You are here:
NZLII >>
Databases >>
High Court of New Zealand Decisions >>
2021 >>
[2021] NZHC 2558
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Bates v Auckland Council [2021] NZHC 2558 (29 September 2021)
Last Updated: 1 December 2021
|
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
|
|
CIV-2017-404-2670 [2021] NZHC 2558
|
|
BETWEEN
|
DENESE ROSEMARY BATES
Plaintiff
|
|
AND
|
AUCKLAND COUNCIL
First Defendant
O’HAGAN BUILDING CONSULTANTS LIMITED
Second Defendant
|
|
Hearing:
|
9–13 March 2020, 16–19 March 2020, 23 March 2020,
21–22
September 2020
|
|
Counsel:
|
T Rainey and J Heaney for the Plaintiff
S C Price, J K Wilson and R Nolan for the First Defendant A L Holloway and
M A Karlsen for the Second Defendant
|
|
Judgment:
|
29 September 2021
|
JUDGMENT OF GWYN J
This judgment was
delivered by me on 29 September 2021 at 12.00 pm pursuant to Rule 11.5 of the
High Court Rules.
Registrar/ Deputy Registrar Date:
Solicitors:
Cameron Flemming Associates Limited, Auckland MinterEllisonRuddWatts,
Auckland
Wotton Kearney, Auckland
BATES v AUCKLAND COUNCIL [2021] NZHC 2558 [29 September
2021]
TABLE OF CONTENTS
Introduction [1]
The parties [4]
The claims [7]
Background [12]
Discovery the house is a leaky building
[12]
Consent process for the remedial
works [18]
The remedial works
[25]
Discovery of current issues
[37]
The evidence at trial
[40]
Scene view [57]
THE CLAIM AGAINST THE
COUNCIL [58]
Did the Council owe a duty of care to Mr
Heaney and Ms Bates? [62]
Ms
Bates’ position [67]
The
Council’s position [70]
Discussion [80]
Did the Council breach its
duty to Mr Heaney and Ms Bates? [86]
Particular 2
– calculations or other verification of subfloor compliance with
E2/AS1 [87]
Discussion
[92]
Particular 1 – polythene sheet to be
laid on subfloor [97] Discussion
[106]
Particular 3 – calculations or
other verification for O’Hagan amendment in July 2007 [111]
Discussion
[120]
Particular 5 – vapour barrier
[125]
Particular 4 – failure to identify
that there was inadequate provision for subfloor ventilation provided for in drawings for the
building consent and the amended building consent [127]
Discussion [130]
Particular 6 – alleged failure to
observe during inspections that the proposed ventilation holes had not been installed
[132]
Discussion [142]
“Superseded”
[148]
Proposed
ventilation holes not installed [156] Particular 7 – alleged
failure to observe during inspections that there was inadequate provision for
subfloor ventilation [166]
The issue of the Code of Compliance
Certificate [169] Discussion
[171]
Was the Council’s
negligence a material cause of, or contributor to, the damage to the house? [172]
Discussion [177]
Defect/damage [177]
Causation [192]
Different course of action [197]
Other causes [199]
Conclusion on negligence
claim against the Council [205]
THE CLAIM AGAINST O’HAGAN [206]
Did O’Hagan owe a duty of care to
Mr Heaney and Ms Bates? [208]
Ms Bates’ position
[208]
O’Hagan’s position
[214]
Discussion [217]
Did O’Hagan breach
its duty to Mr Heaney and Ms Bates? [218] The removal and replacement of the subfloor
timbers [219] Discussion
[221]
The issue of the PS4
[230]
Discussion
[233]
Design advice and obtaining Council approval
for Detail 12 in July 2007 [242] Obtaining the amended building consent
(ABA-62145B) [245] Was
O’Hagan’s negligence a material cause of, or contributor to, the
damage to the house?
[247]
Conclusion on negligence
claim against O’Hagan [254]
Affirmative defences [255]
Third party claim [257]
Scope of remedial work
[258]
Costs [259]
Introduction
- [1] David
Heaney and Denese Bates had a house designed and built for them, at Matakana,
north of Auckland, in 1987. While the house
was initially to be a holiday home,
Mr Heaney and Ms Bates intended that it would ultimately be their main
residence.
- [2] In 2005 Mr
Heaney and Ms Bates discovered that the house was a leaky home. They had
remedial work done to the house in 2007-2009.
In 2016, to their dismay, they
discovered damage in the subfloor area of the house, caused by a serious
moisture problem. They say
it will cost in the order of $1.5 million to repair
the house, and the Auckland Council (the Council) and O’Hagan Building
Consultants Limited (O’Hagan) are liable to meet this
cost.
- [3] The hearing
commenced on 9 March 2020, but was adjourned part-heard on 23 March 2020 as a
result of the COVID-19 Level 4
lockdown. It resumed on 21 September 2020.
Sadly, in the intervening period Mr Heaney died. Ms Bates continued with the
proceeding
as the sole plaintiff.
The parties
- [4] The
first defendant, the Council, is a statutory successor to the Rodney District
Council, a territorial authority constituted
under the provisions
of the Local Government (Auckland Region) Reorganisation Order 1989. The
Rodney District Council issued
the building consents under which the remedial
work to the house was carried out. For ease of reference, I refer to both the
Auckland
Council and the Rodney District Council as “the Council”
throughout this judgment, as nothing turns on the distinction
between the two
entities.
- [5] The second
defendant, O’Hagan, is a building consultancy firm. It was engaged by Ms
Bates and Mr Heaney in 2007, initially
to remove and replace affected timber in
the course of the remedial work to the house.
- [6] Prior to
trial, the parties to the proceeding also included various entities involved in
the remedial work: Allied Exteriors Limited,
an exterior finishes
company;
Scribble Limited (Scribble), a provider of architectural services; Brackenridge
Builders Limited (Brackenridge), the builders who
initially carried out the
remedial work; and Mr Colin Green, the builder who carried out the remainder of
the remedial work. As matters
have progressed, some of the issues have been
resolved or settled. As at the commencement of the hearing, third party claims
brought
by both the Council and O’Hagan against Mr Green remained alive,
and Mr Bates appeared as counsel for Mr Green. However, those
claims were
subsequently settled, and I granted Mr Bates leave to withdraw early in the
proceeding.
The claims
- [7] Ms
Bates’ primary claims against both the Council and O’Hagan are in
negligence. There is no dispute that each of
the Council and O’Hagan owed
duties to Mr Heaney and Ms Bates to exercise reasonable skill and care in
carrying out their respective
roles - its functions under the Building Act 2004
in the case of the Council, and its contractual obligations in the case of
O’Hagan.
- [8] What is in
dispute is what those duties required of each of the Council and O’Hagan
in the particular circumstances of this
case and, following from that, whether
the Council and/or O’Hagan breached any duties owed. If so, there is also
dispute about
whether that negligence was a material cause of, or contributor
to, the damage to the house. Finally, if Ms Bates establishes liability,
the
scope of the remedial work required to the house must also be
established.
- [9] The
Council advances three affirmative defences against Ms Bates –
contributory negligence under the Contributory Negligence
Act 1947, failure by
the plaintiff to mitigate her loss and damage, and betterment. Similarly,
O’Hagan pleads contributory
negligence on the part of Ms Bates. I will
need to consider these matters only if I find that the relevant defendant is
liable to
Ms Bates.
- [10] In
addition, the Council and O’Hagan each cross-claim against the other in
the event they are found liable to Ms Bates.
The Council and O’Hagan also
maintain third party claims against Brackenridge, in the event they are found
liable to the plaintiff.
- [11] The hearing
concluded on the basis that this judgment will determine liability issues and,
if necessary, the scope of the work
required to rectify the damage to the house.
The quantification of the cost of the remedial work will be deferred to a
further hearing,
if necessary.
Background
Discovery
the house is a leaky building
- [12] The house
that Mr Heaney and Ms Bates had designed and built for them is a two-storey
timber-framed construction built on a concrete
block perimeter foundation. The
perimeter foundation supports the external timber-framed walls and a suspended
timber floor. The
cladding on the house was originally a James Hardie product
commonly known as “Harditex”, a texture-coated fibre cement
sheet
fixed directly to the framing of the building.
- [13] Mr Heaney
was the founding partner of a specialist litigation firm called Heaney & Co,
which acted for many local authorities
throughout New Zealand, advising and
providing representation in relation to legal claims made against councils. A
significant part
of Mr Heaney’s work involved defending local authorities
in leaky building cases.
- [14] In his
professional role, Mr Heaney often encountered the question whether the Harditex
product could perform if the product
was installed in accordance with the James
Hardie technical information. Mr Heaney believed that the house he and Ms
Bates had
built was a good example of a Harditex-clad house that did not
leak.
- [15] Mr Heaney
discussed the house with an expert on building construction, Mr Stephen
Alexander, a building surveyor and principal
of Alexander & Co Limited, a
firm of building surveyors and dispute resolution consultants. Mr Alexander
investigated the house
in 2004 or 2005, as part of his general research into
leaky buildings. Mr Alexander discovered that the house was a leaky home. He
found that the cladding on the house did not have a cavity to drain any moisture
which penetrated beyond the external face of the
cladding. There was moisture
ingress through the
cladding, particularly around the windows, which had caused significant damage
to the timber frame of the house.
- [16] Significantly
for the purposes of this proceeding, Mr Alexander had access to the subfloor
space under the house during his investigations.
He inspected the subfloor space
for damage, but aside from an area affected by the leaks through the deck on the
south-east elevation,
he observed no signs of decay or problems affecting the
subfloor of the house.
- [17] In June
2006, Mr Alexander, accompanied by another building surveyor, undertook further
investigations of the house and again
had access to the subfloor area of the
house. Mr Alexander’s evidence at the hearing was that if there had been
any deterioration
of the subfloor timber, he could have seen it at the time of
this inspection, and he would have taken a photograph and samples of
the timber
for analysis. He did not. Mr Alexander also said that, when viewed from the
subfloor space, he could see the subfloor
ventilation situation was “not
satisfactory”, but there was no detriment in
performance:
... Other than the limited area of wet and partially decayed
timber due to the deck issue [arising from the deck being directly fixed
to the
wall], I observed no decay. The earth was not saturated, the sub-floor framing
did not cause me sufficient concern to take
extensive moisture metre readings,
although I may have taken a few measurements. I did not observe mould or
dampness on the sub-floor
timber.
I observed no direct flow of water into the subfloor area.
Sub-floor ventilation present would not have complied with the
Acceptable Solutions for complying with the Building Code or relevant
standards
at the time of my inspection but was adequate to prevent significant
deterioration up to that point. The subfloor complied
with the performance
requirements [in] the Building Code because there had been no detriment in
performance but the situation was
not satisfactory and needed attention to avoid
future deterioration.
Consent process for the remedial
works
- [18] Mr Heaney
and Ms Bates engaged Alexander & Co to design the required remedial work to
the house.
- [19] On 8
September 2006, Alexander & Co, on behalf of Mr Heaney and Ms Bates,
submitted an application to the Council for building
consent for
“Re-cladding and bathroom extension to existing residential house. Works
include new paving around perimeter of
the house and lowering of site
levels.” The plans and specifications prepared by Alexander & Co were
submitted with the
application for building consent.
- [20] The plans
prepared by Alexander & Co proposed that the house be completely re-clad.
Relevant to the present proceedings,
it also proposed improvements to the
subfloor ventilation:
(a) The addition of 15 ventilation holes of 125 mm diameter
around the perimeter of the house (the proposed ventilation holes), shown
on
plan A-03. It was Mr Alexander’s view that an “engineer”, by
which he meant a person overseeing works, needed
to have oversight of the best
place to locate the proposed ventilation holes. The need for an
“engineer” was noted on
plan A-03.
(b) Subsoil drainage around the perimeter of the house.
(c) A gap under the timber decking at the south eastern end of
the house to promote airflow.
(d) The laying of a polythene sheet on the ground under the
house. This detail was not included on the plans, but was recorded in
the scope
of work document.
- [21] On 26
January 2007 the Council issued building consent ABA-62145 (the building
consent), authorising the work contained in the
Alexander & Co plans and
specifications, which were stamped as approved by the Council. The building
consent described the Building
Work as “Re-cladding & bathroom
extension to existing house”.
- [22] Tenders
were called for the repairs based on the plans and specifications submitted to
the Council. In January 2007 Mr Heaney
arranged for Brackenridge
to
carry out the work. Mr Heaney and Ms Bates did not have a written contract with
Brackenridge.
- [23] After
discussion with Mr Steve Brackenridge, Mr Heaney and Ms Bates decided that it
would be unnecessary to contract Alexander
& Co as a clerk of works to
oversee the project, believing it would be more efficient to use
Brackenridge’s clerk of works.
This was despite the fact that it was
Alexander & Co’s usual policy to insist on monitoring works that it
had designed.
Mr Alexander emailed Mr Heaney on 2 February 2007 recording
a concern about Brackenridge, which by then had commenced the remedial
work. Mr
Alexander said:
The detail in question is shown 17 times in the plans. It is of
considerable concern that the builder had not read the plans, thought
he would
do it the way he thought was right and then asked [the architect] rather than us
about what the plans intended. I am concerned
that Brackenridge will not have an
understanding of this type of work and will not follow the plans.
- [24] From that
point, Alexander & Co had no further involvement in the
work.
The remedial works
- [25] Construction
work began on the house in February 2007.
- [26] On 29 March
2007, Brackenridge applied, on behalf of Mr Heaney and Ms Bates, for a
formal amendment to the building consent
to change the cladding system on the
house from the STO system specified by Alexander & Co to the Nu-Lite
cladding system. That
application was approved by the Council on 17 April 2007
as amendment ABA-62145A. It is common ground that the 17 April 2007 amendment
is
not relevant to the issues in the proceeding.
- [27] One of the
conditions of the building consent was that a suitably qualified building
surveyor supervise the removal and replacement
of all timber showing any sign of
decay, and treatment of timber within one metre of the decayed timber. That
building surveyor was
then to provide a Producer Statement Construction Review
(PS4) to the Council,1 certifying that the timber replacement had
been carried out in
1 Under the now-repealed Building Act 1991, a
decision to issue a code compliance certificate turned on whether the
territorial authority
was satisfied, on reasonable grounds, as to
compliance.
accordance with certain technical specifications, before the commencement of the
re-cladding. Mr Heaney and Ms Bates contracted O’Hagan
to carry out this
work. Their instructions to O’Hagan were recorded in a series of emails,
on 11 May 2007.
- [28] During the
course of the remedial works, Mr Heaney wanted to make a change to Detail 12 of
the consented works, relating to the
connection between the patios and the
adjacent walls. Mr Heaney’s evidence was that he wanted the cladding above
the patios
to finish close to the external ground level, for aesthetic
purposes. On 16 July 2007 O’Hagan, on behalf of Mr Heaney
and Ms Bates,
provided the Council with details of these changes, as well as an unrelated
change to the chimney flashing detail,
based on plans prepared by Scribble. The
plans were noted as approved on the same day.
- [29] In
September 2007 Brackenridge instructed their sub-contractor to carry out work on
the house, which in Mr Heaney’s view
departed from the design prepared by
Alexander & Co and approved by the Council. In particular, Brackenridge
arranged for the
plastering sub-contractor to install the Nu-Lite external
cladding system without the reveals around the windows that were recorded
on the
original plans prepared by Alexander & Co. Brackenridge also arranged for
the joinery sub-contractor to install PVC flashings
in place of the aluminium
flashings that were required in the plans and specifications prepared by
Alexander & Co and approved
by the Council.
- [30] Mr Heaney
and Ms Bates learned of these changes in October 2007 and instructed
Brackenridge to stop work until the issues could
be resolved. A dispute then
arose as to who should pay for the additional work necessary to achieve what had
been originally specified.
The 1991 Act contemplated that such a decision might be on the
basis of, among other things, producer statements, which were defined
as meaning
a statement supplied by or on behalf of an applicant for, or the holder of, a
building consent that would be, or had been,
carried out in accordance with
certain technical specifications. The 2004 Act does not provide for the general
use of producer statements,
but there is nothing in the Act to prevent
territorial authorities from relying on them and they continue to be regularly
considered
as part of the building consent process.
- [31] On 29
November 2007 O’Hagan applied, on behalf of Mr Heaney and Ms Bates,
for a second formal amendment to the building
consent to change the cladding
from the Nu-Lite cladding system to Plaster Systems Thermaclad EIFS system. That
application for amendment
was approved by the Council in principle on 8 May 2008
and finally approved on 1 August 2008, as ABA-62145B (the amended building
consent). Some 20 documents that formed part of the building consent, including
plan A-03, were stamped “superseded”
on 8 May
2008.
- [32] On 19
February 2008 Mr Heaney and Ms Bates cancelled their contract with Brackenridge.
They subsequently issued proceedings against
Brackenridge, which were settled by
agreement dated 12 March 2010.
- [33] On 10 March
2008 Mr Heaney and Ms Bates contracted Mr Green to complete the work on the
house. There was no formal contract with
Mr Green, but Mr Heaney said he tried
to set out in an email on 10 March 2008 what they were expecting Mr Green
to attend to
in completing the remedial works. That email did not include
reference to installation of the proposed ventilation holes. Mr Green
started
the work on 17 March 2008. Mr Heaney did not recall providing Mr Green with a
set of the plans and specifications.
- [34] Mr Green
completed the remaining remedial work between March 2008 and November 2008. He
continued to be involved at the property
until after the Code of Compliance
Certificate was issued by the Council in May 2009.
- [35] On 30 April
2009 O’Hagan issued a PS4 confirming “Replacement timber and
certification of existing timber”.
O’Hagan had carried out three
timber inspections, on 24 May 2007, 30 May 2007 and 26 June
2007.
- [36] On 13 May
2009 the Council issued a Code of Compliance Certificate for the building work
authorised under the building consent
and the subsequent amendments to that
consent, which recorded:
The Rodney District Council are satisfied, on
reasonable grounds, that –
- The building
work complies with the consent
Discovery
of current issues
- [37] In 2016 Mr
Heaney noticed that the floor in the downstairs bedroom of the house appeared
spongy. In December 2016 Mr Heaney and
Ms Bates applied for an assessor’s
report under the Weathertight Homes Resolution Services Act 2006. Mr Alan
Bolderson
was appointed by the Weathertight Homes Resolution Services (WHRS) to
investigate the claim. Mr Bolderson attended the property
in February 2017
to carry out an investigation, and produced a report on 16 March 2017 setting
out his findings (the WHRS report).
The WHRS report itself was not part of the
evidence before me.
- [38] Mr
Bolderson concluded that there was a severe moisture problem in the subfloor
areas of the house; there was insufficient ventilation,
and openings in the
foundation walls were allowing water to drain under the house. The damage
observed by Mr Bolderson included damage
to the framing timber in the south-east
elevation of the house, which had been re-clad during the remedial
work.
- [39] This
proceeding was commenced in the High Court on 8 November
2017.
The evidence at trial
- [40] During the
trial, some key facts relevant to the plaintiff’s claim were established
about the remedial works:
(a) Five or six of 13 patio vents that had existed prior to the
remedial works had been covered over during torch on membrane work
around the
tiled areas during the remedial work (the covered patio vents).
(b) The 15 proposed ventilation holes in plan A-03 of the
Alexander & Co plans were never installed.
(c) The polythene sheet suggested by Alexander & Co was not
installed.
(d) Part of an underdeck accessway that had functioned in effect as a
ventilation opening prior to the remedial works was enclosed
in the course of
the remedial work.
- [41] Mr Heaney
was candid in his acknowledgement that, because of his busy professional life
combined with his visual impairment,
he was not closely involved in the process
for seeking consent for the remedial work and the carrying out of the work. He
said he
did not recall seeing the plans and specifications prepared by Alexander
& Co before they were lodged for Council consent. He
relied on Mr Alexander
for that. He was also unaware of the correspondence, pre-consent, between Mr
Alexander and the Council in
relation to subfloor
ventilation.
- [42] Mr
Alexander gave evidence for the plaintiff. As noted above, Mr Alexander is a
building surveyor and principal of Alexander
& Co. Mr Alexander has
considerable experience and expertise in the investigation of building defects
and modes of failure, design
and management of remedial work, and as an expert
witness in building litigation. In this matter, he gave evidence as a witness of
fact.
- [43] Mr
Alexander’s evidence in cross-examination was that when he viewed the
photographs taken after the remedial works he
observed a very different subfloor
condition from when he had investigated it in 2004/2005. He said that
“something had changed
that made things deteriorate, certainly more
rapidly than historically.”
- [44] In
cross-examination, Mr Alexander confirmed that through his plans he was
proposing to increase the ventilation in the subfloor
area, and there was
nothing in his drawings that would propose to reduce any part of the
building’s compliance with the Building
Code.
- [45] Mr
Alexander’s conclusion, under cross-examination, having seen the report of
subsequent investigations of the house, was
that the plans Alexander & Co
had drawn had not been implemented in terms of the subfloor situation. His view
was that one could
not simply overlook those subfloor issues: “They were
too significant, and the notes on the drawings were significant enough
to be
readily identifiable. So it
doesn’t seem to be a simple oversight to not do them.” He said it
looked to him as though it was a conscious decision
not to implement the
plans.
- [46] Expert
evidence for Ms Bates was given by Mr Trevor Jones, Mr John-Paul Biggelaar, and
Mr Peter Jordan. Mr Jordan is an experienced
building consultant and principal
of Building Condition Assessments Limited. He worked in various roles for
councils before establishing
his own business in 1991. He has provided various
services since then, including advice about the building regulation regime set
up by the Building Act 1991 in relation to issuing consents, the inspection
process, and the issuing of code compliance certificates.
He has also
investigated defective buildings under the Building Act 2004, and has previously
been engaged by lawyers in leaky building litigation.
- [47] Mr Jones is
a building surveyor and director of Maynard Marks Limited, a firm of building
surveyors, project managers, quantity
surveyors, and registered architects that
has been involved with the remediation of a number of defective buildings.
Mr Jones
himself has inspected and reported on numerous leaky buildings,
including more than 250 private dwellings and 40 multi-unit
developments. On 13 February 2018 Mr Heaney and Ms Bates engaged Mr Jones
to investigate the defects in the house and provide
them with advice on
remedial work required. Mr Jones carried out an examination of the house,
including the subfloor area,
on 23 February 2018. He made a second visit to
the house on 24 May 2019 to inspect the subfloor ventilation provisions. Mr
Jones
observed damage in the subfloor timbers, and he took moisture readings and
timber samples. As part of his remit to advise Mr Heaney
and Ms Bates, Mr
Jones also reviewed the relevant parts of the Council’s property file for
the house. Mr Jones’ opinion
was that there was inadequate subfloor
ventilation.
- [48] Mr
Jones’ evidence canvassed in some detail those parts of the Building Code
most relevant to his evidence – cls
E2 (External Moisture), B2
(Durability) and B1 (Structure). He particularly referred to Acceptable Solution
E2/AS1 (E2/AS1).2 Paragraph 10.2.4 states:
2 Building Code clauses have acceptable solutions,
which are documents that set out methods of complying with the Building Code.
Anyone
who complies exactly with the methods described in
The subfloor space of all suspended timber floors shall be ventilated. This
requirement shall be met by providing openings in the
foundation wall, at the
rate of no less than 3500 mm2 of net open area for every m2
of floor area. The openings shall be as near as possible to the underside
of plates and bearers.
- [49] Paragraph
10.2.5 of E2/AS1 states:
Ventilation openings shall be constructed by either one of the
following methods, or by a combination of both methods:
(a) Create continuous gaps, of at least 20 mm wide, between
baseboards around the entire perimeter of the building, and/or
(b) Install perimeter wall ventilators to give sufficient net
open area. Ventilators shall be spaced regularly, commencing 750 mm
from wall
corners and at intervals no greater than 1.8 m to all sides of the building.
- [50] Paragraph
10.2.7 states:
Where the subfloor space cannot be adequately ventilated in
accordance with Paragraph 10.2.6, the ground under a suspended timber
floor
shall be entirely covered with a vapour barrier...
- [51] Clause
10.2.7.1 provides minimum ventilation requirements to be constructed, together
with the vapour barrier:
Even with a vapour barrier, ventilation openings shall:
(a) Have a net open area of no less than 700 mm2 for
every m2 of floor area, and
(b) Be located to provide cross-flow air to all parts of the
subfloor space.
- [52] In Mr
Jones’ opinion, the subfloor area of the house following the remedial work
was not constructed in a manner that prevents
the accumulation of moisture in
the subfloor, resulting in damage to the timber floor and wall framing. He says,
“The damage
as described by Alan Bolderson in the WHRS report ... can be
expected to occur when there is inadequate provision for sub-floor ventilation
in suspended timber floors.”
the acceptable solution for a Building Code clause is deemed to
comply with the Building Code. However, as discussed below at [92], it is not mandatory to follow an
acceptable solution. Alternative methods of construction that comply with the
relevant Building
Code requirements become alternative solutions. Acceptable
Solution E2/AS1 is the main acceptable solution for meeting the requirements
of
E2 of the Building Code. (BRANZ, Building Code Compliance).
- [53] Mr
Jones’ conclusion was that the as-built extent of subfloor ventilation was
not enough to meet E2/AS1 or its predecessor,
NZS 3604.3 He
concluded, “as a result of the lack of sub-floor ventilation, building
elements have been extensively damaged.”
- [54] After
the joint experts’ conference, Mr Jones amended his original statement of
evidence. In the amended portion of
his evidence, Mr Jones observed
that 13 openings in the perimeter foundation had been blocked and were not
venting to the outside
air. Mr Jones did not know how many of these provided
subfloor ventilation when the house was constructed, but noted that they were
now redundant. He assumed that at least six of these vents (the covered patio
vents) were covered over during the remedial work.
- [55] Mr Patrick
O’Hagan and Mr Geoffrey Pope gave evidence for
O’Hagan.
- [56] The Council
elected not to call evidence.
Scene view
- [57] With the
parties’ agreement I visited the house, with counsel, at the commencement
of the trial to obtain an orientation
of the layout of the
house.
THE CLAIM AGAINST THE COUNCIL
- [58] I
deal first with the claims against the Council. In some respects, there is
overlap in the factual issues relating to the claims
against both and Council
and O’Hagan, but I will come to that in the course of my
analysis.
- [59] Ms
Bates’ case – both the key aspects of the evidence and the
submissions – shifted during the course of the
trial. The final form of Ms
Bates’ case was not clear until closing submissions. Unfortunately, that
meant the defendants were
left to attempt to answer a fluid case, including at
the time of making their closing submissions. I have endeavoured to analyse
each aspect of the plaintiff’s claim as it
3 NZS 3604 was an acceptable solution for Building
Code cl B1. It was the predecessor to E2/AS1.
was pleaded, noting where the nature of the claim changed during trial, but the
inconsistencies in the plaintiff’s case has
made that difficult.
- [60] The
plaintiff has pleaded two causes of action against the Council, in negligence
and negligent misstatement, but acknowledged
that the second cause of action
adds nothing to the claim in negligence; to succeed in negligent misstatement Ms
Bates would have
to prove the elements of negligence and show reliance on the
negligent misstatement. In relation to the negligence claim, Ms Bates
says the
Council breached its duty to:
(a) ensure it issued a building consent for building work that
complied with the Building Code;
(b) ensure the building work would be undertaken so as to comply
with the Building Code;
(c) ensure any building work undertaken would be in accordance
with the building consent plans and specifications; and
(d) issue a Code of Compliance Certificate only if it was
satisfied on reasonable grounds that the building work undertaken was in
compliance with the Building Code and/or the building consent.
- [61] The issues
relevant to the claim against the Council are:
(a) Did the Council owe a duty of care to Mr Heaney and Ms
Bates? If so, what was the nature and scope of that duty?
(b) Did the Council breach its duty to Mr Heaney and Ms Bates,
in relation to the grant of the building consent, inspection of the
work, and
the issue of a Code of Compliance Certificate? The particulars of the alleged
breach of duty are:
(i) First, the Council failed to consider and require details of
the polythene sheet to be laid on the subfloor beneath the dwelling
including membrane thickness and junctions with foundations before granting
building consent.
(ii) Second, the Council failed to request and/or receive
calculations or other verification to confirm whether the Alexander &
Co
proposed subfloor ventilation plan (if fully installed) would comply with the
ventilation and air flow requirements set out in
E2/AS1 and NZS 3604.
(iii) Third, the Council failed to request and/or receive
calculations or other verification that the amended plan submitted by
O’Hagan
on 16 July 2007 would comply with the Building Code.
(iv) Fourth, the Council failed to identify that there was
inadequate provision shown on drawings for subfloor ventilation in both
the
original Alexander & Co building consent ABA-62145 and the Scribble drawings
with the amended building consent.
(v) Fifth, the Council failed to specify a vapour barrier as
part of the building consent.
(vi) Sixth, the Council failed to observe during its inspections
that the proposed ventilation holes provided for in the consented
plans had not
been installed.
(vii) Seventh, the Council failed to observe during its
inspections that there was inadequate provision for subfloor ventilation.
(viii) Eighth, the Council issued the code compliance
certificate when it did not have reasonable grounds to be satisfied that the
building work complied with the requirements of the building consent and/or the
Building Code.
(c) If the Council did breach its duty, was the Council’s negligence a
material cause of, or contributor to, the damage to the
house?
(d) If yes, what is the scope of the remedial work required?
Did the Council owe a duty of care to Mr Heaney and Ms
Bates?
- [62] The
Council does not dispute that it owed Mr Heaney and Ms Bates a duty to take
reasonable care in carrying out its building
control functions under the
Building Act 2004, including in issuing the building consent, issuing amendments
to the building consent, carrying out inspections, and issuing a Code
of
Compliance Certificate.4
- [63] The Council
also agrees that a duty of care imposed on a council in relation to its building
control functions under the Building Act 2004, “marches in step”
with its statutory functions.5 In Sunset
Terraces, Justice Heath described the duty to take reasonable care in
performing the three regulatory functions at
issue:6
The obligation of the Council can be no higher than expressed in
statute itself; namely, to be satisfied on all reasonable grounds
that a
building consent should issue; to take reasonable steps in carrying out
inspections and to be satisfied on reasonable grounds
that code compliance
should be certified.
- [64] An
assessment of the scope of the duty therefore requires an assessment of the
relevant provisions of the Building Act 2004. In Body Corporate 160361 v BC
2004 Ltd and BC 2009 Ltd, Whata J usefully summarised the Council’s
obligations under the Building Act 2004, and I adopt his
summary:7
[142] The Council’s common law duty of
care is informed by legislative policy. For present purposes, I do not consider
that
the obligations under the Building Act 2004 are materially different from
the obligations under the 1991 Act:8
4 Invercargill City Council v Hamlin [1994] 3
NZLR 513 (PC).
5 Body Corporate No 207624 v North Shore City Council
[2012] NZSC 83, [2013] 2 NZLR 297 [Spencer on Byron] at [71] and
[194].
6 Body Corporate 188529 v North Shore City Council [2008] NZHC 2300; [2008] 3
NZLR 479 (HC) [Sunset Terraces] at [220]-[221].
7 Body Corporate 160361 v BC 2004 Ltd [2015] NZHC 1803.
8 Spencer on Byron, above n 5, at [217].
(a) The purpose of the Act remains the same, namely to bring about safe and
healthy buildings.9
(b) The role of building consent authorities is to issue
building consents, inspect building work for which it has granted consent,
issue
notices to fix and issue Code Compliance Certificates.10
(c) All building work must comply with the building code to the
extent required by the Act, whether or not a building consent is required
in
respect of building work.11
(d) A person must not carry out any building work (including
construction, alteration, demolition or removal of a building) except
in
accordance with a building consent.12
(e) Before granting a building consent, the building consent
authority must be satisfied on reasonable grounds that the provisions
of the
building code would be met if the building work were properly completed in
accordance with the plans and specifications that
accompanied the application
for consent.13
(f) Every building consent is subject to the condition that the
building consent authority is entitled during normal working hours
to inspect
building work and inspection means taking all reasonable steps to ensure that
the building work is being carried out in
accordance with the building
consent.14
(g) The owner of the building must apply for and the building
consent authority must issue a Code Compliance Certificate within 20
working
days15 if it is satisfied on reasonable grounds that the building
work complies with the building consent.16
(h) The building consent authority may issue a notice to fix to
a person carrying out or supervising the building work if there are
reasonable
grounds they are contravening or failing to comply with the
Act.17
- [65] Where Ms
Bates and the Council disagree is as to how those statutory requirements apply
in this case.
9 At [171]; see the Building Act 2004, s 3 and the
Building Act 1991, s 6(1)(a).
10 Building Act 2004, s 12.
11 Section 16.
12 Section 40.
13 Section 49.
14 Sections 90(2) and (3); and s 222.
15 Section 93(1)(a), but note the building consent authority may
request further information – s 93(4).
16 Section 94(1)(a).
17 Section 163.
- [66] An
essential question is: what were the building works for which consent was sought
by Mr Heaney and Ms Bates and granted by
the Council? The consented works are
set out in the plans and specifications (including the amended plans and
specifications) for
which consent was sought by them.. The scope of the
consented works is pivotal to the Council’s duty of care. This issue also
requires consideration of s 112 of the Act.
Ms Bates’ position
- [67] Ms Bates
says that the building work related, in part, to the subfloor of the house
because:
(a) the installation of the proposed ventilation holes was for
the purpose of improving the subfloor ventilation;
(b) some of the decayed and damaged timber to be removed was in
the subfloor; and
(c) some of the cladding and damaged framing to be removed was
within the subfloor.
- [68] In order to
issue a building consent for that work, the Council had to be satisfied that, if
it were completed in accordance
with the plans and specifications, it would
comply with the performance requirements of the Building Code. The Building Code
included
the specific requirements in cl E2 relating to subfloor
moisture.
- [69] The essence
of Ms Bates’ argument is that, because of that connection to the subfloor,
in carrying out its Building Act functions the Council had a duty to ensure that
when the building works were complete, the subfloor area would comply with the
Building
Code. Ms Bates says that s 112 does not materially change the scope of
that duty owed by the Council. Ms Bates’ case is that
the subfloor area is
not in accordance with E2/AS1 (and/or the Building
Code).
The Council’s
position
- [70] The Council
rejects Ms Bates’ assertions as both wrong at law and contrary to the
plaintiff’s own evidence. It says,
first, that E2/AS1 was not in existence
at the relevant time; at that time E2/AS1’s relevant predecessor was NZS
3604. More
importantly, whatever the relevant acceptable solution, it was not
mandatory; what was required was that the building work perform
in accordance
with the Building Code, it did not matter how the building work
complied.
- [71] Second, the
Council says the relevant provisions of the Building Act 2004 require only that
the proposed new building work comply with the Building Code; the performance of
the existing building under the
Building Code must not be worsened.18
It is not the Council’s obligation, nor does it have the power, to
determine what other work, in addition to the proposed new
building work, might
be required to the house. Nor can it require an upgrade to existing parts of the
house, except in limited circumstances.19 The Council’s role is
to be satisfied that:
(a) the proposed (new) work would be compliant with the Building
Code, if done properly; and
(b) the existing building’s level of compliance with the
Building Code will not worsen.
- [72] The Council
says it is for Ms Bates to establish that the new work for which the building
consent was sought (the consented works)
did not in some way comply with the
Building Code.
- [73] Here, the
proposed new work was for a re-clad, a bathroom extension, and the addition of
15 ventilation holes to be drilled into
the existing perimeter foundations of
the house. There is no suggestion in the evidence that any of that proposed new
building work
would not, if built in accordance with the plans and
specifications, perform in accordance with the Building
Code.
18 Sections 17, 49 and 112.
19 For example, fire egress and disability access (s 112) and if
the building is dangerous or unsanitary (s 122).
- [74] The
building consents, and the ambit of the work covered by them,
were:
(a) The building consent issued on 26 January 2007 (ABA-62145):
the application included the following description of the building
work –
“Re-cladding and bathroom extension to existing residential house. Works
include new paving around perimeter of
the house and lowering of site
levels.” The consent itself described the building work as
“Re-cladding & bathroom
extension to existing house”.
(b) The first amendment to the building consent, issued on 17
April 2007 (ABA-62145A): the application to amend the consent described
the work
as “change plaster coat from STO to Nulite cladding”. The consent
replicated the description of work from the
original consent –
“Re-cladding & bathroom extension to existing house”.
(c) The amended building consent issued in August 2008
(ABA-62145B): the application describes the amendment as “Change of
cladding
from Nu-Lite to Plaster Systems Thermaclad EIFS System”.
- [75] The Council
says the subfloor area was pre-existing; it was not constructed under any of
ABA-62145, ABA-62145A or ABA-62145B.
- [76] The Council
accepts that the purpose of the proposed ventilation holes contained in plan
A-03 was to increase the pre-existing
subfloor ventilation, but says there is no
suggestion from Ms Bates that the proposed ventilation holes would worsen the
existing
building’s code compliance; nor was there any suggestion that the
creation of the proposed ventilation holes could not be done
in a way that would
be Code-compliant. But that, the Council says, is a fundamentally different
matter to imposing a requirement
to bring the existing subfloor area,
constructed some 20 years earlier, to current Code-compliance. That, it says, is
the effect
of Ms Bates’ argument that because the creation of the proposed
ventilation holes touch or concern the subfloor ventilation,
then that somehow
means that the subfloor itself must be brought up to Code.
- [77] The Council
accepts that the consented works included the potential for replacement of
decayed timber, including decayed timber
within the subfloor area. However, it
rejects Ms Bates’ contention that the Council was asked to issue a
building consent for
building work which involved replacing all decayed timber
within the structure of the house including timber within the subfloor
space
adversely affected by moisture ingress.
- [78] The
Council’s submission is that the building consent did not identify any
specific timber to be replaced, but rather provided
that if decayed timber was
discovered during the carrying out of the re-cladding works under the building
consent, then it was to
be dealt with in the manner stated in the conditions of
the consent:
Repairs of Timber affected by Decay
All timber showing any sign of decay is to be removed from the
building and replaced by treated timber as required by NZS 3602. Timber
within
one metre of the decayed timber and accessible timber is to be treated with an
appropriate preservative such as “Osmose
Framesaver” or
“Metalex”.
- [79] The Council
says that Ms Bates conflates the proposed new building work (specifically,
drilling the proposed ventilation holes)
with the existing building. The fact
that the new work touches on or concerns part of the existing building does not
mean that the
Council was required to be satisfied that, following the
completion of the consented works, the pre-existing floor area would comply
with
the airflow requirements set out in E2/AS1.
Discussion
112 Alterations to existing buildings
(1) A building consent authority must not grant a building consent for the
alteration of an existing building, or part of an existing
building, unless the
building consent authority is satisfied that, after the alteration,—
(a) the building will comply, as nearly as is reasonably practicable, with
the provisions of the building code that relate to—
(i) means of escape from fire; and
(ii) access and facilities for persons with disabilities (if this is a
requirement in terms of section 118); and
(b) the building will,—
(i) if it complied with the other provisions of the building code immediately
before the building work began, continue to comply with
those provisions; or
(ii) if it did not comply with the other provisions of the building code
immediately before the building work began, continue to comply
at least to the
same extent as it did then comply.
(2) Despite subsection (1), a territorial authority may, by written notice to
the owner of a building, allow the alteration of an
existing building, or part
of an existing building, without the building complying with provisions of the
building code specified
by the territorial authority if the territorial
authority is satisfied that,—
(a) if the building were required to comply with the relevant provisions of
the building code, the alteration would not take place;
and
(b) the alteration will result in improvements to attributes of the building
that relate to—
(i) means of escape from fire; or
(ii) access and facilities for persons with disabilities; and
(c) the improvements referred to in paragraph (b) outweigh any detriment that
is likely to arise as a result of the building not complying
with the relevant
provisions of the building code.
(3) This section is subject to section 133AT.
- [81] There are
very few decisions considering the effect of s 112. Ms Bates cites Wheeldon v
Body Corporate 342525, where the High Court noted that s 112 does not
detract from the s 17 requirement that all building work must comply with the
Building Code and, after alterations, the whole building must comply with
the
Building Code to the extent specified by the Building
Code.20 While that statement in Wheeldon
is correct on its face, it is somewhat circular. Fitzgerald v IAG New
Zealand Ltd contains a more helpful and direct statement of the effect of s
112:21
[The Building Act] only requires the aspects of
the house that are being repaired to be brought up to current compliance levels.
Elements that are
not repaired may be left at the same level of compliance as
they were originally.
20 Wheeldon v Body Corporate 342525 [2015]
NZHC 884, (2015) 16 NZCPR 829 at [159]- [160];
cited in Andrews Property Services Ltd v Body Corporate 160361
[2016] NZCA 644, [2017] 2 NZLR 772 at [112].
21 Fitzgerald v IAG New Zealand Ltd [2018] NZHC 3447 at
[50].
- [82] The
Ministry of Business, Innovation and Employment (MBIE), the agency responsible
for the Building Act 2004 and associated regulations, has published a guide to
altering an existing building under the legislative regime, which engages
s
112. In the relevant part, that guide says, under “Meeting the
requirements for altering existing buildings”:
Building consent applicants need to ensure their building
consent application includes all the required information to demonstrate:
- that compliance
with other Building Code clauses is no less than what it was prior to the
alteration
- compliance
‘as nearly as is reasonably practicable’ with the Building Code for
fire and accessibility (if applicable),
including evidence of weighing up the
sacrifices and benefits of achieving full compliance. This evidence is best
provided in a thorough
report
- that in the case
of a substantial alteration to an earthquake-prone building, the alteration
includes the necessary seismic work so
the building is no longer earthquake
prone
- that the
proposed alteration (ie new building work) complies with the Building
Code.
- [83] A number of
MBIE Determinations, made under Part 3, subpart 1 of the Building Act 2004,
apply a similar interpretation of s 112.22
- [84] Section 112
provides that a building consent must not be granted for the alteration of part
of an existing building unless the overall building,
following the alteration,
will continue to comply with the Building Code to at least the same extent as
before the alteration. That
means that the proposed alterations must make the
existing building no worse (subject to the limited exceptions referred to in s
112 itself). I agree with the Council that there is no obligation – either
for the owner to do, or for a council to require
– to improve an existing
building’s performance against the Building Code, even where the existing
building does not
comply with the Building Code pre-works.
- [85] What that
means in this case is considered below in the context of each particular alleged
breach of the Council’s duty.
22 MBIE Determination 2012-023; MBIE Determination
2014-058; MBIE Determination 2018-061.
Did the Council breach its duty to Mr Heaney and Ms
Bates?
- [86] Ms
Bates alleges breaches of the duty owed by the Council in respect of each phase
of the Council’s functions – the
grant of the building consent,
inspection of the building work, and issue of the Code of Compliance
Certificate. The statement of
claim sets out seven particulars of those alleged
breaches. I have considered the particulars in the order in which the Council
addressed
them.
Particular 2 – calculations
or other verification of subfloor compliance with E2/AS1
- [87] Particular
2 of the statement of claim alleges the Council:
Failed to request and/or receive calculations or other
verification to confirm whether the Alexander proposed subfloor ventilation
plan
(if fully installed) would comply with the ventilation and air flow requirements
set out in E2/AS1 and NZS3604.
- [88] The
Building Act 2004 requires that before issuing a building consent, the Council
must be satisfied on reasonable grounds that the provisions of the Building
Code
would be met if the building work were properly completed in accordance with the
plans and specifications that accompanied the
application for
consent.23
- [89] Ms
Bates’ case is that the application for consent included extensive
building work within the subfloor of the house, including:
upgrading the
subfloor ventilation with the installation of the new ventilation shown on plan
A-03; removing all damaged and decayed
timber which formed part of the subfloor;
and removing the cladding and all damaged framing, including component parts of
the subfloor
in the south-eastern corner of the house. Mr Jones’ opinion
was that there was inadequate consideration of subfloor ventilation
at the time
the building consent was issued.
- [90] The Council
says, first, that E2/AS1 is not mandatory. What is required is compliance with
the Building Code, not an acceptable
solution per se. Second, Mr
Alexander’s evidence for Ms Bates was that as at 2005/06 the subfloor of
the house was performing
in accordance with the Building Code. His plans for the
remedial
23 Building Act 2004, s 49.
works would not have reduced that compliance. Finally, there is no evidence from
Ms Bates of any industry-wide practice of providing
such calculations.
- [91] The Council
also submitted that the allegation is in direct contradiction to Mr
Jones’ amended evidence for Ms Bates
that the subfloor conditions are
attributable to the covered patio vents, which were not part of any of the
consented works.
I consider that issue below, when I come to consider
causation.
Discussion
- [92] Both
Mr Alexander and Mr Jones, in their evidence for Ms Bates, accepted that E2/AS1
is not mandatory. The house was built before
E2/AS1 existed; at that time NZS
3604 would have been the relevant standard. In terms of subfloor ventilation,
NZS3604 was almost
identical to the later Building Code. Regardless, the essence
of what is required is that the building work must perform in accordance
with
the Building Code, rather than in accordance with an acceptable solution; it
does not matter how the building work complies.
Work undertaken in accordance
with an acceptable solution is simply deemed to comply with the Building Code;
whereas work not undertaken
in accordance with an acceptable solution, but which
nonetheless complies with the Building Code, is known as an alternative
solution.
- [93] The
plaintiff’s own evidence was that, prior to the consented remedial works,
the subfloor area of the house was compliant
with the Building Code.
When Mr Alexander investigated the subfloor in 2004 and 2006 he found no signs
of deterioration –
there was no decay, no mould or dampness on the
subfloor timber, and the earth in the subfloor was not saturated. He concluded
that
it had, from its construction in 1987, performed in accordance with the
Building Code.
- [94] Mr
Alexander confirmed that there was nothing in his proposed plans for the
remedial work that would have reduced any part of
the building’s
compliance with cl E2 of the Building Code. His plan to add the proposed
ventilation holes would improve the
ventilation in the existing subfloor
area.
- [95] The
specific allegation by the plaintiff is of a failure by the Council to request
and/or receive calculations or other verification
to confirm whether the
Alexander &
Co proposed subfloor ventilation plan (if fully installed) would comply with the
ventilation and airflow requirements set out in
E2/AS1 and NZS 3604. There was
no evidence before the Court that this was an industry-wide, or even a common,
practice. Mr Alexander
said that it was never his practice.
- [96] I conclude
that this aspect of the claim cannot succeed.
Particular 1 – polythene
sheet to be laid on subfloor
- [97] Particular
1 of the statement of claim alleges the Council:
Failed to consider and require details of the polythene sheet to
be laid on the subfloor ground beneath the dwelling including membrane
thickness
and junctions with foundations before granting building consent.
- [98] This claim
relates to an exchange between the Council and Alexander & Co, prior to the
Council issuing the building consent.
On 2 October 2006 the Council wrote to
Alexander & Co seeking further information in respect of the application for
consent,
including: “Sheet A-29 details sub floor ventilation requirement,
provide details to comply with NZS 3604: 1999 s 6.14 or specific
technical
information.”
- [99] Alexander
& Co replied on 7 November 2006 saying in relation to this
query:
Sub-floor ventilation of the existing house is insufficient
mainly due to the lack of cross ventilation and the high ground levels
around
significant areas of the house. We have improved the sub-floor ventilation by
providing vents in all possible areas and therefore
providing cross ventilation
that is currently absent. As an additional precaution we are willing to specify
a polythene sheet to
be laid on the sub-floor ground beneath the house to
mitigate any concern with inadequate sub-floor ventilation. Locations of
sub-floor
ventilation are shown on page A03.
- [100] The
Council annotated this response: “Good idea”.
- [101] The plans
and specifications as approved by the Council when it issued the building
consent on 25 January 2007 were not amended
to require that a polythene sheet be
laid on the subfloor ground. Mr Alexander’s evidence was that the
polythene sheet was
not added to the drawings, but to the scope of work that was
part of the builder’s specification.
- [102] Mr Jones
said he did not know why the suggestion made by Alexander & Co on 7 November
2006 that a polythene sheet be laid
on the subfloor ground underneath the house
was not incorporated into the building consent documentation, nor required in
any conditions
to the building consent.
- [103] Mr Jones
also said:
... If the original ventilation provisions are considered in
combination with the proposed new 15 openings in the Alexander design,
I assess
that the ventilation requirements of E2/AS1 and NZS3604 would likely have been
met.
If a vapour barrier had been specified, even without the
original openings being known of or taken into consideration, the Alexander
proposed new 15 ventilation holes would likely have complied with the
requirements of E2/AS1.
- [104] Mr Jordan
said that the Council ought to have required that details of the polythene sheet
be incorporated into the plans and
specifications when it issued the consent, in
order to be satisfied that the proposed building work would comply with the
Building
Code.
- [105] In
response, the Council says that the polythene sheet, although suggested by Mr
Alexander, was not specified. No evidence was
led by Ms Bates on that issue. The
Council does not have authority to impose additional requirements on building
work over and above
those contained in the Building Code.
Discussion
- [106] The
application for building consent, and the consented plans and specifications,
did not include provision for laying a polythene
sheet in the subfloor. Mr
Heaney acknowledged that the polythene sheet was specified in the
builder’s specification only, not
in the plans and specifications that
went to the Council for consent.
- [107] While Mr
Alexander did specify laying of a polythene sheet as part of the scope of works
included in the builder’s specification,
his evidence was that nothing
raised by the Council at that point had caused him to think he had got anything
wrong in his proposed
plans. No evidence was led as to why Mr Heaney and Ms
Bates, or their
builders, did not lay the polythene sheet under the house during the course of
the remedial works (it appears they did so subsequently,
in February 2019).
- [108] I agree
with the Council that, notwithstanding its notation that a polythene sheet was a
“good idea”, in the absence
of the polythene sheet being included in
the plans and specifications for which consent was sought, the Council did not
have authority
to impose additional requirements in addition to those required
in the Building Code. I therefore find the Council was not negligent
in failing
to require specification of a polythene sheet before granting the building
consent.
- [109] I also
note that by the stage of closing submissions Ms Bates conceded that the alleged
negligence of the Council in relation
to issue of the building consent would not
have caused any loss, if it were the only negligent act on the part of the
Council. She
says if the proposed ventilation holes shown on the Alexander &
Co plans had been installed as required, the total subfloor ventilation
of the
house would have been sufficient to meet the requirements of NZS 3604. She says,
relying on Mr Jones’ evidence, that
it is more likely than not that the
damage would not have occurred had the proposed ventilation holes shown on the
plans been installed.
- [110] This
aspect of the claim cannot succeed.
Particular 3 – calculations
or other verification for O’Hagan amendment in July 2007
- [111] Particular
3 of the statement of claim alleges the Council:
Failed to request and/or receive calculations or other
verification that the amended plan submitted by O’Hagan Building
Consultants
Limited (16 July 2007) would comply with the Building Code.
- [112] This
claim relates to the change to the plans sought by O’Hagan in July 2007.
Mr Heaney’s evidence was that he wanted
the cladding above the patios to
finish close to the external ground level, for aesthetic purposes. He contacted
Mr Pope at O’Hagan
to discuss a possible solution whereby waterproofing
would be installed under some of the tiles, extending up the wall beneath the
cladding. Mr Heaney asked Mr Pope to provide a sketch of the solution, which Mr
Heaney then emailed to the Council.
Mr Pope and Mr Borich (an employee of Brackenridge) then met with the Council on
site on 6 July 2007 to discuss the solution.
- [113] After the
meeting Mr Pope wrote to the Council, on 16 July 2007, in the following
terms:
We have replaced detail 26, page A36 with a new chimney flashing
detail provided by Scribble Ltd. We have also replaced detail 12
page 24 with
Scribble Ltd details as per attached.
The crossflow ventilation as proposed on original drawings
should now be deleted as the torchon membrane will be covering this area.
Crossflow ventilation should be created from the north and south end of the
dwelling and from under timber deck as per original drawings
A03 proposed
ventilation.
- [114] As
noted above, five or six of 13 existing patio vents that had existed prior to
2007 were covered over during the torch on
membrane work around the tiled areas
during the remedial work. It appears that they were covered over, presumably by
Brackenridge,
when executing the O’Hagan/Scribble design to meet Mr
Heaney’s desire to allow the cladding to be brought down to the
level of
the patios.
- [115] Mr Jones
notes that the 16 July 2007 letter from O’Hagan to the Council was not
followed up with updated plans to confirm
the intended change to the subfloor
ventilation. Nor were calculations provided to confirm whether the proposed
ventilation would
comply with the Building Code.
- [116] It is that
letter and the attached Scribble plan that Ms Bates says required the Council to
seek from O’Hagan calculations
or other verification that the amended plan
would comply with the Building Code. This particular of the claim against the
Council
must be seen in the context of the claim pleaded against O’Hagan
which refers to the changes proposed on 17 July 2007 as “altering
the
sub-floor ventilation”. The calculations or verification sought relate to
those alleged alterations to the subfloor ventilation.
Ms Bates says the
consequence of adopting the detail provided by O’Hagan was to cover over
existing ventilation holes on the
patio.
- [117] Mr Jordan
said that a prudent council would have required calculations and/or appropriate
verification that the subfloor ventilation
proposed would comply with the
Building Code, before it approved the amended details.
- [118] As with
the claim at particular 2, the Council points to the absence of any evidence of
an industry-wide practice of requiring
such calculations. It refers to the
evidence from Mr Alexander, who said it was not his
practice.
- [119] The
Council also refers to the plaintiff’s own evidence, through Mr Jones,
that the subfloor condition is attributable
to the covered patio vents. Mr Jones
accepted in cross-examination that there was no evidence to suggest that the 16
July 2007 letter
and attached Scribble detail concerned those pre-existing
vents. Mr Jones also accepted that the covering of the patio vents was
not part
of the consented plans for the remedial work. He accepted in cross-examination
that the torch on membrane work referred
to in the 16 July 2007 letter could
have been executed without covering the existing patio vents, because it would
be possible to
dress the membrane into the vents rather than taking the membrane
over the top. On Mr Jones’ evidence, the Council says, there
was no
proposed change to the subfloor ventilation and therefore no obligation on the
Council to seek further information.
Discussion
- [120] While
a claim about the reference to ventilation in the 16 July 2007 letter had
previously formed part of Ms Bates’ claim
against O’Hagan, that was
not the case by the time of trial. In closing, Mr Rainey, counsel for Ms Bates,
said the only remaining
relevance of this particular aspect of the claim against
the Council was in respect of the Council’s assertion that the requirement
for the proposed ventilation holes shown on Alexander & Co’s plan A-03
was “superseded” when the amended building
consent was approved in
2008. Ms Bates, as I will come to discuss, does not accept that assertion and
says the requirement to include
the proposed ventilation holes remained. I
consider that issue in relation to particular 6 of the claim discussed below,
but for
completeness at this stage I confirm my view that the 16 July 2007
letter did not specify or require removal of the proposed ventilation
holes, and
I do not accept that the effect of the 16 July letter was to specify or require
the covering of the patio vents.
- [121] The
O’Hagan letter of 16 July was, on its face, somewhat ambiguous. The first
sentence referred to cross-flow ventilation
“as proposed on original
drawings” being deleted. One might take that as a reference to
the Alexander &
Co drawings.
However, the second sentence refers to creating cross-flow ventilation “as
per original drawings A-03 proposed ventilation”,
which suggests
otherwise.
- [122] Mr Pope,
the author of the letter, said it was not intended to mean the deletion of any
existing ventilation, and the resulting
approved change to Detail 12 made no
changes to drawing A-03 in terms of the proposed ventilation holes. As I have
noted, Mr Jones
accepted that was so. Mr Jordan accepted under cross-examination
that where the 16 July 2007 letter said, “created from the
north and south
end of the dwelling and from under the timber deck as per original drawings A-03
proposed ventilation”, it
was referring to the proposed ventilation holes.
He too agreed that Detail 12 drawn by Scribble, and submitted by O’Hagan,
did not impact on the proposed ventilation holes.
- [123] In light
of Ms Bates’ revised position I conclude that I am not required to reach a
view on the claim at particular 3.
If I had been, I would have concluded (as for
the claim at particular 2) that in the absence of evidence that requirement of
such
calculations was a widespread or usual practice, the Council was not
negligent in not seeking such calculations before issuing its
consent to the
amendment.
- [124] In any
event, as the Council flagged, Mr Jones’ evidence that the subfloor
condition was attributable to the covered patio
vents, together with his
acceptance that the reference to crossflow ventilation “as proposed on the
original drawings”
was a reference to plan A-03, would have caused
difficulties for Ms Bates in establishing causation in relation to this
particular
of the claim.
Particular 5 – vapour
barrier
- [125] Particular
5 of the statement of claim alleges the Council:
Failed to specify a vapour barrier as part of the building
consent.
- [126] It is not
clear how this particular of the claim differs from particular 1, which is
discussed above. As the Council notes,
it has no “specification”
role under the Building Act 2004. I reach the same conclusion as in relation to
particular 1.
Particular 4 –
failure to identify that there was inadequate provision for subfloor ventilation
provided for in drawings for
the building consent and the amended building
consent
- [127] Particular
4 of the statement of claim alleges the Council:
Failed to identify that there was inadequate provision shown on
drawings for subfloor ventilation in both the original Alexander building
consent ABA-62145 and the amended Scribble drawings with amended building
consent ABA62145B.
- [128] The claim
at particulars 2 and 3 was that the Council ought to have sought calculations or
other verification in order to be
sure that the original consent application,
and the changes by O’Hagan in 2007, would comply with the relevant
acceptable solution
or the Building Code. Particular 4 is a related but broader
claim.
- [129] Mr Jones
was critical of the fact that no calculations were provided or required to
confirm whether the Alexander & Co proposed
ventilation plan would comply
with the ventilation and airflow requirements in E2/AS1 and NZS 3604. Mr Jones
did his own calculations
and concluded that the proposed ventilation holes alone
would not comply with E2/AS1 and NZS 3604. However, he concluded that the
proposed ventilation holes together with original ventilation provisions would
likely have been sufficient to meet the requirements
of E2/AS1 and NZS 3604.
Alternatively, the proposed ventilation holes together with the polythene sheet
would have met the requirements.
Discussion
- [130] I
accept the Council’s submission that this is in effect an allegation that
the Council ought to have required that the
existing subfloor area was upgraded
as part of the proposed (new) building work. I agree that the claim is
misconceived because:
(a) It is premised on E2/AS1 being mandatory, which it is
not.
(b) Mr Alexander’s evidence for Ms Bates was that the
subfloor area of the existing building had performed in accordance with
the
Building Code, notwithstanding it was constructed other than in accordance with
E2/AS1.
(c) As I have already found, the Council’s obligations are different in
respect of the proposed (new) building work and the
existing building. The
obligation under ss 17 and 49 of the Building Act 2004 is to consider whether
the proposed building work detailed in the building consent application complies
with the Building Code; the
proposed work, as an alteration, does not need to
bring the whole building into compliance with the Building Code. The Council
need
only consider whether the building as a whole will continue to comply with
the other provisions of the Building Code to at least
the same extent as prior
to the alteration. There was no evidence that anything in the Alexander & Co
plans, if implemented correctly,
would have worsened the performance of the
existing building.
(d) Finally, I note that this aspect of the claim is
inconsistent with Mr Jones’ amended evidence during the trial that the
subfloor conditions can be attributed to the covered patio vents (which were not
subject to any building consent), not anything in
the consented plans or amended
consented plans.
- [131] For those
reasons, I conclude that the Council was not negligent in respect of particular
4.
Particular 6 – alleged
failure to observe during inspections that the proposed ventilation holes had
not been installed
- [132] Particulars
6 and 7 of the claim relate to the Council’s inspection
obligations.
- [133] Particular
6 of the statement of claim alleges the Council:
Failed to observe that the ventilation holes provided in the
consented plans had not been installed during its inspections.
- [134] Alexander
& Co’s plans included, at plan A-03, the proposed ventilation
holes
- – provision
for the installation of 15 new ventilation holes of 125 mm diameter, opening
directly into the subfloor space,
around the perimeter of the house.
Mr Alexander’s evidence in cross-examination was that Details 15 and 17 of
the
design provided for the installation of vents through the cladding in those
areas of the house where the concrete footing did not
come as high as the floor
level of the house, so some of the subfloor outer wall was formed by cladding.
In those areas, the design
was to install vents through the cladding to provide
further ventilation. In some places, there would be a hole in the masonry for
the ventilation. In other places, there would be a hole in the subfloor timber
framing and the plaster system. That was because the
ground levels changed
around the house. The important thing was that the hole was clearly above
ground level and would not
allow water to flow through it. Mr
Alexander said that his intention was that the 125 mm ventilation openings would
have
a grill or a grate installed over them, but one that effectively maintained
the same ventilation area and did not materially reduce
the available opening of
125 mm diameter.
- [135] As noted
above, the 15 proposed ventilation holes were not installed during the course of
the remedial work.
- [136] Ms
Bates relied on the evidence of Mr Jordan and Mr Jones in relation to the
Council’s inspection function. The Council
carried out 18
inspections between 14 May 2007 and 11 February 2009. Mr Jordan observed that
the Council’s inspection
list did not include any specific inspection
during which subfloor ventilation would be inspected. His view was that a
“prudent
Council would have given consideration to and identified a lack
of sub-floor ventilation” during the following
inspections:
- Bathroom
foundations – 14/5/07
- Bond
beam – 18/5/07
- Concrete
slab en-suite – 12/6/07
- Preline,
stage 1 – 26/6/07
- Wet
area membrane, ground floor over concrete – 24/9/08
- Drainage,
including comment for deck clearance northern side of house
–
3/11/08
g. Final – 11/2/09
- [137] Mr Jones
said that at the time of the Council’s final inspection it “would
have been straightforward to see that
the ventilation holes provided in the
consented plans, had not been installed.”
- [138] The
Council says it is telling that Mr Jordan’s evidence on this issue was
cast in general terms. Notwithstanding his
willingness to make other specific
criticisms of the Council, Mr Jordan did not specifically comment on whether the
Council should have observed the absence of the proposed ventilation
holes during its inspections. The Council also says that Mr Jordan had not
worked
as a council officer in a consent processing role under the Building Act
1991 or the Building Act 2004, and is unable to give any meaningful evidence as
to what was required of a Council to meet its requisite standard of care. Mr
Jordan
candidly acknowledged in cross-examination “My evidence is really
not what a council officer did, but more what it ought to
have done to meet its
obligations.”
- [139] The
Council also said that Mr Jones did not assert or qualify himself as having any
expertise in Council matters, and his evidence
does not constitute evidence as
to what would be expected of a council.
- [140] The
Council says that, since the proposed ventilation holes were not in fact
installed, it is unclear why Ms Bates alleges the
Council should have inspected
them. Decisions about reducing or increasing the work to the house as originally
proposed were within
the plaintiff’s knowledge. But Ms Bates led no
evidence as to why the proposed ventilation holes were not installed and
chose not to re-examine Mr Alexander on his opinion that it must have been
a conscious decision not to install the vents,
not simply an
oversight.
- [141] The
Council also says that plan A-03 was not works relating to the re-clad, nor to
the bathroom extension. The proposed ventilation
holes were an upgrade to the
existing subfloor. Consent was given, but that did not mean that Ms Bates and
Mr Heaney were obliged
to carry out those works. Obtaining a building consent
does not mean it is mandatory to do that building work. The owner is entitled
to
reduce the scope of the proposed work.
Discussion
- [142] Section 90
of the Building Act 2004 defines the relevant powers of building consent
authorities in relation to inspections and also imposes a duty on them to take
all
reasonable steps to ensure that the building work is carried out in
accordance with the building consent. It provides:
90 Inspections by building consent authorities
(1) Every building consent is subject to the condition that
agents authorised by the building consent authority for the purposes of
this
section are entitled, at all times during normal working hours or while building
work is being done, to inspect—
(a) land on which building work is being or is proposed to be
carried out; and
(b) building work that has been or is being carried out on or
off the building site; and
(c) any building.
(2) The provisions (if any) that are endorsed on a building
consent in relation to inspection during the carrying out of building
work must
be taken to include the provisions of this section.
(3) In this section, inspection means the taking of all
reasonable steps to ensure that building work is being carried out in accordance
with a building consent.
- [143] In
Reeves v Lakes Environmental Ltd,24 Dunningham J
said:
It is clear from s 90 that the express purpose of an inspection
is to ensure that the building work being inspected complies with the building
consent.
That ensures that, at each stage of the building process, the building
consent has been implemented, allowing a code compliance certificate
to issue
when the work is completed.
- [144] Here, the
building consent included the addition of the proposed ventilation holes. On the
face of it, the Council’s duty
to inspect included a duty to inspect the
installation of the proposed ventilation holes.
- [145] The
Council did not call any evidence about what was entailed in each of the
inspections it undertook as part of its inspection
regime. Nor did Ms Bates call
any
24 Reeves v Lakes Environmental Ltd [2014]
NZHC 2760 at [64].
expert evidence other than the general evidence of Mr Jordan; for example from a
building inspector, as to exactly when and how the
absence of the proposed
ventilation holes should have been detected. There was no evidence about what
the Council reported to Ms
Bates and Mr Heaney following its inspections; it
appears that it did not report to them that the proposed ventilation holes had
been installed.
- [146] I am left
to infer from that absence of evidence that the Council did not inspect for the
installation of the proposed ventilation
holes. The question is whether it was
negligent in not doing so. There are two complicating factors in answering that
question:
(a) The “superseded” stamp which was applied to plan
A-03, amongst other documents, on 8 May 2008.
(b) The fact that the proposed ventilation holes were not in
fact installed and, as I have noted, as at March 2008 were no longer
part of the
scope of works between Ms Bates and Mr Heaney, and their builder Mr
Green. Further, at that point it was, in
practical terms, too late to install
them.
- [147] I consider
each of those factors in turn.
“Superseded”
- [148] As noted
above, some 20 documents that formed part of the building consent were stamped
“superseded” on 8 May 2008,
the same day that the amended building
consent was approved. On each of them there was a handwritten notation
“Refer ABA62145/B”
– the amended building consent to allow for
the change of the cladding system. Some of those documents also contained a
reference
to new Scribble plans, but plan A-03 was not among
those.
- [149] The
submission for Ms Bates is that plan A-03 was superseded only in relation to
those details approved as part of the amended
building consent. Ms Bates says
that the application for amendment sought to change only the type of cladding on
the house, not to
make any other amendments. Mr Alexander confirmed that the
amended
Scribble designs relating to the amended building consent did not change the
design intent of his plan regarding subfloor ventilation.
It was, he said,
“effectively the same as my plan ... except ... they’ve changed the
cladding.”
- [150] Ms Bates
has not made any allegation that the Council did anything wrong in stamping plan
A-03 “superseded”.
- [151] The
Council chose not to call any evidence, and there was therefore no evidence
before the Court as to why plan A-03 and the
other documentation was stamped
“superseded”. The Council’s submission was that interpretation
in relation to a
public document (such as a notated plan forming part of a
building consent) is an objective exercise; the test is simply what an
ordinary
member of the public would make of the information contained in a public
document.
- [152] In Body
Corporate 160361 v BC 2004 Ltd and BC 2009
Ltd,25 Whata J in the High Court
applied the approach of the Privy Council in Opua Ferries Ltd v Fullers Bay
of Islands Ltd,26 and held that the subjective view of the
Council officer who applied the stamp was not probative as to the legal effect.
Justice Whata
(endorsed by the Court of Appeal on this point27)
adopted and refined the Privy Council test:28
The persons ordinarily expected to rely on specifications are
qualified builders and building inspectors, not ordinary members of
the public.
The proper test is therefore, in my view, what would the ordinary builder or
inspector make of the revised stamp?
- [153] I adopt
Whata J’s test, that is, what would the “ordinary building
inspector” make of the “superseded”
stamp?
- [154] Plan
A-03 was titled “Proposed New Paving, Ventilation & Cladding
Termination Detail Locator Plan”. In my view
a building inspector would
not simply have assumed from the “superseded” stamp that everything
in that plan was superseded,
but would have looked to other relevant documents
to understand what “superseded” meant. Underneath the
“superseded”
stamp on A-03 was the
25 Body Corporate 160361 v BC 2004 Ltd [2015]
NZHC 1803 at [157]- [158].
26 Opua Ferries Ltd v Fullers Bay of Islands Ltd [2003]
UKPC 19, [2003] 3 NZLR 740 at [20].
27 Andrews Property Services Ltd v Body Corporate 16036,
above n 20.
28 Body Corporate 160361 v BC 2004 Ltd, above n 25, at [157].
handwritten reference to the amended building consent. Although, as I have
noted, there was no reference on plan A-03 to the new
Scribble plans, in my view
the building inspector would have looked at the amended building consent
application and related documents
to understand how and in what way the
specification at A-03 was affected. That exercise would have revealed that the
Alexander &
Co Detail 15 was replaced with the Scribble detail that shows
the same proposed ventilation holes as on plan A-03.
- [155] That being
the case, the Council’s inspection obligation in relation to the proposed
ventilation holes would have remained.
Proposed ventilation holes not installed
- [156] However, I
have concluded that the “superseded” stamp is something of a red
herring. Of greater relevance to the
Council’s response to Ms Bates’
allegations is what appears to have been an earlier decision by Ms Bates and Mr
Heaney
not to install the proposed ventilation holes.
- [157] Mr
Alexander’s evidence was that the omission of the proposed ventilation
holes could not have been a simple oversight;
this aspect of the plans was too
significant to have been simply overlooked, and it must have been due to a
conscious decision to
omit certain features in the Alexander & Co plans. As
Mr Alexander put it in cross-examination, “evidently ... somebody
thought
they were not very important”. Mr Heaney’s evidence in
cross-examination was that Mr Alexander was a “very
thorough, competent
building surveyor” and that he does “the best job you can
get.” Mr Alexander impressed me as
a careful, detached and objective
witness, notwithstanding his earlier involvement in the project. I accept his
evidence on the omission
of the proposed ventilation holes. Significantly, Ms
Bates’ counsel did not re-examine Mr Alexander on that aspect of his
evidence.
- [158] It is not
clear when the decision to omit the proposed ventilation holes was made, or who
made the decision. Mr Heaney’s
evidence was that he was not aware of the
proposed ventilation holes set out by Mr Alexander in the building consent
drawings. Although
Mr Heaney had in February 2007 asked Mr Alexander for the
building consent documentation so he could “review it in its
entirety”,
Mr Heaney’s
evidence at trial was that in fact he would not have looked at the plans once
received. In addition, Brackenridge had on two occasions
provided Mr Heaney with
a programme which referred to the installation of the proposed ventilation holes
and sought direction from
him, but Mr Heaney’s evidence was that he had
not read those documents.
- [159] Ms Bates
led no evidence on why the proposed ventilation holes were not installed by
Brackenridge prior to the termination of
their engagement in about February
2008. Brackenridge representatives were not called to give
evidence.
- [160] Mr
Heaney’s detailed instructions to Mr Green of 10 March 2008, which
commenced “I shall identify below what I think
are the tasks left to
complete. There may be more that I have overlooked ...” did not include
any reference to installation
of the proposed ventilation holes. The plaintiff
did not call Mr Green to give evidence.
- [161] Mr Jones
accepted that by May 2008 it would have been impractical to install the proposed
ventilation holes, given the cladding
had been completed.
- [162] Ms Bates
nevertheless says that the Council was negligent in not detecting and reporting
on the absence of the ventilation holes
as part of its inspection obligation.
She relies on Birch v Palmerston North City
Council.29 What was at issue in
Birch was the Council’s inspection obligations in relation to
defective building work. The Council’s inspection did not detect
the
absence of “birdsmouthing” over the top wall plate, which led to
inadequate structural support of the roof and concrete
tiles upon it.30
The Court found that there were “serious defects in the structural
integrity” of the building.31
- [163] Here, the
alleged negligence was the failure to detect and/or report on an omission to
carry out work, rather than defective
work per se. It was not an important
structural omission, which went to the integrity and safety of the consented
building works,
as in Birch.32 I have accepted that the
installation of the proposed ventilation
29 Birch v Palmerston North City Council HC
Wellington CP 116/92, 22 July 1998.
30 At 3.
31 At 3.
32 At 6.
was an upgrade to the existing building subfloor (Mr Alexander’s evidence
was that prior to the remedial work the subfloor
complied with the performance
requirements of the Building Code). It was open to Ms Bates and Mr Heaney, as
building owners, to reduce
the scope of the consented work.
- [164] I find
that I can properly draw the inference that as of April 2008 Ms Bates and Mr
Heaney (or their builder, Brackenridge)
had decided not to install the proposed
ventilation holes. I arrive at that conclusion through a combination of
factors: the
plaintiff did not re-examine Mr Alexander on his evidence that the
decision not to install the ventilation must have been deliberate;
the plaintiff
did not call either Brackenridge or Mr Green to rebut the suggestion that, as at
early March 2008, the proposed ventilation
no longer formed part of the scope
of works; and nor did Mr Heaney himself address the question in his
evidence.
- [165] However,
the difficulty for the Council is that there is no evidence that it received
notification of that decision, whether
from Mr Heaney and Ms Bates themselves,
or from Brackenridge. The Council says the "superseded" stamp supports the view
that Ms Bates
and Mr Heaney had made that decision, but in the absence of direct
evidence on the point, it is not enough to say the owners must
have already
known (although that of course would be relevant to any question of contributory
negligence by Ms Bates and Mr Heaney).
I conclude that the Council's inspection
obligation required it to inspect whether the proposed ventilation had been
installed and
report to the owners accordingly and it failed to do
so.
Particular 7 – alleged failure to observe during
inspections that there was inadequate provision for subfloor ventilation
- [166] Particular
7 of the statement of claim alleges the Council:
Failed to observe during its inspections that there was
inadequate provision for subfloor ventilation.
- [167] As the
Council noted in closing submissions, it is not clear what this specific
allegation means. Plainly it is intended to
be broader than particular 6, which
relates specifically to the alleged failure to observe that the proposed
ventilation holes had
not been installed. Ms Bates relies on Mr Jordan’s
evidence that “a prudent Council
would have given consideration to and identified a lack of subfloor
ventilation” at the inspections listed above at [136]. The Council says that is inadequate
to establish that the Council was in breach.
- [168] To the
extent that the allegation refers to a failure by the Council to identify that
the existing subfloor area was not constructed
in accordance with E2/AS1, then
for the reasons already advanced in relation to particular 4,33 that
claim cannot succeed. To the extent that it replicates particular 6, I repeat my
finding in relation to that aspect of the claim.
The issue of the Code of Compliance
Certificate
- [169] Ms Bates
did not plead particulars of the allegation that the Council was negligent in
issuing the Code of Compliance Certificate.
In closing counsel for Ms Bates
submitted that the failure to install the proposed ventilation holes could
easily have been identified
by the Council in the course of its inspections,
prior to issuing the final Code of Compliance Certificate, but was not. None of
the producer statements received by the Council related to the subfloor
ventilation. Accordingly, the Council did not have any grounds
to be satisfied
that the building work had been completed in accordance with the consent, and
its decision to issue the Code of Compliance
Certificate was negligent. The
Council ought to have insisted that the proposed ventilation holes be
installed.
- [170] In
response, the Council says that to the extent that the subfloor ventilation was
relevant to the re-clad works, that could
only be in relation to the new
subfloor framing, and the Council did ultimately receive a PS4 from
O’Hagan. Ms Bates has not
alleged that the Council was unreasonable to
rely on the PS4 from O’Hagan.
Discussion
- [171] It follows
from my findings in relation to particular 6 that the Council could not have
been satisfied that the building work
had been completed in accordance with the
consent, and ought not to have issued a Code of Compliance
Certificate.
33 See above at [130].
Was the Council’s negligence a material cause of, or
contributor to, the damage to the house?
- [172] In
view of my findings that the Council breached its duty to Mr Heaney and Ms Bates
in its inspection obligations in relation
to the proposed ventilation holes
(particular 6) and the issue of the Code of Compliance Certificate, I now
consider whether the
Council’s negligence in those respects was the cause
of Ms Bates’ loss.
- [173] Ms Bates
says that the Council’s negligent acts or omissions in relation to the
remedial work are the “but for”
cause of the damage to the subfloor
of the house. Ms Bates says that she has established that if the proposed
ventilation had been
installed as provided for in plan A-03, the subfloor would
have complied with NZS 3604. However, because of the Council’s
negligence, the proposed ventilation was not installed and the ventilation of
the subfloor was inadequate to achieve compliance with
the performance
requirements of the Building Code.
- [174] The
Council says, first, that Ms Bates has not clearly identified the damage for
which she claims.
- [175] In terms
of causation, the Council points to Mr Jones’ evidence that he attributed
the subfloor condition to the covered
patio vents. There is no allegation that
the Council was responsible for the covering of the patio vents. In addition,
the covering
of the patio vents was unconsented works; the Council did not have
a duty to protect against the consequences of unconsented works
done by or on
behalf of Ms Bates and Mr Heaney.
- [176] On the
basis of Mr Jones’ evidence, the Council says that Ms Bates must establish
that the negligence in relation to the
omission of the proposed ventilation
holes was a material cause of or contributor to the damage to the subfloor. It
says the requirements
of legal causation are not
met.
Discussion
Defect/damage
- [177] The
plaintiff has the legal burden of proof as to alleged damage and also, as a
matter of fact, has the power to investigate
and prove damage. In Sunset
Terraces Heath J said:34
... evidence must be weighed
according to the proof which it was within the power of one side to have
produced and in the power of
the other to have contradicted.
- [178] The
plaintiff’s statement of claim describes the “defect” in the
house that is alleged to have been caused
by the defendants’ negligence in
the following terms:
Inadequate provision for prevention of dampness within the
sub-floor space, including a lack of ventilation resulting in undue dampness
to
building elements, including decay to structural timber framing.
(Failure to achieve B2.3.1, E2.3.2)
- [179] I agree
with the Council that is an unhelpful pleading, in that it conflates what is
alleged to be the “defect”,
that is, the error of construction, and
the resulting “damage” (and thus breach of the Building Code). The
Council cites
Ministry of Education v H Construction Ltd where Downs J
considered a similarly imprecise use of the terms and concluded that the term
“defect” means “some
error, shortcoming or imperfection in
relation to an aspect of construction.”35
- [180] The
Council also submits that Ms Bates has not clearly identified what the
“defect” is. The plaintiff’s evidence
as filed (the evidence
of Mr Jones) was that the defect, or what was done wrong, was that the subfloor
was not constructed in accordance
with E2/AS1. However his subsequent evidence
pointed to the covered patio vents as the alleged
“defect”.
- [181] A Joint
Experts’ Statement from Mr Jones, Mr Biggelaar, Mr Geoff Bayley, and Mr
Matthew Earley records:
34 Sunset Terraces, above n 6, at [58].
35 Ministry of Education v H Construction North Island Ltd
[2018] NZHC 871 at [61]- [63].
All experts agree that there is damage to the southern end sub-floor timbers
caused by moisture as a result, at least in part to inadequate
ventilation.
...
The experts agree there are various contributing moisture
sources as per their individual briefs.
- [182] As both
defendants note, the only relevant expert witness to give detailed evidence on
this issue was Mr Jones. Mr Jones’
evidence (as served) was that the lack
of adequate subfloor ventilation has caused extensive damage to the subfloor of
the house.
In his brief of evidence, Mr Jones said:
The sub-floor area following the remedial re-cladding work in
2008 has not been constructed in a manner that prevents the accumulation
of
moisture in the sub-floor resulting in damage to the timber floor and wall
framing, as a result of inadequate provision for sub-floor
ventilation. The
damage as described by Alan Bolderson in the WHRS report and by me later in this
brief, can be expected to occur
when there is inadequate provision for sub-floor
ventilation in suspended timber floors.
- [183] The
plaintiff’s evidence as to damage to the subfloor was not comprehensive.
Although Mr Jones referred to the damage
to the subfloor as
“widespread”, his evidence did not convincingly establish that. As
the Council notes, Mr Jones’
assertion of “widespread damage”
was evidentially supported by only eight samples taken by Mr Jones (all located
at the
south-east end of the house and chosen because they appeared
moisture-affected), together with about 30 photos from within the subfloor
void,
10 showing moisture-meter readings and, in the Council’s words,
“overall simply lacking any cogent
evaluation.”
- [184] Mr Jones
confirmed that he did not take any samples or undertake any other form of
destructive testing other than the eight
samples. He did not carry out any form
of assessment to verify or form his own view in respect of the testing and
samples undertaken
by the WHRS assessor and described in the WHRS report. Of Mr
Jones’ eight samples, in fact only seven indicated damage to the
subfloor
structure.
- [185] Mr Jones
conceded that he did not undertake any testing of the northern end of the
property, although he accepted that it would
have been possible to do so from
the inside of the house (albeit testing of a more destructive nature). Mr Jones
also confirmed that
he did not personally undertake any testing of the joists at
the far north-western end of the property. He admitted that he was merely
expecting the
timber throughout the entire subfloor structure would need to be replaced. That
was his estimation as to the extent of damage, and
he had not actually tested or
investigated the timber to verify that assumption.
- [186] Under
cross-examination, Mr Jones conceded that from his visual investigations, the
most obvious location of blackened or decayed
timber was in the dining/lounge
area of the property, which was the area already included in his
samples.
- [187] Mr Jones
was reliant on the testing results provided by Beagle Consultancy, a specialist
laboratory to whom the timber samples
were sent for testing, in order to
determine their condition and any potential decay and mould that may be present.
Aside from Mr
Jones’ visual inspections, he did not carry out any
investigations or testing in order to form his own view or confirm the
results
set out in the Beagle report.
- [188] As the
Council points out, there was no evidence from the plaintiff as to what
- – if any
– replacement timber subfloor framing, rather than the pre-existing
subfloor, was damaged.
- [189] The
Council says (and this submission was echoed for O’Hagan) that Ms
Bates, in effect, asks the Court to deem
non-compliance as proof of inadequate
ventilation. No evidence was called by Ms Bates as to how the proposed
ventilation holes and/or
the covered patio vents would have successfully
restricted the build-up of moist air and prevented damage, notwithstanding any
other
issues.
- [190] As I have
previously noted,36 Mr Jones supplemented his evidence during the
course of the trial to address the question of the covered patio vents. Mr Jones
said
in cross-examination that he had always known about the covered patio
vents, and that he attributed the subfloor conditions he had
observed to the
covering of the patio vents. He said that, at the time he prepared his original
evidence, he “believed them
[the covered patio vents] to be very
important.” He thought this belief was reflected in his original brief of
evidence.
36 See above at [54].
- [191] In closing
submissions, Mr Rainey acknowledged that Mr Jones had accepted in his evidence
that there were other sources of moisture
within the subfloor area contributing
to the moisture load within the subfloor space, but said that did not detract
from Mr Jones’
original opinion that the failure to install the proposed
ventilation holes contributed to the damage he observed throughout the
whole of
the subfloor of the house.
Causation
- [192] Causation
is generally split into two separate enquiries: causation in fact and causation
in law.37 Causation in fact is usually
addressed by application of the “but for” test, which asks whether
the plaintiff would have
suffered the injury without the negligent act or
omission of the
defendant.38
- [193] As to
causation in law, in Price Waterhouse v Kwan the Court of Appeal said
there is “a crucial difference between causing a loss and providing the
opportunity for its occurrence.”39 It is not sufficient for a
plaintiff to establish that a defendant’s act or omission provided the
opportunity for the occurrence
of the loss; the act or omission must have had a
real influence on the occurrence of the loss, as a substantial and material
cause,40 and must have made a more than de minimis or trivial
contribution to the occurrence of the loss. As Todd on Torts says, the
“defendant is not liable if he or she has done no more than contribute to
the coincidence of time and space in which
damage could
happen.”41
- [194] I am also
conscious of the Court of Appeal’s observation in Accident Compensation
Corporation v Ambros:42
The generous and unniggardly approach referred to in Harrild
may, however, support the drawing of “robust” inferences
in individual cases. It must,
37 Accident Compensation Corporation v Ambros
[2007] NZCA 304, [2008] 1 NZLR 340 at [24] and [70].
38 Stephen Todd (ed) Todd on Torts (8th ed,
Thomson Reuters, Wellington, 2019) at [20.2.01].
39 Price Waterhouse v Kwan [1999] NZCA 311; [2000] 3 NZLR 39 at [28].
40 Party Bus Co Ltd v New Zealand Transport Agency [2017]
NZHC 413, [2017] 3 NZLR 185 at [72].
41 Todd, above n 38, at
[20.3.01]; citing the example given by Lord Hoffmann in Environment Agency
(formerly National Rivers Authority) v Empress Car Co (Abertillery) Ltd
[1998] UKHL 5; [1999] 2 AC 22 (HL) at 30-31.
42 Accident Compensation Corporation v Ambros, above n 37, at [70].
however, always be borne in mind that there must be sufficient material
pointing to proof of causation on the balance of probabilities
for a court to
draw even a robust inference on causation. Risk of causation does not
suffice.
- [195] I am not
persuaded that there is sufficient material supporting proof of causation, on
the balance of probabilities, connected
to the relevant breaches by the Council
in relation to the proposed ventilation holes. First, there is the question of
the plaintiff’s
own evidence. Mr Jones’ evidence as it developed was
that the condition of the subfloor could be attributed to the covered
patio
vents. While he insisted that was at least implicit in his written statement of
evidence, I did not find that convincing. As
I have noted, no allegation is made
against the Council in relation to the covered patio vents and, as the Council
observes, it was
unconsented works for which the Council cannot be held
responsible.
- [196] The
closing submissions for Ms Bates continued to assert that it was the failure to
install the proposed ventilation holes that
was causative of the damage. What is
decisive though is the evidence: it did not establish the causal link that Mr
Rainey invited
me to draw.
Different course of action
- [197] Ms Bates
faces a further issue in terms of causation: it is not clear what different
course she and Mr Heaney would have taken,
had the Council reported to them, as
part of its inspection function, that the proposed ventilation holes had not
been installed.
- [198] That
situation is in contrast to Birch, where Heron J
said:43
It has to be demonstrated here, that as a result of any failure
to adequately inspect, a warning or some other action would have been
taken and
the plaintiffs would have taken a different course of action from the one
adopted. In this case the focus must be on what
occurred as a result of any
inadequate inspection...
43 Birch v Palmerston North City Council,
above n 29, at 4.
Other causes
- [199] Finally,
as the evidence and submissions for O’Hagan made clear, Ms Bates’
evidence failed to eliminate other causes
of the subfloor ventilation issue. In
particular, it did not exclude the enclosure of the lounge deck and drainage
issues as being
the true causes of the excess subfloor moisture and damage to
the timber.
- [200] I turn
first to the enclosure of the lounge deck. Photographs taken by Mr
Alexander at the time of his inspection
of the property in 2006 show that the
space beneath the deck was enclosed by a trellis. Mr Alexander’s evidence
was that air
could move relatively freely through the trellis and then through
the under-deck accessway, and that it functioned in effect as a
ventilation
opening. Mr Jones confirmed that the trellis provided “absolutely no
restrictions on airflow”, and that the
vast majority of the subfloor
ventilation from 1987 to 2008 was being provided by this
area.
- [201] Mr
Jones’ evidence was that when he visited the property in 2018 the deck was
“very different” from before
the remedial works. However, his
evidence was that enclosing the deck would have “little if any
impact” on ventilation.
He said he arrived at that conclusion through a
“mental exercise in my head”. Mr Jones did not measure the impact of
enclosing the deck on air movement through the under-deck
accessway.
- [202] O’Hagan
submits that the effect of enclosing the deck has not been measured or properly
assessed. It is just as, if not
more, likely that the alleged excess moisture in
the subfloor has been caused by the enclosure of the deck, rather than any
change
to ventilation openings.
- [203] In terms
of the drainage issues, it was apparent from Mr Heaney’s evidence under
cross-examination that he was aware of
the need for drainage around the
perimeter of the house and ventilation under the house in June/August
2006. Mr Heaney’s
evidence was that Mr Alexander had told him that he
should put in drainage around the perimeter of the house, and that he accepted
that it needed to be dealt with. Mr Alexander confirmed that he thought that Mr
Heaney had prior knowledge – possibly from
discussions with the architect
of the house – about issues with drainage and potential damp ground in
patches around the house.
Mr Alexander
prepared a drainage plan. The plan was not among those documents stamped
“superseded”.
- [204] No
evidence was called about whether the proposed drains were constructed. However,
photographs taken in December 2019 show
drains terminating under the lounge deck
and pooling of water. Mr Alexander confirmed in cross-examination that it was
not a part
of his design to have any land drains terminating under the deck. Mr
Jones agreed that it was not part of the building consent plans
to have any
drains terminating under the deck.
Conclusion on negligence claim against the Council
- [205] I
conclude that, although the Council breached its duty in respect of its
inspection obligation and in consequence ought not
to have issued a code
compliance certificate, the plaintiff’s evidence did not establish a
causative link between that breach
and the damage Ms Bates has
suffered.
THE CLAIM AGAINST O’HAGAN
- [206] Ms
Bates’ claim against O’Hagan is framed in negligence and negligent
misstatement, with a further cause of action
alleging misleading and deceptive
conduct under the Fair Trading Act 1986. Counsel for Ms Bates conceded that the
negligent misstatement
and Fair Trading Act claims did not add anything to the
negligence claim, and that if the negligence claim is not made out then the
Fair
Trading Act cause of action will also fail.
- [207] The issues
as between Ms Bates and O’Hagan are:
(a) Did O’Hagan owe a duty of care to Mr Heaney and Ms
Bates? If yes, what was the nature and scope of that duty?
(b) Did O’Hagan breach its duty to Mr Heaney and Ms Bates,
in relation to:
(i) the removal and replacement of the subfloor timbers;
(ii) the issue of the PS4;
(iii) design advice and obtaining Council approval for Detail 12
in July 2007; and
(iv) obtaining the amended building consent?
(c) If O’Hagan did breach its duty, was
O’Hagan’s negligence a material cause of, or contributor to, the
damage
to the house?
(d) If yes, what is the scope of the remedial work required?
Did O’Hagan owe a duty of care to Mr Heaney and Ms
Bates?
Ms
Bates’ position
- [208] Ms Bates
says that O’Hagan owed her and Mr Heaney, as owners of the house, a duty
to exercise reasonable skill and care
in performing their contractual
services.44 Ms Bates acknowledges that the scope of
O’Hagan’s duty of care arises out of their contract. There were four
aspects
to those services:
(a) the removal and replacement of the subfloor timbers;
(b) the issue of the PS4;
(c) design advice and obtaining Council approval for Detail
12 in July 2007; and
(d) obtaining the amended building consent, to change the
cladding from Nu-Lite to Thermaclad EIFS.
- [209] There
was no formal written contract between Ms Bates and Mr Heaney and O’Hagan
for any of the services it provided. However,
it is common ground
that
44 Bowen v Paramount Builders (Hamilton) Ltd
[1977] 1 NZLR 394.
O’Hagan was initially contracted to fulfil the role of the suitably
qualified building surveyor, referred to in the building
consent conditions:
Repairs of Timber affected by Decay
All timber showing any sign of decay is to be removed from the
building and replaced by a treated timber as required by NZS 3602.
Timber within
one metre of the decayed timber and accessible timber is to be treated with an
appropriate preservative such as “Osmose
Framesaver” or
“Metalex”.
This work is to be supervised by a Suitably Qualified
Building Surveyor who must provide a Producer Statement Construction
Review (PS4) to Rodney District Council, before the commencement of the
re-cladding, confirming that the decayed timber was removed and that the
retained timber within 1m of the decayed timber and all accessible timber has
been appropriately treated so that the requirements
of cl B2 of the Building
Code has been met.
- [210] It
is also common ground that O’Hagan was contracted to provide the PS4
required by the conditions of the building consent:
Producer Statement (PS4)
Producer Statement Construction Review (PS4) is to be submitted
by Suitably Qualified Building Surveyor for the observation of the
removal and installation of new timber work and certification that these comply
with the design as approved
by this building consent and the requirement of the
New Zealand Building Code in respect to clauses B1 and B2.
- [211] The
plaintiffs originally pleaded that O’Hagan was engaged to inspect and
monitor the building work to be carried out
under the building consent and
the two amendments to the consent. By the time Mr Rainey presented closing
submissions on behalf
of Ms Bates, it was conceded that O’Hagan had not
been engaged to oversee the remedial work, but rather to supervise the repair
of
timber affected by decay and the treatment of remaining timber as required by
the conditions of the building consent.
- [212] Ms Bates
alleges that O’Hagan was not only required to confirm that the decayed
timber was removed and replaced as required
by the building consent conditions,
but also to confirm that the replacement timber would meet the durability
requirements of cl
B2 of the Building Code. Ms Bates says that assessing
durability under cl B2 requires consideration of cl E2 of the Building Code
because, if the
requirements of E2 are not met, then the building will not meet the durability
requirements of B2.
- [213] Similarly,
Ms Bates alleges that in providing advice about the change to Detail 12 in July
2007, and in seeking amendment to
the consent in relation to cladding in late
2007/08, O’Hagan had a duty to ensure that there was adequate provision
for subfloor
ventilation in the house.
O’Hagan’s
position
- [214] O’Hagan
agrees it owed a duty of care to Mr Heaney and Ms Bates to carry out the tasks
for which it was engaged with reasonable
skill and care and in accordance with
standard practices at the time. The dispute is as to what that duty required of
O’Hagan
in the particular circumstances of this
case.
- [215] O’Hagan
says that the scope of the duty owed to Ms Bates and Mr Heaney was a limited one
and turned on the terms of its
engagement. It did not assume a duty to ensure
that the house as a whole achieved full compliance with the Building Code. Its
obligations
in relation to the PS4 were limited to what was required by the
conditions to the building consent and its instructions from Mr Heaney.
Similarly, the work it undertook in July 2007 in relation to Detail 12, and in
2007/08 in seeking the amended building consent, was
limited to specific and
discrete tasks.
- [216] O’Hagan
points to the fees it received for the services as an indicator of the very
limited role it played; for all four
tasks its fee was a total of $4,125 plus
GST. Ms Bates’ claim against it is for more than $1.5
million.
Discussion
- [217] As with my
analysis of the claim against the Council, I consider below what was required of
O’Hagan, in the context of
each particular alleged breach of
duty.
Did O’Hagan breach its duty to Mr Heaney and Ms
Bates?
- [218] Ms
Bates’ claim against O’Hagan shifted during the course of the
proceeding. Each of the four aspects of the claim,
as they developed, is
discussed below.
The removal and
replacement of the subfloor timbers
- [219] In
relation to the timber replacement, no evidence was called to show that
O’Hagan failed to properly identify and replace
all decayed timber and
treat adjacent timber. By the time of Mr Rainey’s closing submissions for
Ms Bates, there was no direct
claim against O’Hagan in respect of the
installation of the replacement framing timber. The essence of the remaining
allegation
in respect of this aspect of O’Hagan’s services is that,
in carrying out this work, it failed to identify that the subfloor
ventilation
of the house was inadequate and, in particular, that the proposed ventilation
shown on plan A-03 had not been installed.
- [220] O’Hagan
accepts that it owed a duty to conduct the timber inspection with reasonable
skill and care in accordance with
standard practices at the time, but says the
scope of its initial engagement was limited to making sure that decayed timber
was replaced
and adjacent timber treated. The duty it owed to Ms Bates did not
extend beyond that, and certifying the same in the PS4. Nor was
it under a
duty to warn Ms Bates and Mr Heaney.
Discussion
- [221] Whether
O’Hagan assumed a responsibility to take care in the respects alleged by
Ms Bates will depend on the precise nature
of the relationship between
O’Hagan and Ms Bates and Mr Heaney, and the role it assumed in the
remediation works. In Andrews Property Services Ltd v Body Corporate 160361
the Court observed:45
[94] ... whether a duty of the
nature found exists will turn on the circumstances of the individual cases. As
Whata J correctly noted,
whether APS, as a contractor, assumed a responsibility
to take care in respect of specific works depended on the precise nature of
the
relationship with Babbage, as the architect/engineer, and the owners and the
role it assumed in the remediation works.
...
[114] We therefore do not consider that a contractor such as
APS, when undertaking a discrete remediation task, has a duty to undertake
remedial work outside of its contractual responsibility to ensure that the
entirety of a building will be code compliant.
45 Andrews Property Services Ltd v Body Corporate
160361, above n 20.
- [222] The
plaintiff’s instructions to O’Hagan in respect of the timber removal
were recorded in an email from Mr Heaney
on 11 May 2007:
I refer to my discussion with you today. My building consent for
the remedial work at Whitmore Road requires a registered surveyor
like you to
tick off on the timber replacement. You are familiar with the drill imposed by
Rodney.
...
You have told me that you do not need to see any adversely
affected framing before it is removed but you will need to inspect before
replacement timber is installed.
The builder started stripping the cladding on Wednesday and
there is evidence of rot in the south western corner and in the vicinity
of a
handrail fixing on the back deck.
- [223] In a
subsequent email to Mr O’Hagan, Mr Heaney said:
I confirm my discussion with you yesterday. You will attend to
the inspections as discussed in my earlier email and at the end of
the repair
work you will provide the Rodney District Council with a PS4 Producer Statement.
You are to send me a contract but we
have agreed that you should charge me on an
hourly basis at the rate of $150 per hour with a fixed fee of $500 for the PS4
statement
at the end of the job.
- [224] On 2 April
2009 Mr Heaney emailed Mr Pope, attaching a letter from the Council dated 17
February 2009 requesting a PS4 in the
following terms:
Original Producer Statement Construction Review (PS4)
from the building surveyor confirming that the decayed timer (sic) was removed
and that
the retained timber within 1.0m of the decayed timber and all
accessible timber has been appropriately treated so that the requirements
of
clause B2 of the Building Code has been met
- [225] O’Hagan’s
role was therefore to ensure that decayed timber was removed, and that the
retained timber within one
metre of the decayed timber and all accessible timber
had been appropriately treated so that the requirements of cl B2 of the Building
Code had been met. O’Hagan was then to provide a PS4, providing
confirmation within the terms set out at [209] and [210] above.
- [226] Both Mr
O’Hagan and Mr Pope gave evidence that their usual practice was to have
the builder decide when and what timber
is exposed for inspection. If exposed
timber is damaged and near an area of unexposed timber, they would instruct
the
builder to remove further cladding or otherwise expose more timber to be
inspected, to make sure that all damaged timber is replaced.
- [227] Mr
Pope’s evidence was that the usual process of timber inspection is to do a
visual inspection of all exposed timber,
as well as physical testing of the
timber by pushing a screwdriver or chisel (or something similar) into the timber
to check if it
is soft or not. The timber that is soft or visibly decaying is
then marked for replacement using a spray paint. The retained timber
is then
treated with a preservative product that helps prevent damage caused by fungi
and wood-boring insects, like FrameSaver or
Metalex. The preservative is usually
applied by the builder onsite, and normal practice is to apply two coats of the
preservative.
Mr Pope’s evidence was that, in the case of the house,
Metalex was the preservative product applied. A final inspection is
done to
check that all of the damaged timber has been removed and remaining timber has
been treated correctly.
- [228] The
inspections of the timber removal and subsequent replacement were initially
carried out by Mr O’Hagan, and then by
Mr Pope. Mr O’Hagan did the
first inspection of the house on or about 24 May 2007, and Mr Pope did two
inspections on 30 May
2007 and 26 June 2007. When Mr O’Hagan and Mr Pope
were onsite carrying out those instructions, the remediation works were
ongoing.
Mr Pope’s evidence was that he carried out his inspections and testing in
accordance with his usual practice. He observed,
in particular, that there was
timber damage in and around the decking area.
- [229] On the
face of Mr Heaney’s instructions to O’Hagan in relation to the
timber removal, there is nothing to suggest
that O’Hagan’s role was
to go beyond what was stated. The question then is whether the further
obligation alleged was
explicit or implicit in the requirement to issue the
PS4.
The issue of the PS4
- [230] Ms Bates
says that O’Hagan was negligent in its issue of the PS4. The PS4 was
issued in respect of: “Replacement
timber + certification of existing
timber”. Ms Bates says that O’Hagan was thereby certifying that the
replacement timber
and certification of the existing timber had been completed
in accordance with the plans
and specifications that had been approved by the Council in the building
consent. As a prudent building surveyor, O’Hagan could
not and should not
have issued the PS4 unless it had confirmed the installation of the proposed
ventilation holes shown in the Alexander
& Co plans. Had it carried out
proper inspections, it would have readily observed that the proposed ventilation
holes had not
been installed. Ms Bates says it was negligent in not doing
so.
- [231] However,
Ms Bates also conceded (at least implicitly) that the PS4 which O’Hagan
was required to produce was limited to
the terms of the building
consent:
... the observation of the removal and installation of new
timber work and certification that these comply with the design as approved
by
this building consent and the requirement of the New Zealand Building Code in
respect to clauses B1 and B2.
- [232] O’Hagan
says it made no representations about subfloor moisture by way of its
PS4.
Discussion
- [233] Again, as
in Andrews Property Services Ltd, the focus must be on what it was that
O’Hagan was asked to do and what in fact it certified (by reference to the
words used
in the PS4).46
- [234] Mr Pope,
on behalf of O’Hagan, filled out a PS4 on or about 30 April 2009, which Mr
O’Hagan signed. Mr O’Hagan’s
evidence was that he and Mr Pope
discussed the PS4 and reviewed the photographs that both of them had taken of
the timber framing,
before Mr O’Hagan signed the
PS4.
- [235] O’Hagan
issued the PS4 on 30 April 2009. Mr O’Hagan’s evidence was that he
noted the requirement for the PS4
in his diary on 6 July 2007, but he could not
recall why it was not issued until April 2009. For present purposes, nothing
turns
on the delay.
46 Andrews Property Services Ltd v Body Corporate
160361, above n 20.
- [236] The PS4
was issued in respect of “Replacement timber + certification of existing
timber.” The PS4 recorded that
O’Hagan had been engaged by Mr Heaney
to provide “Technical + Consultancy” services in respect of
the requirements of B2 of the Building Code for the “building work”
described on “Drawings
consented by [the Council] and drawn by Alexander
& Co and the specification and other documents according to which the
building
is proposed to be constructed.”
- [237] Ms Bates
did not call any evidence as to general practice and requisite standards on the
part of tradespeople in O’Hagan’s
role, in terms of the removal of
the timber or the issue of the PS4. Mr Jordan did give evidence for Ms Bates
that, in his opinion,
a prudent Council would not place any reliance on the PS4
when considering compliance with the requirement for subfloor ventilation.
But
his evidence did not extend directly to O’Hagan’s obligation. In any
event, nor is there a pleading in relation to
the Council’s reliance on
the PS4.
- [238] Ms
Bates’ remaining case against O’Hagan appears to be that
O’Hagan could not have expressed an opinion about
the durability of the
replaced and treated timber without being satisfied, not only as to the
durability requirement in cl B2, but
also the functional requirement of cl E2 in
relation to external moisture: “Buildings must be constructed to provide
adequate
resistance to penetration by, and the accumulation of, moisture from
the outside.” In failing to identify that the proposed
ventilation holes
specified on plan A-03 had not been installed, Ms Bates says O’Hagan
failed in its performance of these contracted
services; O’Hagan ought not
to have issued the PS4 without confirming the installation of the proposed
ventilation holes specified
in plan A-03.
- [239] I do not
accept that assertion. It is not consistent with the relevant passage in the
conditions to the building consent which
required the PS4. I accept that the
only reasonable interpretation of the PS4 is as confirmation of what the Council
had asked for
in its 17 February 2009 letter – that is,
that:
... the decayed timer (sic) was removed and that the retained
timber within 1.0m of the decayed timber and all accessible timber has
been
appropriately treated so that the requirements of clause B2 of the Building Code
has (sic) been met
- [240] That is
consistent with the conditions of the building consent and with Mr
Jordan’s evidence that:
The producer statement refers only to replacement and
certification of existing timber and does not include reference to sub-floor
ventilation. A prudent council would not place any reliance on this document
when considering compliance with the requirement for
sub-floor ventilation.
- [241] I accept
that, at the point when O’Hagan was carrying out the timber inspections
(May and June 2007), there was no obvious
reason for it to fear that the
building consent would be departed from. I do not consider it would be
reasonable to hold that O’Hagan
had a duty to satisfy itself that the
subfloor ventilation provided for in plan A-03 was being or had been
implemented, or to warn
that it was not, before certifying as to the durability
of the timber that had been retained and treated. While the PS4 was not in
fact
issued until 30 April 2009, Mr O’Hagan’s evidence was that was an
oversight on O’Hagan’s part and O’Hagan
did not undertake a
further site visit at that point.
Design advice and obtaining Council
approval for Detail 12 in July 2007
- [242] The third
aspect of O’Hagan’s involvement in the remedial work occurred in
July 2007 when O’Hagan provided
advice and obtained approval for Detail
12. As noted above,47 this related to the termination point of the
cladding, and during the course of this work being completed it appears some
existing
patio vents were covered.
- [243] As I have
already found, O’Hagan’s 16 July 2007 letter did not specify the
covering of the patio vents,48 and the plaintiff’s own evidence
was that the covering of the existing patio vents was not necessitated by the
amendment to
Scribble’s Detail 12. Therefore this argument must also fail
because, as with the removal and replacement of the timber and
the issue of the
PS4, any actions (presumably by Brackenridge) in covering the patio vents were
outside the scope of O’Hagan’s
work (a discrete design task, rather
than ensuring building work undertaken by others would be code-compliant) and
the duty it owed
to Ms Bates and Mr Heaney. I also note
that
47 See above at [112]-[114].
48 See above at [120].
Ms Bates did not plead a discrete duty on O’Hagan to warn; nor would the
facts have supported such a duty.
- [244] For
completeness, I note Ms Bates faced a further significant difficulty with the
claim against O’Hagan in relation to
this aspect of the remedial works:
she accepts that, even if O’Hagan was responsible for the covering over of
the existing
patio vents, that was not causative of the damage to the subfloor
(notwithstanding the evidence from Mr Jones on Ms Bates’
behalf that it
was causative).
Obtaining the amended building
consent (ABA-62145B)
- [245] The final
allegation in relation to O’Hagan related to the amended building consent
issued in 2008, to change the cladding
on the house from Nu-Lite to Thermaclad
EIFS. The initial claim was that the Scribble drawings submitted with the
application made
inadequate provision for subfloor ventilation. Ms Bates’
position by the close of the trial was that the amended building consent
did not
involve removing the proposed ventilation holes provided for in plan A-03. Ms
Bates advances her negligence claim against
O’Hagan in respect of the
amendment only if I conclude that the application for the amended building
consent did involve removing
the proposed ventilation holes provided by
A-03.
- [246] Given I
have found the proposed ventilation holes remained a part of the planned works
after the issuing of the amended building
consent (despite plan A-03 being
stamped “superseded),49 this claim against O’Hagan falls
away.
Was O’Hagan’s negligence a material cause of, or
contributor to, the damage to the house?
- [247] Ms
Bates says that as a result of O’Hagan’s failure to identify the
lack of subfloor ventilation in the as-built
construction, the house was built
with inadequate subfloor ventilation. That negligence is a substantial and
material cause of the
damage suffered by Ms Bates.
49 See above at [154].
- [248] Although I
have found O’Hagan did not breach its duty to Ms Bates, for completeness I
make some observations about causation
in relation to the claim against
O’Hagan.
- [249] First, as
in the analysis of whether O’Hagan breached its duty, I again emphasise
the relevance of the scope of the duty.
BNZ v Guardian Trust illustrates
an approach to the cause in law test by reference to the scope of the duty owed
by the defendant.50 The Court of Appeal cited the House of
Lords’ decision in South Australia Asset Management Corporation v
York Montague Ltd, where it said “the real question in this case is
the kind of loss in respect of which the duty was owed.”51 It
is important to identify the purpose of the relevant cause of action, and the
nature and scope of the defendant’s obligation
in the particular
circumstances.
- [250] Ultimately,
Ms Bates’ surviving allegations against O’Hagan come down to the
same thing: in the course of undertaking
its contractual duties –
identifying and removing decayed timber and treating adjacent timber; issuing
the PS4; preparing and
seeking consent for the amendment to Detail 12; seeking
amendment to the consent in relation to the change of cladding – it
ought
to have identified that the proposed ventilation holes provided for in plan A-03
had not been installed, but failed to do so.
I have found that clearly fell
outside the scope of O’Hagan’s engagement.
- [251] Even if a
broader duty existed, there was no evidence before me as to whether, at the time
of its timber inspections, O’Hagan
would in fact have been able to
identify that the ventilation holes provided for in A-03 had not been
installed.
- [252] Second, Ms
Bates faced one specific challenge in relation to O’Hagan: her primary
arguments in relation to the July 2007
work around Detail 12 related to the
covered patio vents, which she conceded were not causative of the damage she has
suffered. More
generally, Ms Bates would have faced similar issues to those she
faced in the claim against the Council, in establishing the cause
of the damage
to the requisite standard, including a failure to exclude other causes of the
damage to the subfloor.
50 Bank of New Zealand v New Zealand Guardian
Trust Co Ltd [1999] 1 NZLR 664 at 683.
51 South Australia Asset Management Corporation v York Montague
Ltd [1996] UKHL 10; [1997] AC 191 (HL) at 212.
- [253] Ms
Bates’ case is inconsistent as to what was ultimately causative of the
damage to the subfloor: her principal expert
witness said it was the covering
over of the patio vents; plaintiff’s counsel said it was not, and was,
rather, the failure
to install the proposed ventilation
holes.
Conclusion on negligence claim against O’Hagan
- [254] I
conclude O’Hagan did not breach its duty to Ms Bates, and, in any event,
the evidence for the plaintiff would not have
established a causative link
between any breach and the damage alleged.
Affirmative defences
- [255] In
light of my findings that Ms Bates’ claims against both the Council and
O’Hagan have failed, it has not been
necessary for me to go on and
consider the affirmative defences raised by each of the Council and
O’Hagan against Ms Bates.52
- [256] For the
same reason, I have not considered the cross-claims, which fall away as a
consequence of my findings in relation to
Ms Bates’ claims against each of
the Council and O’Hagan.
Third party claim
- [257] O’Hagan
has a remaining third party claim against Brackenridge. Similarly, that claim
falls away as a consequence of my
finding that O’Hagan has no liability to
Ms Bates.
Scope of remedial work
- [258] It
has also been unnecessary for me to go on and consider the scope of any remedial
work to the house.
52 See above at [9].
Costs
- [259] I
invite the parties to agree costs. If they are unable to do so, the defendants
are to file submissions of no more than ten
pages within 15 working days of the
date of this judgment; and the plaintiff is to file any submissions in response,
of no more than
ten pages, within a further 15 working
days.
Gwyn J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2021/2558.html