NZLII Home | Databases | WorldLII | Search | Feedback

High Court of New Zealand Decisions

You are here:  NZLII >> Databases >> High Court of New Zealand Decisions >> 2021 >> [2021] NZHC 2558

Database Search | Name Search | Recent Decisions | Noteup | LawCite | Download | Help

Bates v Auckland Council [2021] NZHC 2558 (29 September 2021)

Last Updated: 1 December 2021


IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2017-404-2670
[2021] NZHC 2558
BETWEEN
DENESE ROSEMARY BATES
Plaintiff
AND
AUCKLAND COUNCIL
First Defendant
O’HAGAN BUILDING CONSULTANTS LIMITED
Second Defendant
Hearing:
9–13 March 2020, 16–19 March 2020, 23 March 2020, 21–22
September 2020
Counsel:
T Rainey and J Heaney for the Plaintiff
S C Price, J K Wilson and R Nolan for the First Defendant A L Holloway and M A Karlsen for the Second Defendant
Judgment:
29 September 2021


JUDGMENT OF GWYN J



This judgment was delivered by me on 29 September 2021 at 12.00 pm pursuant to Rule 11.5 of the High Court Rules.

Registrar/ Deputy Registrar Date:






Solicitors:

Cameron Flemming Associates Limited, Auckland MinterEllisonRuddWatts, Auckland

Wotton Kearney, Auckland


BATES v AUCKLAND COUNCIL [2021] NZHC 2558 [29 September 2021]

TABLE OF CONTENTS

Introduction [1]
The parties [4]
The claims [7]
Background [12]
Discovery the house is a leaky building [12]
Consent process for the remedial works [18]
The remedial works [25]
Discovery of current issues [37]
The evidence at trial [40]
Scene view [57]

THE CLAIM AGAINST THE COUNCIL [58]

Did the Council owe a duty of care to Mr Heaney and Ms Bates? [62]
Ms Bates’ position [67]
The Council’s position [70]
Discussion [80]

Did the Council breach its duty to Mr Heaney and Ms Bates? [86]

Particular 2 – calculations or other verification of subfloor compliance with

E2/AS1 [87]

Discussion [92]

Particular 1 – polythene sheet to be laid on subfloor [97] Discussion [106]

Particular 3 – calculations or other verification for O’Hagan amendment in July 2007 [111]

Discussion [120]

Particular 5 – vapour barrier [125]

Particular 4 – failure to identify that there was inadequate provision for subfloor ventilation provided for in drawings for the building consent and the amended building consent [127]

Discussion [130]

Particular 6 – alleged failure to observe during inspections that the proposed ventilation holes had not been installed [132]

Discussion [142]
“Superseded” [148]

Proposed ventilation holes not installed [156] Particular 7 – alleged failure to observe during inspections that there was inadequate provision for subfloor ventilation [166]

The issue of the Code of Compliance Certificate [169] Discussion [171]

Was the Council’s negligence a material cause of, or contributor to, the damage to the house? [172]

Discussion [177]

Defect/damage [177]
Causation [192]
Different course of action [197]
Other causes [199]

Conclusion on negligence claim against the Council [205]

THE CLAIM AGAINST O’HAGAN [206]

Did O’Hagan owe a duty of care to Mr Heaney and Ms Bates? [208]

Ms Bates’ position [208]
O’Hagan’s position [214]
Discussion [217]

Did O’Hagan breach its duty to Mr Heaney and Ms Bates? [218] The removal and replacement of the subfloor timbers [219] Discussion [221]
The issue of the PS4 [230]

Discussion [233]

Design advice and obtaining Council approval for Detail 12 in July 2007 [242] Obtaining the amended building consent (ABA-62145B) [245] Was O’Hagan’s negligence a material cause of, or contributor to, the damage to the house? [247]

Conclusion on negligence claim against O’Hagan [254]

Affirmative defences [255]
Third party claim [257]

Scope of remedial work [258]

Costs [259]

Introduction

The parties

Scribble Limited (Scribble), a provider of architectural services; Brackenridge Builders Limited (Brackenridge), the builders who initially carried out the remedial work; and Mr Colin Green, the builder who carried out the remainder of the remedial work. As matters have progressed, some of the issues have been resolved or settled. As at the commencement of the hearing, third party claims brought by both the Council and O’Hagan against Mr Green remained alive, and Mr Bates appeared as counsel for Mr Green. However, those claims were subsequently settled, and I granted Mr Bates leave to withdraw early in the proceeding.

The claims

Background

Discovery the house is a leaky building

cladding, particularly around the windows, which had caused significant damage to the timber frame of the house.

... Other than the limited area of wet and partially decayed timber due to the deck issue [arising from the deck being directly fixed to the wall], I observed no decay. The earth was not saturated, the sub-floor framing did not cause me sufficient concern to take extensive moisture metre readings, although I may have taken a few measurements. I did not observe mould or dampness on the sub-floor timber.

I observed no direct flow of water into the subfloor area.

Sub-floor ventilation present would not have complied with the Acceptable Solutions for complying with the Building Code or relevant standards at the time of my inspection but was adequate to prevent significant deterioration up to that point. The subfloor complied with the performance requirements [in] the Building Code because there had been no detriment in performance but the situation was not satisfactory and needed attention to avoid future deterioration.

Consent process for the remedial works

(a) The addition of 15 ventilation holes of 125 mm diameter around the perimeter of the house (the proposed ventilation holes), shown on plan A-03. It was Mr Alexander’s view that an “engineer”, by which he meant a person overseeing works, needed to have oversight of the best place to locate the proposed ventilation holes. The need for an “engineer” was noted on plan A-03.

(b) Subsoil drainage around the perimeter of the house.

(c) A gap under the timber decking at the south eastern end of the house to promote airflow.

(d) The laying of a polythene sheet on the ground under the house. This detail was not included on the plans, but was recorded in the scope of work document.

carry out the work. Mr Heaney and Ms Bates did not have a written contract with Brackenridge.

The detail in question is shown 17 times in the plans. It is of considerable concern that the builder had not read the plans, thought he would do it the way he thought was right and then asked [the architect] rather than us about what the plans intended. I am concerned that Brackenridge will not have an understanding of this type of work and will not follow the plans.

The remedial works

1 Under the now-repealed Building Act 1991, a decision to issue a code compliance certificate turned on whether the territorial authority was satisfied, on reasonable grounds, as to compliance.

accordance with certain technical specifications, before the commencement of the re-cladding. Mr Heaney and Ms Bates contracted O’Hagan to carry out this work. Their instructions to O’Hagan were recorded in a series of emails, on 11 May 2007.




The 1991 Act contemplated that such a decision might be on the basis of, among other things, producer statements, which were defined as meaning a statement supplied by or on behalf of an applicant for, or the holder of, a building consent that would be, or had been, carried out in accordance with certain technical specifications. The 2004 Act does not provide for the general use of producer statements, but there is nothing in the Act to prevent territorial authorities from relying on them and they continue to be regularly considered as part of the building consent process.

The Rodney District Council are satisfied, on reasonable grounds, that –

Discovery of current issues

The evidence at trial

(a) Five or six of 13 patio vents that had existed prior to the remedial works had been covered over during torch on membrane work around the tiled areas during the remedial work (the covered patio vents).

(b) The 15 proposed ventilation holes in plan A-03 of the Alexander & Co plans were never installed.

(c) The polythene sheet suggested by Alexander & Co was not installed.

(d) Part of an underdeck accessway that had functioned in effect as a ventilation opening prior to the remedial works was enclosed in the course of the remedial work.

doesn’t seem to be a simple oversight to not do them.” He said it looked to him as though it was a conscious decision not to implement the plans.

2 Building Code clauses have acceptable solutions, which are documents that set out methods of complying with the Building Code. Anyone who complies exactly with the methods described in

The subfloor space of all suspended timber floors shall be ventilated. This requirement shall be met by providing openings in the foundation wall, at the rate of no less than 3500 mm2 of net open area for every m2 of floor area. The openings shall be as near as possible to the underside of plates and bearers.

Ventilation openings shall be constructed by either one of the following methods, or by a combination of both methods:

(a) Create continuous gaps, of at least 20 mm wide, between baseboards around the entire perimeter of the building, and/or

(b) Install perimeter wall ventilators to give sufficient net open area. Ventilators shall be spaced regularly, commencing 750 mm from wall corners and at intervals no greater than 1.8 m to all sides of the building.

Where the subfloor space cannot be adequately ventilated in accordance with Paragraph 10.2.6, the ground under a suspended timber floor shall be entirely covered with a vapour barrier...

Even with a vapour barrier, ventilation openings shall:

(a) Have a net open area of no less than 700 mm2 for every m2 of floor area, and

(b) Be located to provide cross-flow air to all parts of the subfloor space.



the acceptable solution for a Building Code clause is deemed to comply with the Building Code. However, as discussed below at [92], it is not mandatory to follow an acceptable solution. Alternative methods of construction that comply with the relevant Building Code requirements become alternative solutions. Acceptable Solution E2/AS1 is the main acceptable solution for meeting the requirements of E2 of the Building Code. (BRANZ, Building Code Compliance).

Scene view

THE CLAIM AGAINST THE COUNCIL



3 NZS 3604 was an acceptable solution for Building Code cl B1. It was the predecessor to E2/AS1.

was pleaded, noting where the nature of the claim changed during trial, but the inconsistencies in the plaintiff’s case has made that difficult.

(a) ensure it issued a building consent for building work that complied with the Building Code;

(b) ensure the building work would be undertaken so as to comply with the Building Code;

(c) ensure any building work undertaken would be in accordance with the building consent plans and specifications; and

(d) issue a Code of Compliance Certificate only if it was satisfied on reasonable grounds that the building work undertaken was in compliance with the Building Code and/or the building consent.

(a) Did the Council owe a duty of care to Mr Heaney and Ms Bates? If so, what was the nature and scope of that duty?

(b) Did the Council breach its duty to Mr Heaney and Ms Bates, in relation to the grant of the building consent, inspection of the work, and the issue of a Code of Compliance Certificate? The particulars of the alleged breach of duty are:

(i) First, the Council failed to consider and require details of the polythene sheet to be laid on the subfloor beneath the dwelling

including membrane thickness and junctions with foundations before granting building consent.

(ii) Second, the Council failed to request and/or receive calculations or other verification to confirm whether the Alexander & Co proposed subfloor ventilation plan (if fully installed) would comply with the ventilation and air flow requirements set out in E2/AS1 and NZS 3604.

(iii) Third, the Council failed to request and/or receive calculations or other verification that the amended plan submitted by O’Hagan on 16 July 2007 would comply with the Building Code.

(iv) Fourth, the Council failed to identify that there was inadequate provision shown on drawings for subfloor ventilation in both the original Alexander & Co building consent ABA-62145 and the Scribble drawings with the amended building consent.

(v) Fifth, the Council failed to specify a vapour barrier as part of the building consent.

(vi) Sixth, the Council failed to observe during its inspections that the proposed ventilation holes provided for in the consented plans had not been installed.

(vii) Seventh, the Council failed to observe during its inspections that there was inadequate provision for subfloor ventilation.

(viii) Eighth, the Council issued the code compliance certificate when it did not have reasonable grounds to be satisfied that the building work complied with the requirements of the building consent and/or the Building Code.

(c) If the Council did breach its duty, was the Council’s negligence a material cause of, or contributor to, the damage to the house?

(d) If yes, what is the scope of the remedial work required?

Did the Council owe a duty of care to Mr Heaney and Ms Bates?

The obligation of the Council can be no higher than expressed in statute itself; namely, to be satisfied on all reasonable grounds that a building consent should issue; to take reasonable steps in carrying out inspections and to be satisfied on reasonable grounds that code compliance should be certified.

[142] The Council’s common law duty of care is informed by legislative policy. For present purposes, I do not consider that the obligations under the Building Act 2004 are materially different from the obligations under the 1991 Act:8




4 Invercargill City Council v Hamlin [1994] 3 NZLR 513 (PC).

5 Body Corporate No 207624 v North Shore City Council [2012] NZSC 83, [2013] 2 NZLR 297 [Spencer on Byron] at [71] and [194].

6 Body Corporate 188529 v North Shore City Council [2008] NZHC 2300; [2008] 3 NZLR 479 (HC) [Sunset Terraces] at [220]-[221].

7 Body Corporate 160361 v BC 2004 Ltd [2015] NZHC 1803.

8 Spencer on Byron, above n 5, at [217].

(a) The purpose of the Act remains the same, namely to bring about safe and healthy buildings.9

(b) The role of building consent authorities is to issue building consents, inspect building work for which it has granted consent, issue notices to fix and issue Code Compliance Certificates.10

(c) All building work must comply with the building code to the extent required by the Act, whether or not a building consent is required in respect of building work.11

(d) A person must not carry out any building work (including construction, alteration, demolition or removal of a building) except in accordance with a building consent.12

(e) Before granting a building consent, the building consent authority must be satisfied on reasonable grounds that the provisions of the building code would be met if the building work were properly completed in accordance with the plans and specifications that accompanied the application for consent.13

(f) Every building consent is subject to the condition that the building consent authority is entitled during normal working hours to inspect building work and inspection means taking all reasonable steps to ensure that the building work is being carried out in accordance with the building consent.14

(g) The owner of the building must apply for and the building consent authority must issue a Code Compliance Certificate within 20 working days15 if it is satisfied on reasonable grounds that the building work complies with the building consent.16

(h) The building consent authority may issue a notice to fix to a person carrying out or supervising the building work if there are reasonable grounds they are contravening or failing to comply with the Act.17



9 At [171]; see the Building Act 2004, s 3 and the Building Act 1991, s 6(1)(a).

10 Building Act 2004, s 12.

11 Section 16.

12 Section 40.

13 Section 49.

14 Sections 90(2) and (3); and s 222.

15 Section 93(1)(a), but note the building consent authority may request further information – s 93(4).

16 Section 94(1)(a).

17 Section 163.

Ms Bates’ position

(a) the installation of the proposed ventilation holes was for the purpose of improving the subfloor ventilation;

(b) some of the decayed and damaged timber to be removed was in the subfloor; and

(c) some of the cladding and damaged framing to be removed was within the subfloor.

The Council’s position

(a) the proposed (new) work would be compliant with the Building Code, if done properly; and

(b) the existing building’s level of compliance with the Building Code will not worsen.

18 Sections 17, 49 and 112.

19 For example, fire egress and disability access (s 112) and if the building is dangerous or unsanitary (s 122).

(a) The building consent issued on 26 January 2007 (ABA-62145): the application included the following description of the building work – “Re-cladding and bathroom extension to existing residential house. Works include new paving around perimeter of the house and lowering of site levels.” The consent itself described the building work as “Re-cladding & bathroom extension to existing house”.

(b) The first amendment to the building consent, issued on 17 April 2007 (ABA-62145A): the application to amend the consent described the work as “change plaster coat from STO to Nulite cladding”. The consent replicated the description of work from the original consent – “Re-cladding & bathroom extension to existing house”.

(c) The amended building consent issued in August 2008 (ABA-62145B): the application describes the amendment as “Change of cladding from Nu-Lite to Plaster Systems Thermaclad EIFS System”.

Repairs of Timber affected by Decay

All timber showing any sign of decay is to be removed from the building and replaced by treated timber as required by NZS 3602. Timber within one metre of the decayed timber and accessible timber is to be treated with an appropriate preservative such as “Osmose Framesaver” or “Metalex”.

Discussion

112 Alterations to existing buildings

(1) A building consent authority must not grant a building consent for the alteration of an existing building, or part of an existing building, unless the building consent authority is satisfied that, after the alteration,—

(a) the building will comply, as nearly as is reasonably practicable, with the provisions of the building code that relate to—

(i) means of escape from fire; and

(ii) access and facilities for persons with disabilities (if this is a requirement in terms of section 118); and

(b) the building will,—

(i) if it complied with the other provisions of the building code immediately before the building work began, continue to comply with those provisions; or

(ii) if it did not comply with the other provisions of the building code immediately before the building work began, continue to comply at least to the same extent as it did then comply.

(2) Despite subsection (1), a territorial authority may, by written notice to the owner of a building, allow the alteration of an existing building, or part of an existing building, without the building complying with provisions of the building code specified by the territorial authority if the territorial authority is satisfied that,—

(a) if the building were required to comply with the relevant provisions of the building code, the alteration would not take place; and

(b) the alteration will result in improvements to attributes of the building that relate to—

(i) means of escape from fire; or

(ii) access and facilities for persons with disabilities; and

(c) the improvements referred to in paragraph (b) outweigh any detriment that is likely to arise as a result of the building not complying with the relevant provisions of the building code.

(3) This section is subject to section 133AT.

[The Building Act] only requires the aspects of the house that are being repaired to be brought up to current compliance levels. Elements that are not repaired may be left at the same level of compliance as they were originally.




20 Wheeldon v Body Corporate 342525 [2015] NZHC 884, (2015) 16 NZCPR 829 at [159]- [160];

cited in Andrews Property Services Ltd v Body Corporate 160361 [2016] NZCA 644, [2017] 2 NZLR 772 at [112].

21 Fitzgerald v IAG New Zealand Ltd [2018] NZHC 3447 at [50].

Building consent applicants need to ensure their building consent application includes all the required information to demonstrate:


22 MBIE Determination 2012-023; MBIE Determination 2014-058; MBIE Determination 2018-061.

Did the Council breach its duty to Mr Heaney and Ms Bates?

Particular 2 – calculations or other verification of subfloor compliance with E2/AS1

Failed to request and/or receive calculations or other verification to confirm whether the Alexander proposed subfloor ventilation plan (if fully installed) would comply with the ventilation and air flow requirements set out in E2/AS1 and NZS3604.




23 Building Act 2004, s 49.

works would not have reduced that compliance. Finally, there is no evidence from Ms Bates of any industry-wide practice of providing such calculations.

Discussion
Co proposed subfloor ventilation plan (if fully installed) would comply with the ventilation and airflow requirements set out in E2/AS1 and NZS 3604. There was no evidence before the Court that this was an industry-wide, or even a common, practice. Mr Alexander said that it was never his practice.

Particular 1 – polythene sheet to be laid on subfloor

Failed to consider and require details of the polythene sheet to be laid on the subfloor ground beneath the dwelling including membrane thickness and junctions with foundations before granting building consent.

Sub-floor ventilation of the existing house is insufficient mainly due to the lack of cross ventilation and the high ground levels around significant areas of the house. We have improved the sub-floor ventilation by providing vents in all possible areas and therefore providing cross ventilation that is currently absent. As an additional precaution we are willing to specify a polythene sheet to be laid on the sub-floor ground beneath the house to mitigate any concern with inadequate sub-floor ventilation. Locations of sub-floor ventilation are shown on page A03.

... If the original ventilation provisions are considered in combination with the proposed new 15 openings in the Alexander design, I assess that the ventilation requirements of E2/AS1 and NZS3604 would likely have been met.

If a vapour barrier had been specified, even without the original openings being known of or taken into consideration, the Alexander proposed new 15 ventilation holes would likely have complied with the requirements of E2/AS1.


Discussion
builders, did not lay the polythene sheet under the house during the course of the remedial works (it appears they did so subsequently, in February 2019).

Particular 3 – calculations or other verification for O’Hagan amendment in July 2007

Failed to request and/or receive calculations or other verification that the amended plan submitted by O’Hagan Building Consultants Limited (16 July 2007) would comply with the Building Code.

Mr Pope and Mr Borich (an employee of Brackenridge) then met with the Council on site on 6 July 2007 to discuss the solution.

We have replaced detail 26, page A36 with a new chimney flashing detail provided by Scribble Ltd. We have also replaced detail 12 page 24 with Scribble Ltd details as per attached.

The crossflow ventilation as proposed on original drawings should now be deleted as the torchon membrane will be covering this area. Crossflow ventilation should be created from the north and south end of the dwelling and from under timber deck as per original drawings A03 proposed ventilation.


Discussion
However, the second sentence refers to creating cross-flow ventilation “as per original drawings A-03 proposed ventilation”, which suggests otherwise.

Particular 5 – vapour barrier

Failed to specify a vapour barrier as part of the building consent.

Particular 4 – failure to identify that there was inadequate provision for subfloor ventilation provided for in drawings for the building consent and the amended building consent

Failed to identify that there was inadequate provision shown on drawings for subfloor ventilation in both the original Alexander building consent ABA-62145 and the amended Scribble drawings with amended building consent ABA62145B.


Discussion

(a) It is premised on E2/AS1 being mandatory, which it is not.

(b) Mr Alexander’s evidence for Ms Bates was that the subfloor area of the existing building had performed in accordance with the Building Code, notwithstanding it was constructed other than in accordance with E2/AS1.

(c) As I have already found, the Council’s obligations are different in respect of the proposed (new) building work and the existing building. The obligation under ss 17 and 49 of the Building Act 2004 is to consider whether the proposed building work detailed in the building consent application complies with the Building Code; the proposed work, as an alteration, does not need to bring the whole building into compliance with the Building Code. The Council need only consider whether the building as a whole will continue to comply with the other provisions of the Building Code to at least the same extent as prior to the alteration. There was no evidence that anything in the Alexander & Co plans, if implemented correctly, would have worsened the performance of the existing building.

(d) Finally, I note that this aspect of the claim is inconsistent with Mr Jones’ amended evidence during the trial that the subfloor conditions can be attributed to the covered patio vents (which were not subject to any building consent), not anything in the consented plans or amended consented plans.

Particular 6 – alleged failure to observe during inspections that the proposed ventilation holes had not been installed

Failed to observe that the ventilation holes provided in the consented plans had not been installed during its inspections.

design provided for the installation of vents through the cladding in those areas of the house where the concrete footing did not come as high as the floor level of the house, so some of the subfloor outer wall was formed by cladding. In those areas, the design was to install vents through the cladding to provide further ventilation. In some places, there would be a hole in the masonry for the ventilation. In other places, there would be a hole in the subfloor timber framing and the plaster system. That was because the ground levels changed around the house. The important thing was that the hole was clearly above ground level and would not allow water to flow through it. Mr Alexander said that his intention was that the 125 mm ventilation openings would have a grill or a grate installed over them, but one that effectively maintained the same ventilation area and did not materially reduce the available opening of 125 mm diameter.
  1. Bathroom foundations – 14/5/07
  1. Bond beam – 18/5/07
  1. Concrete slab en-suite – 12/6/07
  1. Preline, stage 1 – 26/6/07
  1. Wet area membrane, ground floor over concrete – 24/9/08
  1. Drainage, including comment for deck clearance northern side of house

– 3/11/08

g. Final – 11/2/09

Discussion

90 Inspections by building consent authorities

(1) Every building consent is subject to the condition that agents authorised by the building consent authority for the purposes of this section are entitled, at all times during normal working hours or while building work is being done, to inspect—

(a) land on which building work is being or is proposed to be carried out; and

(b) building work that has been or is being carried out on or off the building site; and

(c) any building.

(2) The provisions (if any) that are endorsed on a building consent in relation to inspection during the carrying out of building work must be taken to include the provisions of this section.

(3) In this section, inspection means the taking of all reasonable steps to ensure that building work is being carried out in accordance with a building consent.

It is clear from s 90 that the express purpose of an inspection is to ensure that the building work being inspected complies with the building consent. That ensures that, at each stage of the building process, the building consent has been implemented, allowing a code compliance certificate to issue when the work is completed.


24 Reeves v Lakes Environmental Ltd [2014] NZHC 2760 at [64].

expert evidence other than the general evidence of Mr Jordan; for example from a building inspector, as to exactly when and how the absence of the proposed ventilation holes should have been detected. There was no evidence about what the Council reported to Ms Bates and Mr Heaney following its inspections; it appears that it did not report to them that the proposed ventilation holes had been installed.

(a) The “superseded” stamp which was applied to plan A-03, amongst other documents, on 8 May 2008.

(b) The fact that the proposed ventilation holes were not in fact installed and, as I have noted, as at March 2008 were no longer part of the scope of works between Ms Bates and Mr Heaney, and their builder Mr Green. Further, at that point it was, in practical terms, too late to install them.


“Superseded”
Scribble designs relating to the amended building consent did not change the design intent of his plan regarding subfloor ventilation. It was, he said, “effectively the same as my plan ... except ... they’ve changed the cladding.”

The persons ordinarily expected to rely on specifications are qualified builders and building inspectors, not ordinary members of the public. The proper test is therefore, in my view, what would the ordinary builder or inspector make of the revised stamp?

25 Body Corporate 160361 v BC 2004 Ltd [2015] NZHC 1803 at [157]- [158].

26 Opua Ferries Ltd v Fullers Bay of Islands Ltd [2003] UKPC 19, [2003] 3 NZLR 740 at [20].

27 Andrews Property Services Ltd v Body Corporate 16036, above n 20.

28 Body Corporate 160361 v BC 2004 Ltd, above n 25, at [157].

handwritten reference to the amended building consent. Although, as I have noted, there was no reference on plan A-03 to the new Scribble plans, in my view the building inspector would have looked at the amended building consent application and related documents to understand how and in what way the specification at A-03 was affected. That exercise would have revealed that the Alexander & Co Detail 15 was replaced with the Scribble detail that shows the same proposed ventilation holes as on plan A-03.

Proposed ventilation holes not installed
evidence at trial was that in fact he would not have looked at the plans once received. In addition, Brackenridge had on two occasions provided Mr Heaney with a programme which referred to the installation of the proposed ventilation holes and sought direction from him, but Mr Heaney’s evidence was that he had not read those documents.

29 Birch v Palmerston North City Council HC Wellington CP 116/92, 22 July 1998.

30 At 3.

31 At 3.

32 At 6.

was an upgrade to the existing building subfloor (Mr Alexander’s evidence was that prior to the remedial work the subfloor complied with the performance requirements of the Building Code). It was open to Ms Bates and Mr Heaney, as building owners, to reduce the scope of the consented work.

Particular 7 – alleged failure to observe during inspections that there was inadequate provision for subfloor ventilation

Failed to observe during its inspections that there was inadequate provision for subfloor ventilation.

would have given consideration to and identified a lack of subfloor ventilation” at the inspections listed above at [136]. The Council says that is inadequate to establish that the Council was in breach.

The issue of the Code of Compliance Certificate


Discussion

33 See above at [130].

Was the Council’s negligence a material cause of, or contributor to, the damage to the house?

Discussion


Defect/damage

... evidence must be weighed according to the proof which it was within the power of one side to have produced and in the power of the other to have contradicted.

Inadequate provision for prevention of dampness within the sub-floor space, including a lack of ventilation resulting in undue dampness to building elements, including decay to structural timber framing.

(Failure to achieve B2.3.1, E2.3.2)



34 Sunset Terraces, above n 6, at [58].

35 Ministry of Education v H Construction North Island Ltd [2018] NZHC 871 at [61]- [63].

All experts agree that there is damage to the southern end sub-floor timbers caused by moisture as a result, at least in part to inadequate ventilation. ...

The experts agree there are various contributing moisture sources as per their individual briefs.

The sub-floor area following the remedial re-cladding work in 2008 has not been constructed in a manner that prevents the accumulation of moisture in the sub-floor resulting in damage to the timber floor and wall framing, as a result of inadequate provision for sub-floor ventilation. The damage as described by Alan Bolderson in the WHRS report and by me later in this brief, can be expected to occur when there is inadequate provision for sub-floor ventilation in suspended timber floors.

timber throughout the entire subfloor structure would need to be replaced. That was his estimation as to the extent of damage, and he had not actually tested or investigated the timber to verify that assumption.



36 See above at [54].


Causation

The generous and unniggardly approach referred to in Harrild may, however, support the drawing of “robust” inferences in individual cases. It must,


37 Accident Compensation Corporation v Ambros [2007] NZCA 304, [2008] 1 NZLR 340 at [24] and [70].

38 Stephen Todd (ed) Todd on Torts (8th ed, Thomson Reuters, Wellington, 2019) at [20.2.01].

39 Price Waterhouse v Kwan [1999] NZCA 311; [2000] 3 NZLR 39 at [28].

40 Party Bus Co Ltd v New Zealand Transport Agency [2017] NZHC 413, [2017] 3 NZLR 185 at [72].

41 Todd, above n 38, at [20.3.01]; citing the example given by Lord Hoffmann in Environment Agency (formerly National Rivers Authority) v Empress Car Co (Abertillery) Ltd [1998] UKHL 5; [1999] 2 AC 22 (HL) at 30-31.

42 Accident Compensation Corporation v Ambros, above n 37, at [70].

however, always be borne in mind that there must be sufficient material pointing to proof of causation on the balance of probabilities for a court to draw even a robust inference on causation. Risk of causation does not suffice.


Different course of action

It has to be demonstrated here, that as a result of any failure to adequately inspect, a warning or some other action would have been taken and the plaintiffs would have taken a different course of action from the one adopted. In this case the focus must be on what occurred as a result of any inadequate inspection...








43 Birch v Palmerston North City Council, above n 29, at 4.

Other causes
prepared a drainage plan. The plan was not among those documents stamped “superseded”.

Conclusion on negligence claim against the Council

THE CLAIM AGAINST O’HAGAN

(a) Did O’Hagan owe a duty of care to Mr Heaney and Ms Bates? If yes, what was the nature and scope of that duty?

(b) Did O’Hagan breach its duty to Mr Heaney and Ms Bates, in relation to:

(i) the removal and replacement of the subfloor timbers;

(ii) the issue of the PS4;

(iii) design advice and obtaining Council approval for Detail 12 in July 2007; and

(iv) obtaining the amended building consent?

(c) If O’Hagan did breach its duty, was O’Hagan’s negligence a material cause of, or contributor to, the damage to the house?

(d) If yes, what is the scope of the remedial work required?

Did O’Hagan owe a duty of care to Mr Heaney and Ms Bates?

Ms Bates’ position

(a) the removal and replacement of the subfloor timbers;

(b) the issue of the PS4;

(c) design advice and obtaining Council approval for Detail 12 in July 2007; and

(d) obtaining the amended building consent, to change the cladding from Nu-Lite to Thermaclad EIFS.




44 Bowen v Paramount Builders (Hamilton) Ltd [1977] 1 NZLR 394.

O’Hagan was initially contracted to fulfil the role of the suitably qualified building surveyor, referred to in the building consent conditions:

Repairs of Timber affected by Decay

All timber showing any sign of decay is to be removed from the building and replaced by a treated timber as required by NZS 3602. Timber within one metre of the decayed timber and accessible timber is to be treated with an appropriate preservative such as “Osmose Framesaver” or “Metalex”.

This work is to be supervised by a Suitably Qualified Building Surveyor who must provide a Producer Statement Construction Review (PS4) to Rodney District Council, before the commencement of the re-cladding, confirming that the decayed timber was removed and that the retained timber within 1m of the decayed timber and all accessible timber has been appropriately treated so that the requirements of cl B2 of the Building Code has been met.

Producer Statement (PS4)

Producer Statement Construction Review (PS4) is to be submitted by Suitably Qualified Building Surveyor for the observation of the removal and installation of new timber work and certification that these comply with the design as approved by this building consent and the requirement of the New Zealand Building Code in respect to clauses B1 and B2.

requirements of E2 are not met, then the building will not meet the durability requirements of B2.

O’Hagan’s position

Discussion

Did O’Hagan breach its duty to Mr Heaney and Ms Bates?

The removal and replacement of the subfloor timbers


Discussion

[94] ... whether a duty of the nature found exists will turn on the circumstances of the individual cases. As Whata J correctly noted, whether APS, as a contractor, assumed a responsibility to take care in respect of specific works depended on the precise nature of the relationship with Babbage, as the architect/engineer, and the owners and the role it assumed in the remediation works.

...

[114] We therefore do not consider that a contractor such as APS, when undertaking a discrete remediation task, has a duty to undertake remedial work outside of its contractual responsibility to ensure that the entirety of a building will be code compliant.



45 Andrews Property Services Ltd v Body Corporate 160361, above n 20.

I refer to my discussion with you today. My building consent for the remedial work at Whitmore Road requires a registered surveyor like you to tick off on the timber replacement. You are familiar with the drill imposed by Rodney.

...

You have told me that you do not need to see any adversely affected framing before it is removed but you will need to inspect before replacement timber is installed.

The builder started stripping the cladding on Wednesday and there is evidence of rot in the south western corner and in the vicinity of a handrail fixing on the back deck.

I confirm my discussion with you yesterday. You will attend to the inspections as discussed in my earlier email and at the end of the repair work you will provide the Rodney District Council with a PS4 Producer Statement. You are to send me a contract but we have agreed that you should charge me on an hourly basis at the rate of $150 per hour with a fixed fee of $500 for the PS4 statement at the end of the job.

Original Producer Statement Construction Review (PS4) from the building surveyor confirming that the decayed timer (sic) was removed and that the retained timber within 1.0m of the decayed timber and all accessible timber has been appropriately treated so that the requirements of clause B2 of the Building Code has been met

builder to remove further cladding or otherwise expose more timber to be inspected, to make sure that all damaged timber is replaced.

The issue of the PS4

and specifications that had been approved by the Council in the building consent. As a prudent building surveyor, O’Hagan could not and should not have issued the PS4 unless it had confirmed the installation of the proposed ventilation holes shown in the Alexander & Co plans. Had it carried out proper inspections, it would have readily observed that the proposed ventilation holes had not been installed. Ms Bates says it was negligent in not doing so.

... the observation of the removal and installation of new timber work and certification that these comply with the design as approved by this building consent and the requirement of the New Zealand Building Code in respect to clauses B1 and B2.


Discussion




46 Andrews Property Services Ltd v Body Corporate 160361, above n 20.

... the decayed timer (sic) was removed and that the retained timber within 1.0m of the decayed timber and all accessible timber has been appropriately treated so that the requirements of clause B2 of the Building Code has (sic) been met

The producer statement refers only to replacement and certification of existing timber and does not include reference to sub-floor ventilation. A prudent council would not place any reliance on this document when considering compliance with the requirement for sub-floor ventilation.

Design advice and obtaining Council approval for Detail 12 in July 2007




47 See above at [112]-[114].

48 See above at [120].

Ms Bates did not plead a discrete duty on O’Hagan to warn; nor would the facts have supported such a duty.

Obtaining the amended building consent (ABA-62145B)

Was O’Hagan’s negligence a material cause of, or contributor to, the damage to the house?





49 See above at [154].



50 Bank of New Zealand v New Zealand Guardian Trust Co Ltd [1999] 1 NZLR 664 at 683.

51 South Australia Asset Management Corporation v York Montague Ltd [1996] UKHL 10; [1997] AC 191 (HL) at 212.

Conclusion on negligence claim against O’Hagan

Affirmative defences

Third party claim

Scope of remedial work








52 See above at [9].

Costs









Gwyn J


NZLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2021/2558.html