent.
the Original Land to Millstone. The proceeding sought declarations that the
Subdivision Land was held on trust for the O’Connor
interests, specific
performance of the Gordon interests’ obligations under the Buy Back
Agreement and damages.
[26] On 16 June 2014 the parties agreed to a consent order that the
caveat not lapse pending the determination of the above proceeding.
On 26 June
2014 the Gordon interests counterclaimed seeking a declaration that the Buy Back
Agreement was at an end and damages.
[27] Subsequently the parties attended mediation before Robert Fisher QC on 8 and 9 September 2014. A settlement was reached. The terms of the settlement were set out in an agreement dated 9 September 2014. Lawyers for each party were involved in drafting its terms. The settlement agreement provided for specified conveyancing steps to be undertaken (set out at schedule A of the agreement) which would give effect to Stage one of the Varied Resource Consent and result in the
issuing of the three new titles it contemplated.17 It also
provided Millstone with the
option to purchase which is the subject of this proceeding. The parties also
agreed the High Court proceedings would be discontinued
with no issue as to
costs.
[28] As discussed in more detail below, at the time of the settlement Mr
O’Connor was unsure if he would complete the subdivision
and the Gordon
interests were aware of this. The option to purchase arose out of a proposal by
the Gordon interests to buy the Subdivision
Land. The Gordon interests
considered the land would be useful for its sheep and beef farming operations.
It would provide more
space, had better terrain, and it also had smaller
paddocks close to the farmhouse and yards which were useful for holding small
mobs of cattle or stock awaiting trucking. The O’Connor interests
rejected the Gordon interests’ proposal to purchase
the Subdivision Land.
However that led to a suggestion of the option, which was agreed
upon.
[29] The parties completed the conveyancing steps agreed in the Settlement Agreement on 10 October 2014. Separate titles for the Farm Land (one title) and the Subdivision Land (two titles) were issued in December 2014. These recorded
Millstone as the owner of the Farm Land and Myoak as the owner of the
Subdivision
Land.
[30] However a dispute arose over the associated conveyancing costs of
$27,000. Millstone considered they should be paid by Myoak
because they were
Myoak’s responsibility under the Buy Back Agreement. Millstone refused
to execute authorities for the easements,
despite having agreed to do so under
the Settlement Agreement, until these costs were paid. Myoak considered each
party was to
bear their own costs as provided by the Settlement Agreement, which
was in full and final settlement of all matters.
[31] Millstone remained liable for the rates over the Subdivision Land
until 30
June 2015, being the end of the rating year. The grazing arrangement over
the
Subdivision Land was therefore extended until this date. However on 7 May
2015
Mr O’Connor terminated the arrangement with immediate effect. This
caused disruption and inconvenience to Millstone. On
about 17 June 2015
Millstone registered a caveat over one of the two Subdivision Land titles (Lots
12 and 15). Mr Gordon says he
did so because he learned Mr O’Connor had
offered to sell the land to the farmer who had taken over grazing the
land.
[32] Myoak did not progress Stages two to four of the subdivision. On 7
January
2016 the Varied Resource Consent lapsed, not having been renewed or extended.
On
21 January 2016 Millstone’s lawyers asked Myoak’s lawyers to
confirm the option to purchase was exercisable and requested
Myoak’s
notice to commence the process under the option. Myoak’s lawyers
responded that Millstone’s option related
only to what was left of lots 12
and 15 after the subdivision contemplated in Stages two to four. As subdivision
had not taken place,
this was not exercisable. It requested that Millstone
remove the caveat.
[33] Further communications took place about whether the option was exercisable. No resolution was reached. In about February 2016 Myoak applied for Millstone’s caveat to lapse. Millstone applied for the caveat to be sustained. On 17
June 2016 the High Court ruled the caveat should be sustained.18 Myoak appealed
the High Court’s decision. The appeal is scheduled to be heard by the
Court of
Appeal on 30 May 2017.
[34] On 23 August 2016 Millstone commenced this proceeding. The parties endeavoured to resolve the matter at a meeting in January 2017. On 26 January
2017 Millstone offered to purchase the land in Lots 12, 15 and 16 for
$500,000, subject to finance, plus forgiveness of the disputed
conveyancing
costs of $27,000. Myoak did not respond. Mr O’Connor considered the
offer was below the true market value of
the land and should have been supported
by a formal valuation. It seems that no formal valuation has been obtained by
either party,
and no valuation has been adduced in evidence.
The settlement agreement
[35] Clause 1 of the settlement agreement provided for steps, identified in Schedule A, to be taken “for the purpose of completing the requirements of the Buy- Back agreement ... to enable transfer of title to the Buy-Back land” to the O’Connor interests. It provided that most of these steps19 were to be completed by 31 October
2014, that time was of the essence, and if they were not completed the
agreement was voidable at the option of either party.
[36] The steps identified in Schedule A included:
(a) the O’Connor interests withdrawing its caveat;
(b) the discharge of various mortgages and encumbrances;
(c) Millstone executing orders to enable the three new titles over
the
Original Land to be issued;
(d) Millstone transferring title to Lots 5, 12, 15 and 16 to the
O’Connor
interests;
(e) executing an authority to register an easement for the right to
convey electricity, telecommunications and electronic data
and the right to
drain water over lots 5 and 16 in favour of Lots 5, 12, 13 and 15;
(f) Myoak registering a right of way over lot 5 in favour of lot
15;
(g) Millstone executing an authority to register an instrument for the right to convey water over Lots 14 and 58 in favour of Lots 5, 12, 13 and
15, and over other specified lots (under different DP numbers), and executing
an encumbrance over Lot 14 to enable Myoak to abstract
water from the water
source for the benefit of the water recipients; and
(h) Millstone executing a consent to vest lot 16 as road.
[37] Clause 2 provided the option to purchase. It was as
follows:
2. Myoak hereby grants to Millstone an option to purchase of Lots 12 and 15 (after completion of Stage 1) after subdivision out of those Lots, the lots contemplated in stages 2, 3 and 4 of the existing Resource Consent Variation granted to Myoak on 19 November
2013 (“Resource Consent Variation”). The option shall be
exercisable as follows;
a. The exact description and size of the Lots to be purchased shall
be identified by Myoak at the point that Myoak has determined
not to continue
with any further subdivision of the residual land, being no later than expiry of
the date the [sic] Resource Consent
Variation to subdivide – whether
existing, varied or new – lapses;
b. Following notice by Myoak to Millstone, each party shall obtain,
within 28 days of such notice, a valuation from a registered
and suitably
experienced valuer in practice in Hawkes Bay, of the Lots based on then current
market value;
c. Millstone thereafter shall have the right to purchase those Lots
at a price which is the average of the 2 valuations and
otherwise on the
following terms;
a. The right must be exercised within 28 days of the determination
of the purchase price in accordance with this clause;
and
b. The right must be notified by an offer to purchase which is unconditional, due for settlement within
28 days, with a deposit of 10% and otherwise on the usual terms and
conditions of the latest version of the Auckland District Law
Society Inc/Real
Estate agreement for sale and purchase.
[38] Clause 3 provided for the parties to use their best endeavours to
settle and agree a Water Association to manage the water
rights attached to the
encumbrance and easements and provided a process for resolution of any disputes
about this. Clause 4 provided
that the Gordon interests were not to take any
steps to challenge the validity of the Resource Consent Variation and Myoak was
to
consult with Millstone in any approach to the Council concerning the
Resource Consent Variation. Clause 5 provided for
the filing of a notice of
discontinuance of the High Court proceedings on completion of the steps in
Schedule A. Clause 6 provided
there were to be no easements in gross. It
further provided that Millstone would execute authorities to register easement
instrument(s)
for rights to convey water over Lots 14 and 58 in favour of Lots
5, 12, 13 and 15, a number of other specified lots, and such other
neighbouring
properties to which Myoak granted rights under the water scheme.
[39] Clause 7 provided:
[40] Clause 8 required notice if a party wished to transfer its rights. Clause 9 provided that the agreement was a full and final settlement of all claims by either party against the other connected with the subject matter of the proceedings. Clause
10 provided that the parties had authority to enter into the agreement. Clause 11 provided for solicitor/client indemnity costs if one party breached the agreement. Clause 12 provided that the agreement was confidential subject to exceptions (ie using it to bring or defend proceedings). Clause 13 provided that the parties had relied on their own judgment in entering into the agreement. Clause 14 provided that the agreement “constitutes the entire agreement, understanding and arrangement (express or implied)” between the parties relating to its subject matter. Clause 15 acknowledged that each party had received independent legal advice.
The Buy Back Agreement
[41] The Gordon interests rely on definitions in the Buy Back
Agreement in support of their interpretation of the option
to purchase. It is
therefore necessary to consider the terms of that agreement in more
detail.
[42] The Buy Back Agreement covered the following matters:
(a) The subdivision: The O’Connor interests agreed to
“arrange for the preparation, approval and deposit of the subdivisional
plan”
(cl 16.4). The Gordon interests agreed to sign all necessary
documentation to enable the deposit of the subdivision plan (cl 16.4).
Who
would own which parts of the land upon deposit of the subdivision plan was
recorded (cl 16.6).
(b) Settlement: This was to occur 10 working days after
notification by the O’Connor interests of the deposit of the subdivision
plan and
the titles issuing for the Subdivision Land (cl 16.3).
(c) Transfer of interests: If the Gordon interests were to sell
or dispose of its interest in the land before subdivision, they must obtain from
the transferee
a deed of covenant protecting the O’Connor interests under
the Buy Back Agreement (cl 16.7).
(d) Water rights: There were provisions concerning the water source, including that the O’Connor interests were entitled to do all the necessary works to convey water from the water source to the eastern side of Waimarama Road and to register an easement, and Lot 58 would be part of the water scheme and be a water recipient (cls 22.1-
22-25).
(e) Grazing rights: Until settlement the Gordon interests could continue to graze the property in accordance with good farming practice (cl 27).
[43] In the context of providing what interests were acquired the
following definitions were provided:20
15.1 ... [The Gordon interests] have agreed to purchase the lands in CFRs
292113, 360530 to 360537 inclusive and 360521 (“the Farm”) and
Lot 58 DP 385092 (“Lot 58”) (“The Prior Agreement”)
... upon the basis that [the Gordon interests] shall take
title to the Farm and
upon partition of the Farm, which will be achieved by the subdivision and issue
of separate titles contemplated
in this agreement, [the Gordon interests]
shall retain Lots 13 and 14 on the annexed scheme plan (“the Land”)
plus Lot 58 and [the O’Connor
interests] acquires all interest in the
Property as described on the front page of this agreement.
[44] And:
16.6 It is the intention of the parties that upon deposit of the plan of subdivision contemplated by this agreement and the settlement of this agreement [the Gordon interests] shall own the Land plus Lot
58. [The O’Connor interests] shall be the registered proprietor of
Lots 2 to 7 (inclusive), Lot 9, Lot 11, Lot 12 and Lot 15 on the annexed Scheme Plan or other description of those Lands on any
variation of the Scheme Plan (“the Final Property” and also
referred to as “the Residual Land” in the
Encumbrance).
[45] In the context of the water rights, the following definitions were
provided:
22.4 To that end [the Gordon interests] by their execution hereof
acknowledges that the encumbrance to be registered against the
title to the Farm
pursuant to the Prior Agreement will on settlement of this agreement be
discharged and the Encumbrance, modified
to recognise that the Scheme Plan
annexed shall be replaced by a subdivisional plan and modified to reflect the
separate new legal
descriptions and the interpretations set out later in this
clause shall be given. Contemporaneously on the settlement date [the
Gordon
interests] ... shall deliver to [the O’Connor interests] such Encumbrance
in registrable form duly executed and completed
in all respects with priority
over all mortgages of the Land to the intent that the Encumbrance shall be a
first charge over the
Land. For the purposes of interpretation and because
certain lands to benefit from Water Source are not adequately defined in the
Encumbrance the following shall apply in the definition of the
Encumbrance:
“Farm” means the land presently comprised in the subdivision
being all of the lands comprised in CFRs 292113, 360530 to
360537 (inclusive)
and 360521.
“Land” means Lots 13 and 14 on the Scheme Plan which arise as a
result of the subdivision of the Farm.
“Residual Land” means the balance of the Farm after the Land has
been subdivided out and is the Final Property.
[46] A draft memorandum of encumbrance for the water rights was prepared.
In that draft “residual land” was defined
as meaning “the
balance land remaining from the Farm once the Land has been subdivided out of
the Farm”.
The Subdivision Land
[47] The O’Connor interests rely on evidence from Mr
O’Connor about his intentions for the Subdivision Land
as being relevant
to the factual matrix when the option was entered into.
[48] Mr O’Connor’s evidence was that, at the time of the
mediation, there was a high likelihood that Myoak would not
undertake any of
Stages two to four. This was because he thought Stages two to four would be
costly and the lifestyle market was
“reasonably dead”. It was also
because the conflict with the Gordon interests had “eaten up”
nearly a
year of the two year extension under the Varied Resource
Consent and caused substantial legal costs to be incurred.
[49] If the Varied Resource Consent expired before Stages two to four were implemented, those Stages could not be carried out subsequently. This was because under the Council rules, this level of subdivision depended on owning a larger parcel land than the Subdivision Land.21 Following Stage one, Myoak would own only
57 hectares of land. However, as Mr O’Connor saw it, subdivision
options that
would remain open to Myoak were:
(a) A subdivision of the Subdivision Land into two blocks.
(b) A subdivision into three 20 hectare blocks, if Myoak acquired a further six hectares from neighbouring properties over which he had options, and combined this with the Subdivision Land.
[50] Mr O’Connor’s unchallenged evidence was that the vesting
of the road in the Council would involve substantial
upgrading work at an
estimated cost of $50,000. However neither of these options would require Lot 16
to be vested in the Council
as a road. Lot 16 was of value to the future
potential of the Subdivision Land. This is both because it added to the total
area
of the Subdivision Land and it provided access to Waimarama Road for any
future properties created in a subdivision.
[51] Mr O’Connor says these possibilities meant that it was not
advantageous for him to agree to give the Gordon interests
an option to purchase
the Subdivision Land if Stages two to four did not proceed. Selling the
Subdivision Land to the Gordon interests
at the market price when the Varied
Resource Consent expired would not reflect the potential value he could later
extract from the
Subdivision Land.
The parties’ respective positions
[52] Millstone seeks to purchase the Subdivision Land at fair market value. It submits the option applies whether Stages two to four were completed or not. It says Myoak was required to give it notice identifying the land to be valued at the time it determined not to carry out or complete the subdivision under the Varied Resource Consent, or when the resource consent expired, whichever came first. It says the question was when not if notice would be given. It acknowledges the option relates to Lots 12 and 15, and Lot 16 is not referred to. It refers to cl 7 of the Settlement Agreement which requires the parties to do all things necessary to give effect to the agreement. It says this required Myoak to remove Lot 16 from the title and its failure to do so is a breach of this clause. It says Myoak cannot rely on its own failure to avoid the option. Millstone is willing to take on the burden of purchasing Lot 16. Accordingly it says notice must be given under the option covering Lots 12,
15 and 16.
[53] Myoak contends it was only obliged to give notice if it had completed all stages of its subdivision. As it has not done so, it is not obliged to give notice to Millwood under the option. It submits the effective part of the option makes it clear that it applies to Lots 12 and 15 only “after” the lots in Stages two to four have been subdivided out of Lots 12 and 15. That is, the completion of Stages two to four was a condition precedent to the option arising. It submits that even if it was now
required to give notice (which it denies), it cannot because Lots 12 and 15
are the only two lots referred to in cl 2 and Lot 16 (a
formed road subject to
rights of way) remains within the same certificate of title. It says that once
the Varied Resource Consent
expired it had no right to remove Lot 16 from the
title and if it was to be vested as a road it would be required to pay the costs
of upgrading it.
My assessment
[54] The “essence of the modern approach”22 to
determining the meaning of a contractual term is as
follows:23
... The necessary inquiry therefore concerns what a reasonable and properly
informed third party would consider the parties intended
the words of their
contract to mean. The court embodies that person. To be properly informed the
court must be aware of the commercial
or other context in which the contract was
made and of all the facts and circumstances known to and likely to be operating
on the
parties’ minds.
[55] The facts and circumstances include anything a reasonable person would regard as relevant, for example, the origins of the contract, the particular concerns and needs of the parties and the commercial purpose of the contract.24 But the information must be relevant in that it might cast objective light on the meaning the words are intended to bear.25 Where the words are ambiguous or otherwise susceptible to different interpretations, the court should adopt the interpretation which best accords with business common sense.26 However, if there is an ordinary and natural meaning of contractual language, the conclusion that it reaches a commercially absurd result should only be reached in the most obvious and extreme
of cases.27
22 Burrows, Finn and Todd Law of Contract in New Zealand (5th ed, LexisNexis, Wellington,
2016) at 178.
23 Vector Gas Ltd v Bay of Plenty Energy Ltd [2010] NZSC 5, [2010] 2 NZLR 444 at [19] per
Tipping J.
24 Burrows, Finn and Todd above n 22 at 179 citing Bank of Credit & Commerce International SA
v Ali [2001] UKHL 8, [2002] 1 AC 251 at [39] per Lord Hoffman.
25 Yandina Investments Ltd v ANZ National Bank Ltd [2013] NZCA 469 at [54].
26 Rainy Sky SA v Kookmin Bank [2011] UKSC 50, [2011] 1 WLR 2900 at [21] per Lord Clarke;
Lumley General Insurance (NZ) Ltd v Body Corporate 205963 [2010] NZCA 316 at [41]; and BOS International (Australia) Ltd v Strategic Nominees Ltd [2013] NZCA 643 at [56]. The parties in this case do not rely on subsequent conduct as relevant to the meaning of the option.
27 Firm PI1 Ltd v Zurich Australian Insurance Ltd t/a Zurich New Zealand [2014] NZSC 147, [2015] 1 NZLR 432 at [93] per Arnold J. See also Wood v Capita Insurance Services Ltd [2017] UKSC 24 at [11].
[56] The opening words of cl 2 of the Settlement Agreement are that
“Myoak hereby grants to Millstone an option to purchase”.
The next
words identify what the option relates to. Those identifying words are
“of Lots 12 and 15 (after completion of Stage
1) after subdivision out of
those Lots, the lots contemplated in Stages 2, 3 and 4 of the Resource Consent
Variation ...”.
The balance of cl 2 describes when the option is
exercised.
[57] The dispute centres on the words which identify what the option
relates to. The first few words identify that the
option relates to
Lots 12 and 15 after completion of Stage one. At the time of entering the
agreement the parties were focussed
on the need to complete Stage one and had
agreed a process intended to ensure that completion occurred quickly. The words
of the
option therefore proceed on the basis that Stage one will be completed.
It is clear the words relate to an option to purchase after
this has
occurred.
[58] However the option is further qualified by the words “after
subdivision out of those Lots, the lots contemplated in
stages 2, 3 and 4 of the
existing Resource Consent Variation ...”. On the plain meaning of these
words the option relates
to Lots 12 and 15 after two things have occurred.
First, the completion of Stage one (by which the separate titles for the Farm
Land, Lots 13/14, and Lots 12/15/16 was obtained). Secondly, after subdivision
out of Lots 12 and 15, the lots contemplated in Stages
two to four. On its
plain meaning, therefore, the option relates to what is left of Lots 12 and 15
once the contemplated Stages
two to four have occurred.
[59] Myoak contends the matter ends there. It submits the option applies
only if Stages two to four have been completed, because
it only applies to the
land that is left “after” those Stages have occurred. It says it
has no obligation to carry out
those stages and, as it has not done so, the
option does not arise. Millstone submits this fails to have regard to the
balance of
cl 2.
[60] The question then is whether the balance of cl 2 describes what may be purchased if Stages two to four have not occurred. Subparagraph (a) provides that “the exact description and size of the Lots to be purchased shall be identified by Myoak” at a specified time. The time specified is “the point Myoak has determined
not to continue with any further subdivision of the residual land, being no
later than expiry of the date [of] the Resource Variation
to subdivide –
whether existing, varied or new lapses.”
[61] The clause therefore contemplates that the description and size of
Lots 12 and
15 over which the option is exercised may vary, depending on actions taken by
Myoak. The point at which Myoak is to identify the
description and size of Lots
12 and 15 is when it has “determined not to continue with any further
subdivision of the residual
land, being no later than expiry of the date [of]
the Resource Consent Variation to subdivide – whether existing, varied or
new lapses.” These words envisage that Myoak might decide not to carry
out any further subdivision prior to expiry of the
Resource Consent Variation.
But otherwise, the point for Myoak to identify the exact description of Lots 12
and 15 for the option
to purchase, is the expiry date of the Resource Consent
Variation.
[62] Millstone submits the words “determined not to continue with
any further subdivision” refers to Stages two to
four and “the
residual land” refers to the Subdivision Land. It submits the wording
covers the possibility that none
of Stages two to four would be completed. In
that event it submits the option applies to the whole of Lots 12 and 15, rather
than
only the residual parts of those Lots after the lots contemplated in Stages
two to four have been subdivided out of them. It says
that if the option was
only to apply if Stages two to four were carried out, these words would not have
been necessary: the option
need only have stated that it applied to Lots 12 and
15 only if Stages two to four were completed.
[63] In support of its submission, Millstone refers to the definitions in the Buy Back Agreement. Under that agreement “the Land” is defined as Lots 13 and 14 after subdivision (that is, after separate title to Lots 13 and 14 is obtained) and “Final Property” and “Residual Land” means the remaining property (that is, after lots 13 and 14 have separate title).28 It submits the residual land referred to cl 2 of the Settlement Agreement means the land that is left after it has a separate title from Lots
13 and 14. In other words, the option to purchase Lots 12 and 15 arises
after the
subdivision which provided separate title for Millstone’s
farm, and relates to
28 See cls 15.1, 16.6 and 22.4 quoted at [43]-[45] above.
whatever is left of Lots 12 and 15 depending on the extent to which further
subdivision was carried out by the expiry of the Resource
Consent
Variation.
[64] Myoak submits, however, that the words “determined not to
continue with any further subdivision of the residual land”
refers to
possible further subdivision, after Stages two to four, of the remainder of Lots
12 to 15. It submits this was possible
because the Resource Consent Variation
could be further varied. It says it was reserving its right to carry out a
different or additional
subdivision than that covered by the Resource Consent
Variation. It submits it did not need to grant Millstone an option to purchase
the Subdivision Land if it did not proceed with some or all of Stages two to
four, whereas if it had extracted all the value it could
from the Subdivision
Land it would be content to sell what was left of Lots 12 to 15 to Millstone.
It submits there is no
suggestion in the Settlement Agreement that
“residual land” meant “Residual Land” as defined in the
Buy Back Agreement. Moreover, under the Buy Back Agreement the Residual Land did
not include Lot 16 (or Lot 1).
[65] Overall I consider the words, in the context and circumstances in
which they were agreed, were intended to mean the option
was to apply only to
Lots 12 and 15 after Stage one and after the further subdivisions contemplated
under Stages two to four (or
some variation to the further contemplated
subdivisions under Stages two to four). It was not intended to apply to Lots 12
and 15
if no further subdivision took place after Stage one.
[66] First, the structure of cl 2 supports this interpretation. The option identifies what it applies to in the opening paragraph. The words say that it applies “after” the contemplated Stages two to four. The plain meaning of this part of the clause is that Stages two to four (or some variation of them) are a condition precedent to the option arising. The use of the word “contemplated” indicates these stages have not yet happened and may not happen. If they do not happen the condition giving rise to the option is not satisfied. If the condition is satisfied then the balance of the clause explains how the option is to be exercised.
[67] Secondly, the words “determined not to continue with any
further subdivision of the residual land” have meaning
even if Stages two
to four, or some variation of them, are completed in full. By these words Myoak
reserved to itself the ability
to carry out some further subdivision of Lots 12
and 15 beyond what was contemplated by Stages two to four. That might have been
unlikely given the size of those lots if Stages two to four were completed.
Nevertheless it is not surprising that Myoak, as a property
developer, would
wish to preserve all of its options to extract value from the land should
further opportunities arise. If there
were no better uses for what was left of
Lots 12 and 15 then it made commercial sense to give Millstone an option to buy
that land.
[68] Thirdly, I consider it does not matter whether “residual
land” in cl 2 of the Settlement Agreement was meant
to have the same
meaning as “Residual Land” in the Buy Back Agreement. In their
context, these words meant the land
other than the farm land to which Millstone
obtained title pursuant to Stage one (essentially the same as that under the Buy
Back
Agreement although at that time Lots 1 and 16 would vest in the Council
when Millstone obtained title because the subdivision was
to occur at once).
But in my view this does not assist Millstone. The real issue is what was meant
by “any further subdivision”.
I consider those words meant any
subdivision additional to that contemplated by Stages two to four.
[69] Fourthly, the option is expressed as applying to Lots 12 and 15. It was known at the time of the mediation that, if Stages two to four did not proceed, Lot 16 would remain on the title. The option could have been expressed to apply to Lots 12 and 15, and 16 if Stage two was not completed, if that was the intention. That said, if Stages two to four were completed, Lot 8 would be part of the same title as Lots
12 and 15. Unless that was varied before the expiry of the Varied Resource
Consent, that too would have presented a problem with
how the option was to
work. This is not, therefore, the strongest of the points in favour of
Myoak’s interpretation.
[70] Fifthly, I do not accept that Millstone’s interpretation is supported by the possibility that Myoak may want to sell the land before the Varied Resource Consent expired. If Myoak did wish to do so, without completing any of Stages two to four, it would not be in its interests to agree to provide Millstone with this option. It could
simply offer the land for sale and let the Gordon interests compete in the
market to purchase the land if it wished to do so.
[71] Lastly, I do not accept Millstone’s submission that the option
was of no value to it if it applied only if Myoak proceeded
with Stages two to
four. Mr Gordon did not say the remaining parts of Lots 12 and 15 would be of
no use to his farm. Although it
appeared unlikely at the time that
Stages two to four would be completed, and therefore Millstone’s
option was
unlikely to arise, both parties obtained a mutually satisfactory
settlement of their differences at the mediation irrespective
of this.
Specifically, the Gordon interests obtained a means to receive title to their
farm in a timely fashion, Myoak obtained
a way of resolving the issues relating
to water rights and both parties achieved an end to the litigation and the
associated costs
and risks of that. In these circumstances, the option
provided something of potential additional benefit to each party in
the
(unlikely) event Stages two to four were completed and no detriment to either
party if they were not.
[72] I therefore find against Millstone on its first cause of action.
Myoak has not breached cl 2 of the Settlement Agreement.
I also find against
Millstone on its remaining causes of action. What Myoak represented it would do
is set out in the Settlement
Agreement. It did not represent to offer Lot 16 as
part of the option to purchase Lots 12 and 15 in the event that Stages two to
four did not proceed. Nor has Millstone established there was any common
intention about whether Lot 16 would be included if Stages
two to four did not
proceed.
Result
[73] Millstone’s claim is dismissed. Myoak is entitled to costs.
If there is any issue regarding costs, the parties may
file brief memoranda
(limited to five pages each) within 30 days of the date of this
judgment.
Mallon J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2017/773.html