You are here:
NZLII >>
Databases >>
High Court of New Zealand Decisions >>
2021 >>
[2021] NZHC 3234
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Linehan v Thames Coromandel District Council [2021] NZHC 3234 (29 November 2021)
Last Updated: 20 December 2021
|
IN THE HIGH COURT OF NEW ZEALAND HAMILTON REGISTRY
I TE KŌTI MATUA O AOTEAROA KIRIKIRIROA ROHE
|
|
|
|
BETWEEN
|
BRIAN JOSEPH LINEHAN, SHANNON JAMES WALSH and
ROSS DOUGLAS BLAIR as trustees of the Eliza Trust
Plaintiffs
|
|
AND
|
THAMES COROMANDEL DISTRICT COUNCIL
First Defendant
BERNARD BARBER LIMITED
Second Defendant
BERNARD BARBER
Third Defendant
MARK TARRANT HOSKINS
Fourth Defendant
.../intituling cont over
|
|
Hearing:
|
13–24 July 2020, 1 December 2020, 9 February 2021.
Further submissions filed 18 October and 1 November 2021.
|
|
Counsel:
|
VA Whitfield, KI Bond and LHH Hunt for Plaintiffs DJ Neutze and C Robertson
for Defendant
|
|
Judgment:
|
29 November 2021
|
JUDGMENT OF HINTON J
This judgment was
delivered by me on Monday, 29 November 2021 at 4 pm
pursuant to Rule 11.5 High Court Rules.
Registrar/Deputy Registrar
Solicitors/Counsel:
Brookfields Lawyers, Auckland.
Braun Bond & Lomas Ltd, Hamilton. VA Whitfield, Cambridge.
LINEHAN v THAMES COROMANDEL DISTRICT COUNCIL [2021] NZHC 3234
[29 November 2021]
CITY CERTIFYING CONSULTANTS LIMITED
Fifth Defendant
MURRAY SIEVERS
Sixth Defendant
MARK GORTON
Seventh Defendant
STRAIGHT EDGE EXTERIOR PLASTERING LIMITED
Eighth Defendant
PENINSULA ROOFING LIMITED
Ninth Defendant
PAULA MAREE HARVEY
Tenth Defendant
- [1] This
proceeding concerns a dwelling on the beachfront at 15 Wharekaho Crescent,
Simpsons Beach, which has many features typical
of a leaky building. The
property was purchased by trustees of the Hilldon Trust, a trust
settled by Dr Brian Linehan
in March 2003, with the knowledge it was a leaky
building. The property was sold in 2013 to the plaintiffs who are trustees of
the
Eliza Trust, also settled by Dr Linehan (the
Trustees).1
- [2] Dr Linehan
carried out extensive remedial work on the house in 2011 and on the upstairs
balconies (only) in 2016, in an effort
to address the leaks. Some of the 2011
works and all of the 2016 works were themselves inadequate or defective.
Weathertightness
problems and risks remain. Dr Linehan also carried out more
minor unconsented work on the upstairs balconies in
2014/2015.
- [3] This
proceeding is not about the original construction of the building. It relates
solely to the 2011 and 2016 remedial works.
The Trustees say that the first
defendant, the Thames Coromandel District Council (the Council) was negligent in
issuing building
consents, inspecting, and issuing code compliance certificates
in respect of both the 2011 and 2016 works. They note many defects,
including
defects in cladding, roofing, parapets and balconies, and seek compensation for
all or substantially all such defects.
Importantly, the Trustees claim that the
Council is liable for the full cost of repairs even if its only breach was in
respect of
the balconies.
- [4] The Trustees
claim the cost of repairs, stigma, and associated damages in a total sum of
$1,559,369. As the 2016 repairs failed
completely, they also claim damages of
$197,528 for the wasted cost of those repairs. Interest is claimed on all
sums.
- [5] The Council
acknowledges it was negligent in 2011 in certifying balcony tiling that had
been, contrary to the building consent
and the Building Code, affixed directly
to the membrane below. The tiles should have been installed on a suspended jack
system where
they are placed above and separate to the membrane. The Council
also accepts it was negligent again in 2016, this time in issuing
a building
consent for
1 No mention was made of the other plaintiff
trustees. I refer to the Trustees and Dr Linehan interchangeably.
direct-fixed tiling. It denies any other breaches and denies that it has any
liability other than it accepts liability for the cost
of targeted repairs for
the 2016 balcony breach. The Council assessed that cost at $548,571, or at most
$581,310. The Council says
any award of damages should be reduced by at least 50
per cent for contributory negligence.
- [6] The Trustees
also claimed in negligence against their builder, Bernard Barber, and a number
of others who had been involved in
relation to the works on the property. I was
advised that the claims against all defendants other than the Council had been
discontinued.
No cross-notices were served.2
Background
- [7] The
dwelling was built in 1997. It has many features typical of the houses built in
that period that became known as “leaky
homes”. These included a
wedding cake design, flat roofs, curved walls, and monolithic
cladding.
- [8] As noted,
the trustees of the Hilldon Trust purchased the property in March 2003 and it
was transferred to the trustees of the
Eliza Trust in March 2013. The Council
takes no issue over the change in ownership.
- [9] Dr Linehan
knew before the Hilldon Trust purchased the property that the building was
leaky. Prior to the purchase he had obtained
an expert opinion on the water
ingress of the building. Surprisingly, Dr Linehan did not retain that report.
The Trustees submit
variously that he no longer had the report in 2010 when he
was engaging Mr Barber, and that he did still have it but did not make
it
available to Mr Barber (nor presumably his insurers) because he considered its
contents obvious. In any event, at least since
2010 Dr Linehan has not retained
a copy. According to Dr Linehan the report showed the building had problems with
water ingress into
the walls, particularly around the front stairs and in
respect of the eastern ocean-facing wall, it was based on a non-invasive
inspection
and the leaks at that point were minor. Dr Linehan says now that the
report did not contain anything that would influence the way
the work was
carried out but there is an obvious difficulty in categorically
stating
2 As counsel continued to use the full intituling, I
have done likewise.
now the contents of a report prepared in 2003, that Dr Linehan plainly had not
read since 2010 or earlier, and that he did not bother
to retain. The
investigator may for example have not only reported on actual leaks but also on
leak risks generally including risks
inherent in fixed tiles.3 A
purchaser who obtains such a report prior to purchase would want to know
everything they could about the house so that, with their
eyes open, they were
best able to negotiate that purchase.
- [10] In any
event it is clear that not only was Dr Linehan aware of actual leaks, but he was
also aware of the general weathertightness
risks inherent in the design and
construction of the house and that it was only a matter of time before major
works would be required.
He said he knew he would need to address the issues but
that once possession of the property was taken, there was little internal
evidence of weathertightness issues such that he decided not to act on the 2003
report. Also, he decided the leaking noted in the
2003 report might have been
caused by a screwdriver hole in a wall and a birds’ nest in the guttering
(both of which he fixed).
- [11] According
to Dr Linehan, weathertightness issues became apparent in 2010, with water
collecting in the ceiling of the garage
and bunk room. He resolved then to take
steps.
- [12] For reasons
which are not clear, given his awareness that the house had weathertightness
issues at the time of purchase, Dr Linehan
contacted his insurance company,
Medical Assurance Society. The insurer arranged for an assessor and Mr
Barber, who was a local
builder, to look at the house. Dr Linehan’s
evidence is that Mr Barber held himself out to be an expert in repairing leaky
buildings and he was referred to him by the insurance company as having
appropriate expertise. He says he therefore did not engage
a building surveyor
to advise on the scope of remedial works.
- [13] As recorded
in a letter dated 23 June 2010, Dr Linehan engaged Mr Barber4 to
identify all the leaking problems in the house, to repair or cause to be
repaired those
3 The problems with direct-fixed tiles were
well-known at the time of the 2003 report. See brief of evidence of Andre Vernon
Laurent
dated 23 October 2019 at [27] and [28].
4 Trading as Bernard Barber Ltd but referred to throughout as Mr
Barber.
leaks, to obtain all necessary consents and to ensure all legal requirements
were met. Dr Linehan’s oral evidence is that Mr
Barber was engaged to
re-clad the house, install new double-glazed aluminium windows, extend an
existing deck, and remove high- risk
(in terms of promoting water ingress)
features of the dwelling related to its curved walls. He and Mr Barber also
decided to replace
all the tiles; including on the decks, and to change
staircases and the entrance foyer. The engagement did not refer to any repairs
of the roofs of the dwelling.
- [14] There was
no formal written agreement between Dr Linehan and Mr Barber for the 2011 works,
nor any scope of works beyond that
stated above. Rather, the engagement was
primarily undertaken pursuant to a verbal agreement, with certain points
recorded in the
23 June 2010 letter.
- [15] Mr Barber
engaged Ms Simpson of Simpson Design Services to draw up plans for Dr
Linehan’s purposes and for the purposes
of obtaining the required building
consent. It appears that Ms Simpson was an architectural designer, not a
registered architect.
Dr Linehan says he had only minor involvement in the
design process. He appears to have been happy to trust Mr Barber with most
aspects of the design. Dr Linehan described Ms Simpson’s job as
minimal and as being managed by Mr Barber.
- [16] Neither Ms
Simpson nor anyone other than Mr Barber appears to have been engaged to identify
all the leaky problems, to determine
the manner in which the house should be
repaired, or to assess the likely cost. Dr Linehan acknowledges that he probably
met Ms Simpson
but says he could not recall her nor discussing plans with
her.
- [17] No project
manager or architect was engaged to supervise the work. Mr Barber was to have,
as recorded in the letter of 23 June
2010, “overall responsibility for the
integrity of work” and for ensuring all work was “carried out in a
proper
tradesman- like manner conforming, where appropriate, to the relevant
standards”. Correspondingly, Mr Barber was engaged on
a full-contract
basis with all sub- contractors retained and paid for by his company.
- [18] In
mid-2010, Mr Barber commenced work without a building consent and apparently
without having received plans from Ms Simpson.
As a result of a complaint from a
resident in the area, the Council visited the site on 7 July 2010. The
Council’s file note
of the same date makes it clear that no building
consent had then been applied for. Mr Barber advised the Council that Ms Simpson
was “doing the plans”. Mr Barber received a stop-work notice as a
result of the investigation by the Council inspector.
Dr Linehan must have been
aware of this.5
- [19] Mr Barber
applied for a building consent after the stop-work notice issued. The
application estimated a cost of works of $100,000,
a sum well below 10 per cent
of the final cost of the works (about $1.4 million) and possibly below the cost
of works already carried
out. On 20 September 2010, the Council granted a
building consent for the re-cladding of the building, replacement of aluminium
windows
with double- glazed joinery, adding to the existing deck and removing
certain high-risk quarter- round features (the last item apparently
relating to
the removal of the dwelling’s high- risk curved wall). The consent
required a raised platform for tiled decking
on the upstairs balconies, that
having been specified by Ms Simpson.
- [20] During the
works there was a discussion between Mr Barber and Dr Linehan regarding the
tiling on the upstairs balcony where Dr
Linehan expressed a preference for the
tiling to be fixed rather than on a raised platform. Construction proceeded that
way, contrary
to the Trustees’ plans and the consent. Dr Linehan
acknowledges he was told by Mr Barber that suspended deck tiling was the
“preferred method”, and “for some councils” that was
compulsory. He says “I don’t recall the
exact words but my
impression, in retrospect, was that it was a recommendation rather than a
requirement of [this] Council”.
Dr Linehan says he personally was not
aware of the exact building requirements in relation to the tiling issue and
relied on Mr Barber
to advise him of such matters. I presume this means Dr
Linehan did not take steps to look at the plans or the building consent or
to
make any inquiries. Dr Linehan’s evidence in chief was that his preference
related to aesthetics and “the other option”
was very expensive. He
subsequently said this decision related more to
aesthetics.
5 The scope of pre-consent works is not clear but on
30 September 2010, Mr Barber sent invoice No 3 to Dr Linehan for
$120,901.45.
Given that he had undertaken to stop works until 20
September, this (and possibly earlier invoices) were presumably at least
in part
for work done prior to the date of the building consent.
- [21] The works
were carried out from mid-2010 (that is before the consent), until December
2011.6 Dr Linehan advises that the total cost was about $1.4
million.
- [22] The Council
carried out inspections and eventually, on 19 December 2011, issued a code
compliance certificate in respect of the
2011 works under s 95 of the Building
Act 2004 (the Act). It seems the Council did not notice that the tiled decking
was non-compliant with the conditions of the consent.
- [23] After the
2011 works were completed, Dr Linehan became concerned about the visual
appearance of the tiled decking on the upstairs
balconies. By around Christmas
2014 the tiles had begun to lift. By December 2015, Dr Linehan noted water
“pouring” into
the lounge from the balcony
above.
- [24] In a manner
that the Council submits to have been a materially intervening act, Dr Linehan
arranged for some further repairs
to be carried out in 2014/2015. He again
retained Mr Barber to undertake such repairs. The exact timing and extent of
these interim
works is unclear. Dr Linehan considers them to have been minor.
Those works appear to have involved at least two stages. No building
consent was
obtained, and the Council did not know of them. Nor were those works mentioned
to Council subsequently, including when
seeking building consent for the 2016
works.
- [25] The only
evidence of what was actually done in 2014/2015 was from Dr Linehan
who says the tiles were lifted and re-laid
by a different tiler, Mr Barber
having blamed the previous tiler for the defects and been unable to get him to
return. As Dr Linehan
disclaimed any detailed knowledge of any of the other
works, it is reasonable to conclude he would have had little knowledge of any
detail of these interim works.
- [26] The Council
considers the interim works and the works carried out in 2016 to have been such
that they removed all available evidence
as to damage resulting from the 2011
non-compliance and that these interim repairs may even be the cause of some of
the alleged defects
associated with the upstairs
balconies.
6 I refer generally to the 2010/2011 works as being
2011 because that is how counsel describe them.
- [27] In early
2016 Dr Linehan engaged Mr Barber again to address the issues with the tiles. Ms
Simpson was not retained. One consequence
of this is that Ms Simpson’s
knowledge about the need for suspended deck tiling was lost. (As noted, she had
specified suspended
tiling.) Paula Harvey was retained in her stead to draw up
plans for obtaining the required building consent.
- [28] The
Trustees say that a Mr Brunton was retained to provide necessary expert advice.
The Council submits that Mr Brunton was engaged
primarily in relation to a
dispute with the original tiler. Mr Brunton did not give evidence. There is
insufficient evidence to conclude
that Mr Brunton contributed materially to
investigations, design solutions or supervision.
- [29] On 13 May
2016 the Council granted Mr Barber’s application for a building consent
for works relating only to the balcony
tiling issue, being replacement of the
tiling and related waterproofing work. The plans as prepared by Ms Harvey
provided for fixed
tiles on the balconies, possibly reflecting the then reality
of the balconies. It is accepted by the Council that the consented works
were
not in compliance with the Building Code. The work was carried out and the
Council issued a code compliance certificate on 6
September 2016. The building
consent had noted a “project value” of
$49,000. The actual cost was $197,528, significantly less than the 2011 works,
but the scope of the works was much more limited.
The experts
- [30] Expert
testimony was called by the Trustees and the Council.
- [31] The
Trustees called five experts. The Council called four.
The Trustees’ experts
- [32] Andre
Laurent. Mr Laurent is a licensed architectural designer and a director of
Creative Space Architectural Design Ltd. Creative Space has specialised
in the
remedial design and documentation of leaky buildings since 2004. Mr Laurent
describes their role as finding “buildable
and cost-effective solutions to
any recognised damage area and the cause of damage as identified by a registered
building surveyor
or weathertightness expert”. Mr Laurent says it is his policy wherever
possible to eliminate risk rather than manage it as
many of the issues they find
are actually designed to fail. His evidence extended to the plans and
specifications submitted with
the 2016 building consent and his opinion as to
the remedial works required to rectify the defects with the house. Mr Laurent
does
not refer to any previous experience as an expert witness.
- [33] Paul
Probett. Mr Probett is a forensic building specialist with 14 years’
experience in forensic building pathology and 47 years’ experience
in the
building industry. His evidence related to the defects in the 2011 works, the
defects in the 2016 works, the appropriate remediation
scope, and
betterment.
- [34] Stephen
Flay. Mr Flay is a building surveyor with over 39 years’ experience in
the building industry, including as a Council employee and
contractor. His
evidence related to the Council’s responsibilities, including whether it
should have identified defects and
whether the Council should have done more
than it did in 2011 in relation to the roofing.
- [35] James
White. Mr White is a registered quantity surveyor with almost 20
years’ experience. His evidence related to the costs of carrying out
repairs under various scopes.
- [36] Chris
Coakley. Mr Coakley is a registered valuer with extensive experience in the
valuation of residential and rural properties. His evidence related
to the loss
in value associated with stigma from the failed 2011 and 2016
repairs.
The Council’s experts
- [37] Simon
Paykel. Mr Paykel is a registered building surveyor with extensive
experience of Council practices and 25 years’ experience in the building
industry. He has acted in a considerable number of weathertightness claims,
representing clients at mediations, arbitrations and
adjudications and giving
evidence as an expert witness in the High Court, District Court and Weathertight
Homes Tribunal. Such engagements
have been on behalf of homeowners, bodies
corporate, tradespeople, developers,
insurers and councils in both claimant and defendant capacities. His testimony
was extensive. It included testimony as to Council
liability and as to remedial
solutions.
- [38] Craig
Turner. Mr Turner is a building consultant with over 40 years’
experience in the building industry. He has extensive experience in the
repair
of dwellings damaged by excessive moisture ingress. Initially, he had been
retained as an expert by the then ninth defendant.
- [39] Jake
Woolgar. Mr Woolgar is a chartered building surveyor with 20 years’
experience in the building industry in New Zealand and overseas.
Mr Woolgar had
viewed the house in February 2016 prior to the Trustees’ 2016 attempted
remediation of the tiling issue. His
evidence was in relation to what he then
saw.
- [40] Greg
Cutfield. Mr Cutfield is a registered quantity surveyor. He has over 35
years’ experience in the construction industry. His evidence related
to
the cost of carrying out repairs under varying scopes.
My observations on the expert testimony
- [41] I consider
the expertise of all these witnesses to have been appropriately established.
Although counsel on each side sought
to question the objectivity or the
expertise of the other’s experts, I considered their evidence to be of the
standard that
the Court requires.
- [42] The
Trustees particularly challenged Mr Paykel’s qualifications to advance
what is referred to as targeted remediation
scopes. They say he is not a
licensed designer, and he is not an expert in design matters. While Mr Paykel is
not a licensed designer,
I consider, based on his qualifications, broad
expertise and extensive experience, he is sufficiently qualified as an expert in
all
the evidence he gave. I found Mr Paykel to be technically competent,
measured and very practical. While accepting that he could not
progress a
building consent without using a licensed designer, I consider his evidence as
to remediation measures to be well within
his expertise.
Summary of the Trustees’ case
- [43] The
Trustees produced a list of defects with the building and, at least initially,
alleged that all such defects arose from failings
on the part of the Council in
2011, or at least that the Council was liable to rectify them. There was, as I
note has occurred in
other cases,7 generally some confusion between a
defect and a breach, one almost being assumed to amount to the other. The
Trustees’ closing
submissions began with a discussion of the appropriate
scope of remedial works and subsequently turned to consideration of the alleged
breaches.
- [44] There was a
substantial level of consensus between experts on the absence of Council
negligence in relation to some matters.
Cladding is the most significant such
example. Sealing issues are another.
- [45] The list of
defects with brief comments on breach includes the
following:
(a) Balconies. This is the tiling issue already noted, where the Council
accepts breach.
(b) Cladding. The key issue is that the plaster applied in 2011 was too
thick. The experts agreed the Council is not liable, which in context is
an
agreement that the Council had breached no duty in relation to the cladding.
(c) Z Flashings. The 2010 building consent contemplated that Z flashings
would be used behind horizontal joints. They were not so used. Sealant had
been
used instead. The Trustees say the Council should have identified this on
inspection.
(d) Seal issues. There were a large number of defects listed in the
schedule. I will not detail them because the experts agreed that the Council had
not breached any duties in relation to them.
7 See for example Minister of Education v H
Construction North Island Ltd [2018] NZHC 871 and
Bates v Auckland Council [2021] NZHC 2558.
(e) Parapets. The Trustees claim that the paint on the upper parapet
bands is porous and inadequately coated, the saddle flashings have failed and
are allowing moisture entry. They say the required layer of ProtectoWrap EIFS
tape was not installed over the top of the parapets
and that there is plaster
shearing in parapet caps. The Trustees allege the Council should have identified
the missing ProtectoWrap.
(f) Roof. The defects schedule notes inter alia a lack of falls (and some
ponding) on the first-floor roof and on other roofs. It also notes
waterproofing
issues with the membrane on the first-floor roof. The Trustees claim that the
Council is liable for these defects because
the 2010 building consent process
contemplated work would be done to the roofing in a manner that required the
Council to insist
upon full compliance with the requirements of the Building
Code (especially as to falls, ponding and membranes). They also claim
that, even
if this was not the case, the Council should have noticed the extent of works
actually carried out in 2011 and then required
such full compliance. They say
that as a consequence the Council should have required the roof to be replaced.
(The Trustees accept
that this would mean the roofing should have been addressed
by them in 2010 or at least that they should not get a “free roof”
from the Council. To adjust for this, they say it is appropriate to assess the
cost of such works as at 2010/2011 applying CPI adjustments
retrospectively
against current costings and to include a credit for that, plus interest,
against the currently assessed costs.)
(g) Tanking. The Trustees allege that, in installing a new retaining
wall, an excavation in the 2011 works cut through a pre-existing membrane
in
order to tie the walls together and that the return wall should not have been
connected as that results in moisture migrating
into the house. They say the
Council failed to pick this up on inspection.
- [46] The
Trustees’ final position as to the extent of the Council’s actual
2011 breaches was not always easy to determine,
their focus being on the defects
rather than
the nature of any breach, and also on their argument that even with regard to
the one accepted balcony tiling breach, the same quantum
of damages followed.
The Trustees’ closing submissions strongly suggest that claims of direct
breach regarding cladding and
sealing defects are not maintained but, in the
absence of clear confirmation of that I make formal rulings below regarding each
of
the listed “defects”.
- [47] In terms of
the 2016 works, which were limited to an attempt at repair of the balcony, the
Trustees say the Council breached
its duty of care because it issued a building
consent that contemplated directly fixed balcony tiles. (The Trustees also
pleaded
that the Council breached its duties in relation to inspection and
certification of the tiling but that would not change the extent
of the
Council’s liability.
- [48] Other than
in their very recent submissions, the Trustees did not specifically address the
question of causation. They say that
the consequence of a breach by the Council
is that it is liable for the cost of repairs; namely the amount required to
rectify the
defects. They also say, as noted, that in this case the Council is
liable for the full repair cost even if its only breach is the
accepted breach
regarding the tiling. The Trustees acknowledge that the measure of damages can
alternatively be diminution in value,
but say that would have to have been
pleaded by the Council and in any event the Council accepted the “cost of
repairs”
approach.
- [49] It is
important to note that in their additional submissions filed on 18 October 2021,
the Trustees make it clear their claim
for costs of repair is not based
on the Council’s negligence in 2011 regarding the balcony. They say rather
that “the costs of repair now claimed
arise out of the Council’s
negligence with the 2016 works (being balcony-related only) and the non-balcony
related defects
from the 2011 works”.
- [50] The
Trustees submit that the cost of repairs should be assessed having regard to
what they refer to as Concept Plan repairs.
These Concept Plan repairs are the
repairs that one of the Trustees’ experts, Mr Laurent, says are necessary.
They involve
not only new decking but also a new roof, new cladding and a
substantial re-design of the house. Mr Laurent advises that because
the house
has a very high level of weathertightness risk, a “specific design”
is called for to remove risk factors and
incorporate protective design elements
where possible. The proposed works are
clearly extensive. The photographic and pictorial evidence is such that there is
no obvious similarity between the existing house
and that proposed by Mr
Laurent. Mr Laurent rejected any lesser scope of works. He was particularly
critical of the repairs proposed
by the Council to which I will refer soon.
- [51] The
Trustees accept that there is some betterment in the works they propose,
presumably because the Concept Plan repairs would
completely re-fashion the
house, but they say betterment has been allowed for in the claim they have made.
They appear to consider
betterment arises only to the extent they are better off
than they would be if the house complied with the Building Code. I consider
this
analysis to be incorrect but ultimately I do not need to consider betterment
issues as such.
- [52] In
addition, the Trustees claim the sum of $197,528.85 being the wasted costs they
incurred in the 2016 work. They say the 2016
work was a reasonable mitigating
action flowing from the 2011 breach and therefore they should be entitled to
recover the full wasted
cost.
- [53] The
Trustees deny any contributory negligence, primarily on the basis that there has
been no “negligent” action on
their part that was causative of the
loss.
- [54] Finally,
the Trustees submit that the onus is on the Council to establish betterment or
contributory negligence or to propose
that damages might be assessed on the
basis of diminution in value as opposed to the cost of
repairs.
Summary of the Council’s case
- [55] The
Council accepts that it breached its duties in 2011 regarding certifying of the
balcony tiles. The 2010 plans, as approved,
correctly showed the tiles as being
on a raised platform, not fixed, but the tiles were fixed by Mr Barber/his
tilers and the Council
failed to pick that up. The Council denies any breach in
terms of inspection in respect of the 2011 works.
- [56] As to
whether the Council also breached any duties in relation to other defects, it
says:
(a) Cladding. Experts agreed that the Council has no responsibility for
this defect or at least did not breach any duty in relation to cladding
per
se.
(b) Z Flashings. The Council accepts that the building consent stipulated
that Z flashings must be used and that they were not. It denies negligence.
The
basis for this is not clear but it can only be that the Council could not
reasonably have been expected to pick this up. However,
it says that, if the
non-use had been noted, it would have resulted in a minor variation permitting
the use of the sealant instead
of the Z flashings. The Trustees’ expert Mr
Flay agreed with this. The Council also says that the non-use has not been shown
to have caused any damage and that the Trustees’ expert Mr Probett agreed
it had not caused significant damage.
(c) Sealant. Again, the experts agreed that the Council had breached no
obligation in relation to this defect.
(d) Parapets. The Council denies breach in relation to allegedly
defective works on the parapets. Mr Flay and Mr Paykel agreed that the Council
had not breached any obligation in this regard. Subsequently, Mr Flay altered
his position based on further investigations by Mr
Probett, which the Council
says did not justify the change in position. Further, the Council claims that Mr
Probett’s testing
was supportive of its claim that there was no evidence
of damage.
(e) Roof. The Council says the building application did not seek any
consent as to roofing on the upper-level roof or the level two low-pitch
roof
surfaces (nor was any carried out). There was no reason for the Council to
address those roofs. There was some relatively minor
work on upstands on the
first-floor roof and replacement of a small section of membrane, but the plans
recorded that the existing
roof membrane was to be retained. The Council says
the Trustees elected not to carry out any roof works other than what amounted
to
maintenance or minor works as necessitated by other works for which consent was
granted.
In those circumstances the Council was not under any obligation to bring the
roof into full compliance with the Building Code. The
Council also denies that
the lack of falls and any ponding were matters the Council should have noted or
acted upon in 2010/2011,
submitting there is no, or insufficient, evidence to
that effect. In these circumstances, the Council was not under any obligation
to
require the Trustees to re-roof. The Council also says that the roof has not
been shown to have failed in 2011 nor at the current
time. There may now be what
it considers to be a relatively minor amount of ponding, but any ponding
concerns can be rectified with
minor works and without a completely new roof. So
too, while still denying liability, the Council notes the experts agreed that
any
waterproofing failures could be repaired in isolation with targeted
repairs.
(f) Tanking. In this regard the Council says the relevant excavation in
2010 was not included in any building consent because it did not need to
be. Nor
was it embraced by the relevant code compliance certificate. The Council submits
there is no evidence of the alleged defect,
but that, even if it exists, the
Council has breached no relevant duty.
- [57] The Council
argues that the Trustees cannot establish any loss from the 2011 balcony tiling
breach because the subsequent 2014/2015
interim works and the 2016 works mean
there was a different set of circumstances by the time the claim was made, such
that the chain
of causation cannot be demonstrated, and damages cannot be
assessed. There were no photographs able to be provided or measurements
made of
the consequences in 2011 of the wrongly fixed tiling, that is there was nothing
to link the breach to the 2014 (and later)
leaking problem. The Council also
argues that the Trustees’ loss in 2011 was complete before its breach.
However, these arguments
ultimately go only to the 2016 wasted costs issue
because the Trustees have made it plain that apart from the 2016 wasted costs,
they do not otherwise claim damages flowing from the 2011 balcony tiling
breach.
- [58] The Council
accepts that it breached its duties in 2016 when issuing a building consent that
did not require the proposed balcony
works to comply with
the
Building Code and that it has to rectify that breach. The Council accepts that
targeted repairs, at a cost assessed by its expert
Mr Cutfield at between
$548,571 and
$581,310,8 are required and appropriate.
- [59] The Council
submits that the damages to be awarded should be discounted by at least 50 per
cent to reflect the Trustees’
negligence in terms of the Contributory
Negligence Act 1947.
- [60] It also
claims that damages should be adjusted so as to remove any potential betterment,
or assessed so as to exclude betterment.
Extent of Council’s duty and breach
Legal considerations
- [61] There is no
question but that the Council owed a duty of care to the Trustees or their
predecessor trustees when issuing building
consents, inspecting, and issuing
code compliance certificates in respect of both the 2011 and 2016 works. Those
duties are propounded
by the Trustees and accepted by the Council. They are
based on principles of negligence and on s 49 of the Act.
- [62] The
Trustees have the burden of proof to establish both duty and
breach.
- [63] Section
49(1) of the Act provides:
A building consent authority must grant a building consent if it
is satisfied on reasonable grounds that the provisions of the Building
Code
would be met if the building work were properly completed in accordance with the
plans and specifications that accompanied the
application.
- [64] Although
somewhat unclear, I believe that the Trustees seek to go further. They submit
that the Act requires all building work
to comply with the Building Code,
regardless of whether a building consent is required or sought for the work.
They refer
8 Mr Cutfield’s initial assessment was
$490,318. The sum of $581,310 reflects a possible increased scope of targeted
repairs and
both sums reflect the need for balustrades which had been overlooked
by both parties.
to Wheeldon v Body Corporate 342525,9 Fitzgerald v IAG
New Zealand Ltd,10 and s 17 of the Act, in support. Section 17
provides that all building work must comply with the Building
Code “to the extent required by this Act, whether or not a
building consent is required in respect of that building work”.
- [65] Effect must
be given to the words italicised above. Section 112 of the Act is relevant in
this context. Section 112(1)(b) provides
with regard to alterations to
existing buildings:
(1) A building consent authority must not grant a building
consent for the alteration of an existing building, or part of an existing
building, unless the building consent authority is satisfied that, after the
alteration,—
...
(b) the building will,—
(i) if it complied with the other provisions of the Building Code immediately
before the building work began, continue to comply
with those provisions; or
(ii) if it did not comply with the other provisions of the Building Code
immediately before the building work began, continue to comply at least to
the same extent as it did then comply.
(Emphasis added)
- [66] Schedule 1
of the Act is also relevant. That schedule provides for building work for which
building consent is not required and
where exemptions may be granted, as
follows:
1. General repair, maintenance, and replacement
(1) The repair and maintenance of any component or assembly
incorporated in or associated with a building, provided that comparable
materials are used.
(2) Replacement of any component or assembly incorporated in or
associated with a building, provided that—
(a) a comparable component or assembly is used; and
(b) the replacement is in the same position.
9 Wheeldon v Body Corporate 342525 [2015] NZHC
884, (2015) 16 NZCPR 829 at [160].
10 Fitzgerald v IAG New Zealand Ltd [2018] NZHC 3447 at
[48].
(3) However, subclauses (1) and (2) do not include the following building
work:
(a) complete or substantial replacement of a specified system; or
(b) complete or substantial replacement of any component or assembly
contributing to the building’s structural behaviour or
fire-safety
properties; or
(c) repair or replacement (other than maintenance) of any component or assembly
that has failed to satisfy the provisions of the
building
code for durability, for example, through a failure to comply with the
external moisture requirements of the building code; or
(d) sanitary plumbing or drainlaying under the Plumbers,
Gasfitters, and Drainlayers Act 2006.
2. Territorial and regional authority discretionary
exemptions
Any building work in respect of which the territorial authority
or regional authority considers that a building consent is not necessary
for the
purposes of this Act because the authority considers that—
(a) the completed building work is likely to comply with the building
code; or
(b) if the completed building work does not comply with the building
code, it is unlikely to endanger people or any building, whether on the same
land or on other property.
- [67] It is clear
from s 112 and sch 1 that to the extent the Trustees might contend that all
building work must comply with the Building
Code, regardless of whether a
building consent is required, then that is incorrect. So too is any suggestion
that a building consent
may not be issued if, after the proposed works, the
building does not comply with the Building Code. I am satisfied that s
112(1)(b)(ii)
provides for the lawful issuance of building consents provided the
new works are compliant or exempted from compliance and there
is otherwise no
reduction in the level of compliance. It also follows that a Council may issue a
code compliance certificate where
contemplated works are completed
notwithstanding that other aspects of a building will not be brought fully up to
Code. Contrary
to the Trustees’ submission, I do not consider Wheeldon
or Fitzgerald contradict these basic propositions and if they do, I
respectfully disagree.
- [68] For
completeness, I accept that there may often be circumstances where a council has
duties that extend beyond ensuring that
the works
specifically
contemplated by a building consent application are compliant with or exempted
from compliance with the Building Code. This may arise
for example where an
application that does not extend to certain works is patently inadequate, or as
a result of onsite inspections.
But this cannot be taken so far as to place such
a burden upon councils that they become underwriters of past work or of all
consequences
of owner oversight. A council is clearly not able to turn a blind
eye towards or otherwise ignore works brought squarely to its attention
even
though outside the scope of a consent application but, where there is a
suggestion that a consent should have extended to other
external elements of a
building beyond those expressly stated, the onus must be firmly on the owner to
establish the existence of
a duty or breach of a duty on the part of the
council.
Breach as to balcony tiling defects?
- [69] The Council
has not denied negligence in failing to notice the direct fixing of the tiles
when it certified in 2011 or when it
granted consent in 2015/2016. It seems
reasonably clear, and I so find, that the Council breached its duties in these
respects.
- [70] The
Trustees also pleaded that the Council breached its duty when undertaking
inspections of the balcony tiling in 2010, or otherwise
prior to the issuance of
the code compliance certificate. Little was made of this in closing submissions
and I have insufficient
evidence on which to conclude that the Council did so
breach. At most, in re-examination, Mr Flay said that the defective methodology
should have been noticed on 20 December 2010. Mr Paykel’s evidence was to
the effect that the non- compliance could not reasonably
have been identified by
the Council.
- [71] The Council
did receive a producer statement with a membrane that differed from what was on
the approved plans. However, this
is not per se advice as to the direct fixing
of the tiles and, even if it were, it is possible that a council would only look
at
such statements when considering the issuance of a compliance certificate. On
the evidence I am not satisfied as to the precise nature
of or the timing of any
such negligence.
- [72] I therefore
further find that the Council did not breach any duty in inspecting the balcony
tiling during the 2011 works or in
any other respect prior to the issuance of
the compliance certificate.
Breach as to cladding?
- [73] With
respect to the cladding, the experts have agreed that the Council has no
responsibility resulting from the key alleged defect,
incorrect cladding
thickness. As stated, the Trustees’ final position in relation to a
negligence allegation in this respect
is unclear but, to the extent they
maintain that allegation, I find it not to have been
established.
Breach as to seal issues?
- [74] The same
applies in relation to seal issues. The experts agreed the Council has no
liability. To the extent necessary to determine
the matter I find the sealing
issues not to have resulted from or to suggest any negligence on the part of the
Council.
Breach as to ProtectoWrap on parapets?
- [75] As has been
noted, the Trustees allege the Council is liable for defects in relation to the
parapets around the roof and the
saddle flashings. A second layer of EIFS tape
(also called ProtectoWrap), that was required to be installed over the top of
the Graphex
over the parapets and at the saddle flashing junction, was not
present.
- [76] Also as
noted, at the experts’ conference in April 2020, Mr Flay and Mr Paykel
agreed that the Council had breached no
duty in this regard. Mr Probett
investigated further and, on the basis of photos he produced from the Council
file, two in particular,
Mr Flay said the Council must have known or should have
been on notice of the missing second layer. He said one photo demonstrated
inability to install the tape where the abutting wall had been completed. His
stance became that the Council should therefore have
confirmed the presence of
the second layer on top of the parapets.
- [77] Mr Paykel
responded by saying that works were still ongoing at the time of inspection and
the Council could reasonably have assumed,
tape having been in evidence, that
the builders would continue in a compliant manner. He disputed Mr
Flay’s change in
evidence. He said the Council had acted reasonably based
on its observations during the staged construction. More particularly, Mr
Paykel
interpreted
the photographic evidence differently to Mr Flay. He considered the evidence to
be consistent with his view that a second layer of
ProtectoWrap either could
still reasonably be expected to be installed or had in fact been installed.
- [78] Mr Flay
acknowledged that in at least one photo a second layer of ProtectoWrap could
have been installed.
- [79] Mr Paykel
noted also that two layers of ProtectoWrap were being installed in other
locations, that the installers were licensed
and that a producer statement was
provided. For all these reasons, he did not consider that the Council had been
negligent in its
inspections.
- [80] Councils
are not underwriters of defects regardless of whether they ought reasonably to
have been discovered. Reasonable discoverability
for inspection purposes should
be a robust exercise. Given Mr Flay’s earlier agreement with Mr
Paykel that there had
been no breach, their different interpretations of the
further photos (both of which seemed to be available) and the other factors
Mr
Paykel notes, I am not satisfied that the Council was negligent in this
regard.
- [81] I find that
the Council did not breach its duties in 2011 and is not liable for these
defects.
- [82] In the
circumstances I do not need to address a further submission by Mr
Neutze to the effect that there must be evidence
of parapet failure to establish
breach. If this had been relevant, I would not have agreed with his submission.
While possibly relevant
to an assessment of damages, I do not consider that
actual damage must be demonstrated to establish breach. In this respect I agree
with Downs J’s view in Minister of Education v H Construction North
Island Ltd that there is no meaningful distinction between acceptable and
unacceptable damage.11 It suffices if it is established that damage
could result from a breach.12 I note though that the absence of
damage is often relevant to assessment of damages. It does not follow from
the
11 Minister of Education v H Construction North
Island Ltd [2018] NZHC 871.
12 See too Carter Holt Harvey v Minister of Education
[2016] NZSC 95, [2017] 1 NZLR 78 at [66].
decision in Minister of Education that defects must always be removed.
It was a given in that case.
- [83] For
completeness, if I had found the Council negligent in relation to the parapets,
I would be satisfied that the capping solution
proposed by Mr Paykel would
appropriately rectify the defect. The evidence of actual failure was
insufficient and the cappings would
remove any potential for failure as might
otherwise have resulted from the breach. I particularly do not accept the
Trustees’
submission that the rectification exercise should be influenced
by considerations of aesthetics. There is no evidence that aesthetics
were of
particular concern with regard to the house. In fact I would conclude otherwise.
I consider the aesthetics of the capping
solution to be acceptable and
commensurate in the context of the overall building. (I am not aware of evidence
as to the cost of
the capping solution but understand it to be relatively
minor.)
Breach as to tanking?
- [84] As to
tanking, the allegation is that in installing a new retaining wall in 2011 a
pre-existing membrane had been cut through
in order to tie the walls together
and the return wall should not have been connected as that results in moisture
migrating into
the house. This allegedly should have been identified by Council
on inspection. Again, the Trustees’ position in this respect
by the end of
the trial is a little unclear. The point did not seem to be specifically
addressed in counsel’s closing submissions.
But I am not aware that the
claim has been withdrawn.
- [85] Mr Paykel
said he saw no evidence of any membrane being cut “let alone cut as a
result of the retaining wall installation”.
He also said any damage might
have been caused following the Council’s inspection or in areas not
contemplated by the 2011
works. Mr Flay said the defect was in only one location
and that it was not a consenting issue because it was not in the
plans.
- [86] The
retaining wall was not part of the building consent, and no code compliance
certificate was issued in relation to it. As
stated, councils may still have
liability in circumstances where they are aware of unsatisfactory workmanship or
even
where they should be so aware. But I am not persuaded that there was any breach
of duty here.
- [87] In terms of
the alleged defect, the Trustees appear to rely upon one photograph.13
That photograph does seem to show that the wall is intended to abut an
existing structure, but it is a photograph of footings only
and not evidence of
non- compliance. Mr Flay appeared to accept this. When shown the photograph he
said, “I can’t comment
on whether any of the steel penetrates that
block wall or [compromises] that membrane”. Mr Probett said that the
evidence clearly
showed an area of bituthene tanking, which had no reason to be
there unless it was to provide a protective layer. I think he is correct,
but I
do not see how this justifies a conclusion that the Council failed in its
duties. I certainly do not accept that the Trustees
have established breach as a
result of the absence of details or information in relation to this matter on
the Council files.
- [88] Overall, I
find that the Council did not breach any obligations in relation to the tanking
defect. At the least there is insufficient
evidence to make any finding of
breach.
Breach as to roofing?
- [89] I consider
the Trustees’ argument with regard to the roof defects to be misconceived.
It was difficult to follow, not helped
by the Trustees’ statement of claim
which simply pleads defects and Council liability based on the duties to take
reasonable
care in granting consent, inspecting and certifying. That does not
sufficiently identify the Trustees’ case in this respect
at
least.
- [90] Although
counsel regularly referred to “the roof”, the house in fact has a
number of roofs. The Trustees point to
the alleged roofing defects, being
insufficient falls and excessive ponding across the roofs (defect 20-10) and
waterproofing failures
mostly near sheet joints on the first-floor roof (defect
21-10). Essentially the Trustees say the falls on the roofs and the roofing
membrane are non-compliant with the Building Code and that the Council is
responsible for those defects because it should
13 At 790 of the Council’s file, vol 2.
have required a new roof, which in turn would have removed the defects. It is
not suggested that the Council could or should have
taken any steps short of
requiring a new roof.
- [91] Mr Probett
gave extensive evidence as to the inadequacies of falls, the risks inherent in
liquid applied membranes, and the exclusion
of such membranes from the
application of E2/AS1 of Acceptable Solution E2/AS1 of the Building Code. The
extent of these defects
was materially disputed by the Council’s
experts.
- [92] Prima facie
the Council is not liable for these defects because, whatever the extent, the
defects were present in the roofs before
the 2011 works and were not made any
worse by those works. The Council does not have a duty to see to it that an
applicant for consent
remedies pre-existing defects, as is clear from s
112(1)(b)(ii) of the Act.
- [93] Furthermore,
this was not a situation where the Council should have been on notice that more
needed to be done. The Trustees
had not sought consent for a new roof. To the
contrary, the consented plans state the roof and roofing membrane were to be
retained.
I note further:
(a) The experts agreed that relevant works were only on the first-floor roof.
There were no works on the top roof or the level two
low-pitch roofs (and in
fact no defects on the top roof). Where no works are carried out, the Council
generally would have no duty
to inspect in any event.
(b) The works on the first-floor roof were relatively minor and involved
replacement of a small area of membrane on the flat surface
of the roof and the
addition of a small section of membrane lapping the horizontal surface of the
roof and against the vertical surface
where the roof abutted the upper wall
area. Even this was barely noted on the drawings. There was also a minor amount
of additional
work carried out that was not referred to in the plans.
(c) It may well be that the work carried out to the first-floor roof either did
comply with the Building Code (for example the falls
in that area were adequate)
or it amounted to maintenance or repair using comparable materials, and was work
which fell under cl
1 of sch 1 of the Act. That is, no building consent was
required. Alternatively, an exemption from obtaining a building consent would
have been available under cl 2 of sch 1 of the Act if necessary. Mr Paykel noted
that the cost of seeking a building consent might
be $25,000–$30,000 for a
repair that might cost $500–$600, which he considered disproportionate and
inconsistent with
the Act. He considered that the infilling of the roof that was
required as a result of other non-roof works would also have been
exempted if
necessary.
(d) I am not persuaded that cl 1(3)(c) of sch 1 precluded reliance on cls 1 and
2 of that schedule. The Trustees have not established
that it applies. As the
Council submits, there is no or insufficient evidence, photographic or
otherwise, to support the submission
that the roof had failed as contemplated by
cl 1(3)(c) above, or that the Council was or should have been on notice of
failings in
2010/2011 such that it should have required full compliance with the
Building Code. Mr Flay for the Trustees accepted, although he
considered ponding
at least at one location was “pretty obvious” when he inspected in
2020/2021, there was no evidence
suggesting a failure by the Council to notice
ponding (the lack of falls) in 2010. The evidence is that as at 2010 the roof
was performing
and had done so already for 13 years.
- [94] In these
circumstances the Council had no obligation to require the Trustees to build a
new roof, and I would doubt it even had
the right to do so. The Council could
possibly, if it considered it had the right, which is doubtful, have refused to
consent the
work applied for under s 49(1) of the Act. But there was nothing to
indicate that would have resulted in a new roof. It may have
simply meant that
no work was carried out (or an exemption sought). Either way, it would not have
removed the alleged defects which
it is agreed went back to the original
construction.
- [95] I therefore
reject the Trustees’ claim in this regard. The Council did not fail to
take reasonable care by “failing”
to require the Trustees to
construct new roofing.
Breach regarding failure to use Z flashings?
- [96] It is clear
that the 2010 building consent stipulated for the use of Z flashings. It is also
likely that the manufacturer of
the Graphex cladding product required such
usage. That manufacturer did not give evidence but the Trustees’ assertion
to this
effect did not appear to be seriously challenged by the Council. It is
also clear that Z flashings were not in fact used.
- [97] Mr Paykel
maintained that the Council could not reasonably have been expected to notice
the non-use during its inspections. He
also says that, even if the Council
should have noticed the non-use, there was no breach or at least that there was
no damage because,
had the Council noticed, it could and properly would have
issued a minor variation permitting the use of sealant instead of the Z
flashings. The Trustees did not appear to dispute this (in fact Mr Flay appeared
to concur) but Ms Whitfield contended that minor
variations had to be recorded
in writing, and none was recorded.
- [98] I accept
that a minor variation was probably required. But it does not follow that
non-compliance with procedure in this respect
results in a finding of breach of
duty. Where a deviation from a building consent stipulation would likely have
been effectively
waived by a variation, I do not consider the Council to have
failed to take reasonable care. I therefore reject the Trustees’
claim in
this regard also.
- [99] Even if
there had been a breach, damages would be nominal. Here, I note that, even after
changing his stance as a result of changed
evidence (with which I take no
issue), Mr Probett for the Trustees still accepted that this breach had not
caused significant damage.
Summary as to breach
- [100] The
Trustees have the burden of proof to establish breach. I have considered
carefully each alleged defect. I have clearly been
influenced by agreements or
near agreements reached by the experts, but I have also reviewed the evidence
submitted
and had regard to what I have said above about the extent of Council duties in
these circumstances.
- [101] For the
reasons noted, I am not satisfied that there have been any actionable breaches
by the Council other than the issuance
of a compliance certificate in 2011
notwithstanding the non-compliance of the balcony works, and the issuance of a
building consent
in 2016 when it provided for fixed
tiling.
- [102] To the
extent the Trustees allege other breaches, I have not been satisfied that they
exist. Specifically, I have not been satisfied
that the Council breached any
duties in relation to cladding, seal issues, ProtectoWrap, tanking, roofing or Z
flashings, all of
which are alleged to have occurred in
2010/2011.
What is the appropriate measure of damages in relation to the
tiling breaches?
- [103] The
two “balcony tiling” breaches above having been established,
(neither of which was denied by the Council), the
next step is to consider what
damages flow from those breaches.
Are the wasted costs in 2016 an appropriate measure of
damages for the 2011 certification breach?
- [104] In respect
of the 2011 certification breach, the Trustees claim a loss in terms of the
wasted costs of the 2016 work. I repeat,
as they have, they do not claim for
loss in terms of the cost of rectification work flowing from this breach. (For
completeness I
comment further on this point below.)
- [105] The
Trustees say that the 2016 wasted costs were incurred in mitigation of damage
and that the burden of proof falls on the
Council to disprove that. I do not
agree with that analysis. I consider that the standard test for causation
applies. That is, the
Council is liable for the cost of putting the Trustees in
the position they would have been in “but for” the Council’s
certification of the 2011 works. And it is for the Trustees to prove on the
balance of probabilities that the wasted 2016 repair
works fall into that
category. The Council’s negligence has to have been a material cause of or
contributor to the loss in
terms of subsequent wasted costs.
- [106] However,
in terms of the end result in this case, the difference in approach makes no
difference to the outcome. I am satisfied
that the wasted costs in 2016 do
reasonably flow as a consequence of the 2011 certification breach. There is no
evidence the Trustees
became aware of the Council’s breach in the interim.
It would have been material to the Trustees’ decision to repeat
the fixed
tiling in 2016 that the Trustees had the Council’s sign-off to that
methodology in 2011. Clearly also the 2016 rectification
works were a complete
waste of time and money.
- [107] As
discussed earlier, the Council says the wasted costs have not been proven to
flow from the 2011 breach. They rely on a novus
actus interveniens in terms of
the 2014 work or alternatively on their argument that because the
Council’s breach came after
the negligent work in 2011, the
Council’s breach did not cause a loss in terms of the cost of repairs. The
Council could have
given a notice to fix as Mr Flay acknowledged. In that event
the Council says it would have had no liability for the cost of
repairs.
- [108] The simple
answer to the latter point in the context of the wasted 2016 costs is that the
Council had not given a notice to
fix. The Trustees were not carrying out
rectification work as would have followed from a notice to fix and are not
claiming the cost
of that work based on the 2011 breach. They are claiming the
wasted 2016 costs. I consider that does flow from the certification
breach.
- [109] As to
whether the 2014 works broke the chain of causation, the Council says it is
possible those works caused the 2011 works
to fail and brought on the necessity
for the 2016 works. The interim works also meant that any photographic or other
evidence of
the state of the building as at the date of application for the 2016
consent could not be relied on as proof of what flowed from
the 2011
works.
- [110] The
evidence on the Council’s novus actus point was thin, which is
understandable given the Council knew nothing of the
2015 works at the time. The
only evidence came from Dr Linehan and comment by Mr Paykel. I believe that the
interim works were superficial.
The evidence of Mr Paykel, which I considered
throughout to be pragmatic and impartial, did not go so far as to realistically
suggest
that those works would have been a novus actus.
- [111] I
therefore find, subject to issues of contributory negligence, that the Council
is liable for the 2016 wasted costs of $197,528.
- [112] I do not
have to consider whether the Council would have been liable for damages based on
the cost of balcony (and other) repairs
following on from the 2011 breach
because the Trustees expressly base their claim in this respect only on the 2016
building consent
breach. I do not have to consider the Council’s arguments
in this regard.
- [113] I note
though, inter alia, that there may have been difficulties with proving that the
appropriate measure of loss flowing from
the 2011 breach was the cost of repair.
That is not to say that the Trustees would not have had a claim for damages
flowing from
the 2011 breach beyond the wasted costs on a different basis, but
the case was not advanced in that way.
- [114] In
particular, there is an issue as to whether the 2011 balcony breach, which I
have found proven only at the date of certification,
actually caused the
Trustees’ claimed loss in terms of the cost of repairs. The work had all
been completed at the point of
certification and the Trustees were in a position
where, even if certification had not been given, the costs they now claim would
have had to be incurred in any event at their own expense or the expense of
their contractor. This goes without saying but is also
consistent with the
evidence of the Trustees’ expert Mr Flay.14 The Council would
still be liable for the lost opportunity to repair as at and from 2011 and
potentially the lost opportunity to require
the builder to pay for that. And I
have already found it liable for the wasted costs. But it would not necessarily
be liable for
costs of rectifying work that had already been negligently carried
out prior to the Council’s negligence.
- [115] This is
reflected in [38] of Ms Whitfield’s latest submission where she
says:
If the Council had rejected the Code Compliance Certification in
2011 on the basis that the tiling work was defective, then the only
reasonable
inference is that the works would have been immediately remediated at no cost to
the Trustees. Because of Council’s negligence, the opportunity to
require the
14 Mr Flay did later say that the contractors’
breach should have been identified earlier, but I have found that the breach was
only at certification.
builder to comply with the Council’s requirements in 2011, at the
builder’s cost, was not afforded to Dr Linehan.
- [116] It does
not follow though that damages should be assessed on the basis of the cost of
repairs especially when there is no evidence
that when Dr Linehan became aware
of the issue the builder was unable to pay or unable to attend to the
rectification work.
- [117] I am not
aware of a comparable case where the Council has been found liable for the cost
of repairs where the claim is only
in respect of negligent certification and
where it is not either obvious or otherwise pleaded/accepted that the builder
whose negligence
preceded the Council’s, could not have paid or been held
liable.
- [118] However,
the point is academic and there is no need to take it any
further.
Are repair costs the appropriate measure of damages for the
2016 consenting breach?
- [119] The
Trustees’ claim for the cost of repairs (which they assess at
about
$1.36 million) is based on the alleged 2011 non-balcony breaches and the 2016
balcony breach. I have found against the 2011 non-balcony
breaches. The claim
for the full cost of repairs is therefore based solely on the Council’s
negligent grant of a building consent
in 2016 with regard to balcony works
only.
- [120] The
Trustees move from the conceded breaches to an argument as to the appropriate
measure of damages. Ms Whitfield submits that
the Council is liable for the full
repair costs. She says that the measure of loss for defective building cases is
the cost of repair
if it is reasonable to repair and if not, then diminution in
value. I accept that is frequently treated as the prima facie
“rule”.
Ms Whitfield says it is irrebuttable in this
context.
- [121] The
Council agrees with the prima facie rule but says it is not invariable or
inflexible and the overriding approach should
be to achieve fairness between the
parties, relying on the statements of principle in Johnson v Auckland
Council.15
15 Johnson v Auckland Council [2013] NZCA
662.
- [122] The
Council’s helicopter position throughout has been that it is prepared to
accept responsibility for “reasonable
repair costs for the balcony
defects, based on the Paykel scope of targeted repair, but it is not liable for
anything beyond that
targeted scope of repair”.16 The Council
accepts such liability as being consequent upon its 2016
breach.
- [123] In
defective building cases it is often not necessary to pause over causation
because it is obvious that the defendant is liable
for the full loss, and
obvious that will be the cost of repairs even possibly to the point of a
complete rebuild. That was the case,
for example, in North Shore City Council
v Body Corporate 188529 where the Council had negligently failed to notice
on inspection the defective foundations upon which a building had been
built.17 In that case the Supreme Court confirmed that the Privy
Council’s opinion in Hamlin was consistent with New Zealand law and
that territorial authorities were liable to original and subsequent homeowners
for loss caused
by the failure of building inspectors to carry out their
inspection functions with reasonable skill and care.18 The Court
noted the Privy Council’s finding that in cases of latent structural
defects which a Council by negligent inspection
had failed to prevent, the
owner’s loss was not the physical defect in the structure, but loss either
in the form of diminution
of the market value of the property or the cost of
repair, if that were reasonably possible. That explanation was based on the
House
of Lords decision in Ruxley Electronics and Construction Ltd v
Forsyth.19
- [124] But it is
necessary to be satisfied as to what loss has been caused in each case and
therefore what damages are appropriate.
In Ruxley itself a swimming pool
was negligently built to a maximum depth of six feet rather than seven feet, six
inches. The only practicable
method of achieving a pool with the required depth
was demolition and reconstruction. The owner sought damages on that basis. The
Judge was not satisfied the owner intended to build a new pool at that cost. It
was considered wholly disproportionate to the disadvantage
of having a shallower
pool and therefore the Judge considered it would be unreasonable to carry out
the works. On appeal the
16 As recorded in the Council’s latest
submissions.
17 North Shore City Council v Body Corporate 188529 [2010]
NZSC 158, [2011] 2 NZLR 289 (Sunset Terraces).
18 Invercargill City Council v Hamlin [1996] UKPC 56; [1996] 1 NZLR 513,
[1996] AC 624 (PC).
19 Ruxley Electronics and Construction Ltd v Forsyth [1996]
1 AC 344, [1995] 3 WLR 118.
Court upheld the trial Judge’s finding that the owner was entitled to
damages based only on loss of amenity.
- [125] I do not
accept Ms Whitfield’s proposition that it would not be permissible for me
to consider causation in this context
because the Council did not plead lack of
causation as an “affirmative defence” and further that the burden
would be
on the Council to prove it as an affirmative defence. The Council
denied causation in its statement of defence. Causation is one
component of the
cause of action on which the Trustees have the burden. They have to satisfy me
that the Council’s breach in
granting building consent for the further
work on the balcony in 2016 caused the loss for which they claim, namely the
full cost
of repairs, or at least that the Council is liable for those
costs/losses.
- [126] In my view
the 2016 breach(es) did not have the claimed effect. Before the 2016 works the
building was already, on the Trustees’
case, in a state where it required
the full Concept Plan repairs. The 2016 work was merely a failed attempt to
remedy one aspect
of the 2011 works. There is no evidence that the 2016 work
made the building or even the balconies worse than was already the case
before
the beginning of the work. The 2016 work did not cause the Trustees loss in
terms of the cost of rectification work. It failed
to remedy already existing
loss. The Trustees’ own case is that the 2016 work was a waste of time and
money.
- [127] The
Council is liable for the cost of putting the Trustees in the position they
would have been in “but for” the
Council’s negligent consent
to the 2016 works. That would put them back in the position they were in at the
point of making
application in 2016, which was that they had a house already
suffering from the defects and breaches now claimed. The loss to the
Trustees
flowing from the 2016 works was that they had wasted the costs involved, along
with any proven consequential losses, including
interest.
- [128] I have
already found that the wasted costs are recoverable as flowing from the 2011
breach. Those costs cannot be recovered
twice. There is no evidence of other
consequential losses beyond interest.
- [129] The
Council, as recorded, accepts responsibility for reasonable repair costs based
on the Paykel scope – but for nothing
beyond that. Based on that
concession and given that the Trustees might otherwise have argued their case
differently, I am constrained
to accept that the Council is liable for costs on
that basis, subject to my finding on contributory
negligence.
- [130] There is
then a difficulty as to whether the Council’s concession and the fact
their liability consequently exceeds the
finding I would otherwise make, affects
my finding as to wasted costs. The Council, although it accepted liability for
the Paykel
adjusted scope, expressly denied liability for the 2016 wasted costs.
However, I consider my finding as to liability for wasted costs
should stand
alongside the Council’s concession. That concession was not conditional on
a finding that the Council has no liability
for wasted
costs.
If the Council is liable for repair costs how are they
assessed?
- [131] If I am
wrong and the Council is liable for repair costs as a consequence of its 2016
breach, I nonetheless consider that the
appropriate approach to assessing those
costs is that taken by Mr Paykel for the Council, referred to as targeted
repairs. I therefore
would not come to any different conclusion than that
reached on the basis of the Council’s concession.
- [132] As noted,
at one end the Trustees seek damages at a level calculated to permit them to
substantially renovate or re-build the
house not only with new balconies but
also with a new roof, new cladding, and substantially modified design (as
mentioned, these
are referred to as Concept Plan repairs). And at the other end
the Council submits that its liability extends only to the cost of
what it
refers to as “targeted repairs”, the scope evidenced by Mr Paykel.
This involves the removal of the ground floor
balcony membrane and tiled surface
finishes, removal of balcony balustrades, removal of the surrounding wall
elevations, cladding
and joinery units. Mr Paykel notes that, once the decayed
timber framing had been replaced, new plywood, membrane, tiles and cladding
would be required. He considers it appropriate to look at repairing the tiling
defects as if they appeared in isolation. He is confident
that a building
consent for such remediation would be forthcoming.
- [133] In between
are other scopes of work, being different forms of like-for-like repairs on
which both parties have submitted but
for which neither advocates. In fact Mr
Laurent says any like-for-like repairs would be “unworkable”. There
are also
various assumptions as to the period that the works will take and other
variables.
- [134] The
various like-for-like scopes seek to rectify defects on, not surprisingly, a
like-for-like basis. This invariably involves
more cost than for targeted
repairs both because the extent of work within any line item is greater
(replacing a wall as compared
to possibly only repairing it), and because some
works are not included in targeted repairs at all. Roofing and site works are
examples
of the latter. Having said that, I do not perceive a significant
difference between the cost of the proposed targeted balcony repairs
and of a
like-for-like repair of the balconies. The material differences arise as to
other works that are included in the like-for-like
scopes. These scopes
originated as an alternative to the Concept Plan repairs and are not directed at
repairing the balcony breaches
solely.
- [135] The range
of costs for targeted repairs was between $490,318.26 and
$594,648.79. The range of costs of the like-for-like scopes is between Mr
Cutfield’s estimate of $771,399.30 and Mr White’s
estimate of
$1,127,970.14. The range of costs for the Concept Plan repairs is between
$1,090,509.21 and $1,333,302.96.
- [136] Given my
finding that the Council is liable only for balcony-related breaches, and my
subsequent findings, the like-for-like
repair assessments fall away. Neither
counsel argued that I should adopt these assessments in any
event.
- [137] Also,
given my finding that the Council is liable only for balcony-related breaches, a
scope of work that targets and seeks
to repair that breach would prima facie
appear appropriate.
- [138] The
Trustees seek damages based on Concept Plan repairs regardless of my finding
that there were no Council failures beyond
the direct fixing of the tiles.
Ms Whitfield submits that the evidence still leads to the conclusion that the
reasonably necessary
remedial works are the Concept Plan repairs. Whilst one
might be surprised at a suggestion that the level of damages would be
substantially
unaffected by the level
of breach, I do not dismiss that possibility. I accept at least that to achieve
the basic outcomes required (in this case delivering
balconies that comply),
other costs may be incurred and recoverable. Indeed, Mr Paykel’s targeted
repairs include for example
additional sections of replacement cladding. But the
Court would need to be satisfied that the additional costs are reasonably
necessary.
- [139] The key
question is whether the necessary repairs also reasonably necessitate other
works. I use the term “reasonably
necessitate” because I consider
that nothing less is appropriate. I do not consider that the Council should be
liable for the
cost of other works to make the house fully compliant with the
Building Code (bearing in mind the provisions of s 112 of the Act);
or that may
be “desirable”, “prudent” or even extremely
“advisable”. If the breach can be remedied
in isolation, then that
is the full extent of the Council’s obligations.
- [140] I am not
persuaded by the Trustees’ claim for Concept Plan repairs. In my view,
their evidence and in fact submissions
do not focus on the correct test. In
closing submissions Ms Whitfield says: “There is no betterment as the
works required are
reasonably necessary to put the plaintiffs in the position
they should have been in but for the Council’s negligence –
having a
house that complied with the Building Code”. Similarly Mr Laurent
regularly refers to addressing failure of the house
as opposed to failures for
which the Council is liable. As is clear, my task is not to assess the amount
required to make the house
fully compliant with the Code. That would well exceed
the Council’s liability.
- [141] Even to
the extent the Trustees refer to “reasonable necessity” they suggest
a lesser standard than “necessity”.
Much of the evidence (especially
from Mr Laurent and Mr Probett), addresses prudency or desirability or at least
strongly suggests
the additional works. Mr Laurent, for example, says that
anything less than his full concept plan is “not feasible or
reasonable”.
I consider all such evidence to be essentially irrelevant. My
sole concern is as to reasonable necessity.
- [142] I reject
the Concept Plan approach for the key reason that I am not persuaded the
Trustees’ experts have properly focussed
on the test that has to be
applied here. I am not persuaded that their expansive scope of works is
reasonably necessary. It is
focussed on delivering a house that is defect-free. That falls well outside the
present exercise.
- [143] That
essentially leaves the evidence of Mr Paykel in support of a targeted repair
solution. For clarity, I am referring to targeted
repairs under what is referred
to as the increased scope plus replacement of the balustrade. The latter was
agreed as a necessary
addition. Mr Paykel’s increased scope was in
response to a number of points made by Mr Probett. It was not ultimately clear
to me what position the Council took on the increased scope. As it makes only a
small difference to the end result, I have decided
to err in the Trustees’
favour and adopt the increased target repair solution.
- [144] In my view
Mr Paykel had carefully considered how rectification should proceed and his
approach best reflects the legal test
I must apply.
- [145] I accept
Mr Paykel’s evidence that the targeted repair works would be consented (or
more relevantly, I have not been satisfied
that they would not be consented) and
in particular that the cladding could be joined and did not require complete
replacement. While
Mr Laurent said that Resene would have to sign off on the
cladding joinder and he doubted they would, I had no evidence from
Resene.
- [146] Ms
Whitfield claims that the Council should have given evidence as to whether a
building consent would be forthcoming for the
targeted repairs. I do not accept
that. Indeed, I consider the Council acted appropriately in remaining neutral as
to its future
regulatory role. Expert evidence suffices. I note, as Mr Neutze
submits, that the Council granted consent for targeted works on the
balcony in
2016. While those works failed, the evidence is they failed because of repeated
direct-fixing, not the targeted nature
of the works.
- [147] Ms
Whitfield also refers to Gilbert J’s decision in Body Corporate 326241
v Auckland Council,20 in support of a submission that a plaintiff
should not have to accept “makeshift repairs” and be left with the
risk that
they will not be effective. I do not consider that decision to be
helpful here. There, the works in question were required as a direct
result of
breach. The question was as to the nature of repairs. The
20 Body Corporate 326241 v Auckland Council
[2015] NZHC 862.
defendant proposed (with little to support it) what the Court considered to be a
makeshift solution with inherent ongoing risks.
There is no suggestion by the
Council here that the works for which it is responsible should be carried out in
anything like a makeshift
manner, nor do I consider that to be the case, and the
scope has been properly evidenced.
- [148] I accepted
earlier that remedying one defect may sometimes require a much greater scope of
work than repair to the immediate
area, for which the party liable for the one
defect has to pay. However, I am not aware of a case where that involves
repairing significant
defects for which other parties are solely liable. Where
on the Trustees’ own case, the greater scope of work is also remedying
other defects at least as significant as the balcony defects, and which require
contemporaneous remedy, but for which I have found
the Council is not liable,
the cost of that work should be apportioned in any event to achieve a fair
outcome. This is analogous
to the concept of betterment, at least in terms of
principle. The Trustees would otherwise be receiving a windfall. On this basis
I
would again consider Mr Paykel’s scope establishes the extent of the
Council’s liability, even if a building consent
were not available for the
targeted balcony repairs alone.
- [149] There are
two further points I consider relevant but on which I do not
rely.
- [150] The first
is to consider what the Trustees would have done if they had been required at
material times to comply with the Building
Code in relation to the balconies.
Although Dr Linehan may have changed his stance in the past few years and
especially in the context
of this litigation, I am satisfied that he would not
have then proceeded with anything in any way similar to the Concept Plan
repairs.
There is, on the contrary, every indication that he would have either
pursued a non-compliant outcome dispensation so that he could
retain the fixed
tiling and achieve the aesthetic outcomes he clearly preferred or that he would
have himself proceeded with the
targeted repairs that Mr Paykel has
proposed.
- [151] Secondly,
the question of the likely issue of or the extent of work required to obtain a
building consent may be somewhat artificial
because, on the Trustees’ own
case, it seems it would be unreasonable for the Trustees to proceed with the
repairs
(other than, perhaps, on a very limited basis) and that it is unlikely they
would do so. The Trustees say it is imperative that they
properly remedy all
defects in their property, and that they implement Mr Laurent’s Concept
Plan. The cost of implementing
that plan, as noted, is estimated by the Trustees
at $1.36 million. But the Trustees’ own valuer says that, following that
work, the rectified building will still have significant stigma (in large part
attributable to their original purchase) and the value
of the rectified building
(even after the full Concept Plan redesign) will be only $854,000. That is
materially less than the claimed
repair cost. Ms Whitfield says the Council
cannot take the point that the work will not be carried out because Dr Linehan
was not
cross-examined on it. She says that the Trustees intend to proceed
with the Concept Plan and the property has significant sentimental
value as
evidenced by the substantial sums they have already paid. I note it is doubtful
the Trustees intended to pay anything approaching
those sums given the estimates
in the two building consent applications. But the point is that, as in
Ruxley, it is clearly uneconomic to effect the Concept Plan repairs. The
Council is not arguing that, as a consequence, the Trustees should
be limited to
diminution in value, but I agree with the Council, it may be relevant to a
pragmatic and fair assessment of the reasonably
necessary cost of repairs for
which the Council is liable, that it would be unreasonable on the
Trustees’ own case to carry
out the repairs on the basis claimed by
them.
- [152] In
assessing damages, I have not considered the implications of the transfer of the
house to the Trustees in 2013. The Council
took no exception to this transfer
per se. I note however that no evidence was provided as to the terms of
transfer. While the
Council clearly owes duties to purchasers, it is less clear
that damages suffered and compensable to such purchasers should be at
the same
level as for prior owners. If a purchaser buys a leaky home for land value only
(less any demolition costs) then one would
struggle to see any basis for
compensation. The correct plaintiff then would be the prior owner. No evidence
in this respect was
provided by the Trustees.
Quantum of “targeted repairs”
- [153] I
next consider how best to quantify damages based on the targeted repairs
increased scope. Evidence was given by two quantity
surveyors, Mr White for the
Trustees and Mr Cutfield for the Council.
- [154] Having
determined that Mr Paykel’s increased targeted repairs scope is the
appropriate scope for the assessment of rectification
damages and noting that
the Council agreed that balustrades which were previously overlooked must also
be replaced, the range of
costs is between $581,310 (Mr Cutfield) and
$652,902 (Mr White). Clearly the distance between the Trustees and the Council
as to the appropriate rectification methodology is far greater than the distance
between their experts as to the cost of such works.
- [155] As a
preliminary point, I agree with the Trustees that the Council has taken a
“top down” approach under which Mr
Cutfield critiqued the
Trustees’ costings and either adopted their costings or imposed his own.
Consequently, Mr Cutfield did
not suggest a cost item greater than that proposed
by the Trustees but often suggested lower figures. The Trustees say that this
was inconsistent with Mr Cutfield’s duties as an independent expert. Mr
Cutfield replied to the effect that he thought the
approach he had adopted was
most likely to assist the Court and that in a number of instances he had simply
accepted the Trustees’
figure even though it was higher than his own. I
note the Trustees’ concern and it is not without merit, but I have found
it
helpful to have a direct comparison.
- [156] Further, I
was impressed by Mr Cutfield’s testimony. He presented as highly
experienced. I did not consider him to have
been partial or that the weight of
his evidence was materially affected by his “top down” approach.
That is not to be
critical of Mr White (for the Trustees), but it is important
to remember that the burden here is on the Trustees.
- [157] The
overall difference between the two quantity surveyors is $71,000 approximately.
The key differences making up that sum are
regarding external scaffolding
($28,222), rubbish removal ($9,109) and architect fees ($15,180). These three
items total $52,000.
- [158] In terms
of the scaffolding, I find in favour of the Council’s figure. I am not
persuaded there is anything wrong with
Mr Cutfield’s approach, which was
based on rates from other projects, a “quote” for an approximate
rate and an
extra allowance for
location. I also consider it reasonable, as he has allowed, that the scaffolding
would not need to be in place for the entire construction
period.
- [159] I also
favour Mr Cutfield’s evidence regarding the labour cost of rubbish removal
(or at least am not persuaded it is
wrong). That is that most of the rubbish
will relate to sub-contractors’ works and will be covered by those
costings.
- [160] In terms
of architect fees, I do not consider I have sufficient evidence to decide
between the two figures. The burden is on
the Trustees, and I note that Dr
Linehan himself seemed to keep architect’s fees to a minimum in all of the
works carried out.
I have decided however, to halve the difference between the
two quantity surveyors on this cost item.
- [161] As to the
balance of the differences (that is a total of approximately $20,000), I adopt
Mr Neutze’s proposal, admittedly
advanced on a narrower basis, to split
that difference equally.
- [162] The end
result is an upward adjustment to Mr Cutfield’s increased targeted scope
costing of $581,310.14, by $17,300, leading
to a final rounded figure
of
$598,610 which I fix as the quantum of the cost of repairs.
- [163] I referred
above to the possibility that damages might need to be reduced by a contribution
or credit from the Trustees to reflect
costs they would have incurred if the
Council had not breached or to reflect betterment. For completeness, I note that
no such adjustments
are required in the context of a targeted repair solution.
If I had found in favour of a wider scope of works then such adjustments
may
well have been required.
Other heads of damages
Stigma
- [164] The
Trustees seek damages of $104,000 for stigma associated with the failed 2011 and
2016 works. They say that even after repairs
are completed (which based on the
Council’s concession and my alternative finding is on a targeted basis),
the
house will be worth materially less than it would have been because of the
stigma attached to it and claim that $104,000 of that
stigma relates to the two
defective works.
- [165] Leaving to
one side the question of whether trustees of a trust can ever be said to suffer
stigmatic losses in a context like
this, I am not persuaded that the Trustees
have suffered material additional stigma from the Council’s failings. The
Trustees
of the Hilldon Trust, the original Linehan purchaser, were prepared to
foot the stigma of a building they knew to be leaky and that
had the obvious
characteristics of such a building. They lived with that stigma for eight years
before taking action. That stigma
is obviously significant even on their own
valuers’ evidence. I accept there would be some additional stigma from two
lots
of faulty repairs but consider it artificial and strained to try to
apportion that against the considerable stigma that would be
attached to this
building anyway. Importantly here, the Council is arguably not liable for the
fact the 2011 works were defective,
all of that work having been completed prior
to certification. At best it is only liable in small part for the 2011 defective
works,
being that which relates to the balcony tiling breach. The
Trustees’ list of defects requiring repair is considerably wider
than the
liability I have found on the part of the Council. I also note that while there
is precedent for a stigma award for faulty
original construction, no case has
been cited where damages have been awarded for additional stigma resulting from
repairs.
- [166] For these
higher-level reasons, I do not allow the claim. Also, while not questioning Mr
Coakley’s qualifications as an
expert valuer, his stigma analysis is not
sufficiently probative. He relies on material that strays from the usual hard
data comparatives
used by expert real estate valuers, including hearsay
conversations with vendors and real estate agents. Ultimately there is no
reliable
data to support his percentage breakdown of the total stigma from which
he says the house will suffer even after full repair, into
the components of
stigma from the original construction, and from each separate bracket of work.
In all, I do not find his evidence
or this claim
persuasive.
- [167] The claim
for stigma is therefore rejected.
Resource consent costs
- [168] The
Trustees seek to recover $5,305, being their costs for a resource consent
application that was submitted in relation to
protruding eaves. I do not
consider the Council to have any responsibility for the protruding eaves. They
are not attributable to
any breach by the Council and, to the extent the Council
might be responsible for the cost of targeted repairs, are not necessary
to
progress those repairs. I therefore reject this claim.
Removal and storage costs
- [169] These
costs were assessed at $7,992 on the basis of the Concept Plan repairs. The
Council is not liable for Concept Plan repairs.
Nor is there any suggestion that
the targeted repairs will require the removal and storage contemplated. The
Trustees’ claim
in this respect fails.
General damages
- [170] The
Trustees claim $15,000 general damages for each of the two failed works. Their
claim is premised upon their stance that
the Council’s breaches have
caused them stress and anxiety. I have found that the Council has only breached
its duties in relation
to certifying the deck tiling in 2011 and consenting in
2016. Again, the defects went well beyond that. The 2011 work was defective
in
many respects, certainly on the Trustees’ evidence. It is difficult in
those circumstances to make any realistic assessment
of the share the Council
should bear, but I allow $15,000 in total for this head of
damages.
Interest
- [171] The
Trustees claim interest under the Judicature Act 1908 at five per cent per
annum from the date costs were assessed, or
incurred, until judgment. Mr Neutze
submits that interest should not apply. I disagree. The claim has been assessed,
or costs incurred,
as at stated dates and, but for the time required to
litigate, sums were payable at those stated dates. The principle established
in
Worldwide is applicable.21
21 Worldwide NZ LLC v NZ Venue and Event
Management Ltd [2014] NZSC 108, [2015] 1 NZLR 1 at [23].
Also costs, particularly of building works, are never static. Interest is to
apply on damages as assessed.
- [172] The Court
has a discretion to assess interest at a lower rate than five per cent but that
is not appropriate here.
Contributory negligence
Legal principles
- [173] There
remains the question of whether there has been contributory negligence on the
part of the Trustees. The Council seeks
to invoke s 3 of the Contributory
Negligence Act 1947. It claims that any damage suffered by the Trustees for
which the Council would
otherwise be liable has resulted, at least partly, from
the fault of the Trustees such that the damages recoverable should be reduced
to
such extent as this Court thinks just and equitable having regard to the
Trustees’ responsibility for the damage.
- [174] Counsel
for both the Trustees and the Council appear to be agreed on the applicable
principles. Section 3 of the Contributory
Negligence Act contemplates a
reduction in the damages that would otherwise be recoverable to such extent as
the Court thinks just
and equitable having regard to a plaintiff’s share
in the responsibility for the damage. The pre-condition is that the damage
in
question must have been at least partly caused by the fault of the Trustees.
Burden of proof issues are subtle but they are embraced
or removed by the
Court’s assessment of what is just and equitable.
- [175] Fault is
akin to negligence but is a wider term. In particular, it is not necessary for
the Council to prove that the Trustees
owed it a duty of care. It is sufficient
to show negligent failure to avoid being hurt by the Council or to take
precautions that
would have reduced the loss.22 If there is a point
of disagreement in principle here between counsel it is that there are some
indications that the Trustees consider
s 3 cannot apply unless the Council could
prove negligence against them. I do not consider that is so and indeed if it
were so then
s 3 would add little if anything to a
22 Carolyn Sappideen and Prue Vines (eds)
Fleming’s The Law of Torts (10th ed, Brookers, Sydney, 2011) at
[12.30].
simple cross-suit or to issues of causation. For that reason, I tend towards
using the term “fault” rather than negligence.
That fully accords
with s 3.
- [176] Contributory
negligence must be assessed against the nature and extent of the relevant
breaches. For example, if I had found
that the Council had breached duties in
relation to the roof, it is possible that there might be additional
“fault” considerations
in relation to that
issue.
- [177] I consider
the matters broadly raised by Mr Neutze to be relevant to a s 3 assessment and
address them below in chronological
order. Also expressly referred to are
specific points raised by Mr Neutze which I reject:
(a) Dr Linehan failed to retain an expert weathertightness report he obtained
when purchasing the property, or if he did, he did
not show it to his builder or
to the Council. The extent of that report is not known. At a minimum the report
identified problems
with water ingress into the walls, particularly around the
front stairs and in respect of the easterly wall. The expert’s report
may
have gone further and for example identified the problem with the deck tiling.
In any event the report may have been of assistance
to Dr Linehan and his
builder and it may also have been possible to gather more information from the
writer of the report.
(b) Despite having obtained the report Dr Linehan took no steps in respect of
the weathertightness issues until 2010 when there was
“a large bulge
containing many litres of water protruding down from the ceiling in the
garage”. There is no evidence that delay contributed to or exacerbated
the damage suffered. However, it does mean that Dr Linehan
was facing urgent
works where that should not have been necessary. He left himself with no time to
conduct appropriate due diligence
into the extent of work required and to secure
appropriate expert assistance. He embarked instead on a rushed job.
(c) I note at this point Mr Neutze’s submission that Dr Linehan had found
a screwdriver hole in the membrane in the easterly
wall and determined that
water ingress issues were caused by this despite his lack of qualifications to
form that view and despite
the original report. I consider this largely
irrelevant, but it adds to the tapestry of an owner who it seems was avoiding
taking
steps to fully investigate the condition of his house.
(d) Dr Linehan retained Mr Barber without appropriate due diligence into his
qualifications and reliability. He took Mr Barber’s
own word as to his
expertise. As Mr Neutze said, Dr Linehan engaged Mr Barber on a handshake. I
heard no evidence from the insurer,
whose involvement was obviously minimal.
Clearly Mr Barber was not thorough, compliant or sufficiently expert. Ms
Whitfield correctly
pointed out that a client is not responsible for ensuring
that design or the finished building complies with the Code, referencing
Minister of Education v H Construction North Island Ltd.23
That is the responsibility of the professionals they have engaged and the
client is reliant on advice given by those professionals.
But an owner is still
responsible for engaging expertise at an appropriate level especially with a
house such as this. In this case
Dr Linehan clearly failed to engage a builder
who was suitably qualified, thorough or compliant, or to take reasonable steps
to do
so.
(e) The Council notes that Dr Linehan failed to enter into appropriate
contractual arrangements with Mr Barber. I cannot see that
this was
causative.
(f) Dr Linehan failed to take any steps when he should have known quite quickly
that Mr Barber was someone who cut corners. Dr Linehan
would have known of this
from the outset when Mr Barber carried out significant works without a building
consent and was ordered
to stop
23 Minister of Education v H Construction North
Island Ltd [2018] NZHC 871 at [334].
work. It is likely Dr Linehan would have known the plans were not even
available. When Mr Barber finally made application for building
consent he
estimated costs at a fraction of the final cost. This indicates either a
complete lack of preparation or a lack of forthrightness.
Again Dr Linehan
should have been aware of this. Dr Linehan should also have been concerned,
again at an early point, at Mr Barber’s
preparedness to direct-fix tiles
when he said (at the least) that was not preferable and not allowed by at least
some councils. That
this was too cavalier an approach for works such as this
would have been evident to the reasonable owner.
(g) Further in this regard, Dr Linehan (and his builder) failed to take any
account of the only expert he did engage. Dr Linehan
had used Ms Simpson
as a “technical exercise” to reflect the plans he and Mr Barber
had discussed. He says he
did not look at those plans. If that is true, he
should have done so, or at least inquired of Ms Simpson or Mr Barber what the
plans
provided for regarding the balcony tiling. Instead, he and Mr Barber
ignored the plans at least in that significant respect.
(h) Dr Linehan was intimately involved in the most critical decision, namely the
decision in 2011 to fix the tiles and not to suspend
them. I consider this
particularly relevant. It is clear that Dr Linehan knew at all material times at
least that other councils
required a suspended tiling solution and that this was
the preferred solution (rather than direct fixing). He was or should have
been
aware of the risks. Having been approached by Mr Barber to make a decision on
this, I consider a reasonable owner could have
inquired more fully and that even
the briefest of inquiries would likely have caused him to conclude that direct
fixing was not only
ill-advised but in fact contrary to the Building Code,
contrary to the consent, and contrary to his own plans. Again, I am not making
any findings as to actionable negligence. I am considering “fault”
solely for the purposes of s 3.
(i) Dr Linehan failed to obtain expert advice that a reasonable owner would have
obtained, and followed, in the circumstances. An
owner in Dr Linehan’s
circumstances with a valuable property, long suffering from weathertightness
issues, must bear a degree
of responsibility for ensuring the issues are
understood, appropriate experts engaged, and their advice/reports followed. He
recognised
the need to engage experts before buying the house and again for
purposes of this litigation. It is not fanciful to think that with
a fraction of
the expertise he engaged for this case before and during the 2011 building
project, Dr Linehan would not have been
in Court.
(j) Especially relevant is the fact that, despite the sorry history of repairs,
Dr Linehan continued in 2015/2016 to use and to have
almost complete faith in Mr
Barber and to persist with a tiling solution that had failed by that stage
twice, once in 2011 and
again in 2014. Interestingly Dr Linehan still
did not inquire of Ms Simpson and in fact engaged a different draftsperson. At
this point it must have been even clearer that Dr Linehan needed to engage
consultants with special expertise in remediation. I am
not persuaded that Mr
Brunton provided that assistance. It was not good enough, particularly given the
terms of the contract with
Mr Barber, under which he was liable for all
subcontractors, for Dr Linehan to rely on Mr Barber, whether Mr Barber
attributed
blame to the tiler or not. The Trustees should have sought expert
advice before taking any further steps.
- [178] I consider
each of the factors I have identified as relevant to have had causative potency
and that Dr Linehan clearly contributed
to his (the Trustees’) own
loss.
- [179] Overall,
having regard to the evidence, I am satisfied that Dr Linehan (and therefore the
Trustees) as owners of a valuable
property they knew to have material
weathertightness issues materially failed to take such steps as they reasonably
could to ensure
the job was well done. They ought to have taken more advice both
at the outset and over time and to have followed the advice
they did
receive from Ms Simpson and even Mr Barber as to the tiling. The further
advice could reasonably
be expected to have extended to more thorough investigation, to more thorough
design solutions, suitably expert builders and contractors
and/or to
supervision. Dr Linehan also personally made the decision to affix the tiles in
2011 even though he had been told it was
not the preferred option. If Dr Linehan
had taken appropriate advice and exercised more care in decisions about the
works, it is
likely that the 2011 building consent would have been complied with
and this action would not have arisen. That was even more the
case in 2016.
- [180] On the
basis of the breaches by the Council and the scope of damages that I have found,
I consider it just and equitable to
reduce such damages by 50 per cent under s 3
of the Contributory Negligence Act, having regard to the Trustees’ own
responsibility
for the damage.
- [181] In fixing
the percentage, I have not distinguished conduct in 2011 from subsequent
conduct. The Trustees’ claim and therefore
quantum is based largely on the
2016 breach. If anything, I consider the percentage of contributory negligence
in the 2016 works
higher than 50 per cent, so 50 per cent is a fair overall
apportionment of responsibility.
Judgment
- [182] Accordingly,
I order the Council to pay damages to the Trustees as
follows:
(a) 50 percent of the cost of increased targeted repairs of $598,610, being
$299,305.
(b) 50 per cent of wasted costs of $197,528, being $98,764.
(c) 50 per cent of general damages of $15,000 being $7,500.
(d) Interest assessed under the Judicature Act at five per cent per annum from
the date of Mr White’s assessment in the case
of (a) and from the date the
costs were incurred in the case of (b), down to the date of
judgment.
- [183] Counsel
wished to be heard separately as to costs. The plaintiffs are to file
submissions within two weeks, the defendants to
file submissions one week
afterwards and the plaintiffs may file reply submissions if any within one
further week. All submissions
are to be limited to five
pages.
Hinton J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2021/3234.html