NZLII Home | Databases | WorldLII | Search | Feedback

High Court of New Zealand Decisions

You are here:  NZLII >> Databases >> High Court of New Zealand Decisions >> 2021 >> [2021] NZHC 3234

Database Search | Name Search | Recent Decisions | Noteup | LawCite | Download | Help

Linehan v Thames Coromandel District Council [2021] NZHC 3234 (29 November 2021)

Last Updated: 20 December 2021


IN THE HIGH COURT OF NEW ZEALAND HAMILTON REGISTRY
I TE KŌTI MATUA O AOTEAROA KIRIKIRIROA ROHE
CIV-2017-419-000141
[2021] NZHC 3234
BETWEEN
BRIAN JOSEPH LINEHAN, SHANNON JAMES WALSH and
ROSS DOUGLAS BLAIR as trustees of the Eliza Trust
Plaintiffs
AND
THAMES COROMANDEL DISTRICT COUNCIL
First Defendant
BERNARD BARBER LIMITED
Second Defendant
BERNARD BARBER
Third Defendant
MARK TARRANT HOSKINS
Fourth Defendant
.../intituling cont over
Hearing:
13–24 July 2020, 1 December 2020, 9 February 2021.
Further submissions filed 18 October and 1 November 2021.
Counsel:
VA Whitfield, KI Bond and LHH Hunt for Plaintiffs DJ Neutze and C Robertson for Defendant
Judgment:
29 November 2021


JUDGMENT OF HINTON J

This judgment was delivered by me on Monday, 29 November 2021 at 4 pm

pursuant to Rule 11.5 High Court Rules.


Registrar/Deputy Registrar

Solicitors/Counsel:

Brookfields Lawyers, Auckland.

Braun Bond & Lomas Ltd, Hamilton. VA Whitfield, Cambridge.

LINEHAN v THAMES COROMANDEL DISTRICT COUNCIL [2021] NZHC 3234 [29 November 2021]

CITY CERTIFYING CONSULTANTS LIMITED
Fifth Defendant

MURRAY SIEVERS
Sixth Defendant

MARK GORTON
Seventh Defendant

STRAIGHT EDGE EXTERIOR PLASTERING LIMITED
Eighth Defendant

PENINSULA ROOFING LIMITED
Ninth Defendant

PAULA MAREE HARVEY
Tenth Defendant

1 No mention was made of the other plaintiff trustees. I refer to the Trustees and Dr Linehan interchangeably.

direct-fixed tiling. It denies any other breaches and denies that it has any liability other than it accepts liability for the cost of targeted repairs for the 2016 balcony breach. The Council assessed that cost at $548,571, or at most $581,310. The Council says any award of damages should be reduced by at least 50 per cent for contributory negligence.

Background

2 As counsel continued to use the full intituling, I have done likewise.

now the contents of a report prepared in 2003, that Dr Linehan plainly had not read since 2010 or earlier, and that he did not bother to retain. The investigator may for example have not only reported on actual leaks but also on leak risks generally including risks inherent in fixed tiles.3 A purchaser who obtains such a report prior to purchase would want to know everything they could about the house so that, with their eyes open, they were best able to negotiate that purchase.

3 The problems with direct-fixed tiles were well-known at the time of the 2003 report. See brief of evidence of Andre Vernon Laurent dated 23 October 2019 at [27] and [28].

4 Trading as Bernard Barber Ltd but referred to throughout as Mr Barber.

leaks, to obtain all necessary consents and to ensure all legal requirements were met. Dr Linehan’s oral evidence is that Mr Barber was engaged to re-clad the house, install new double-glazed aluminium windows, extend an existing deck, and remove high- risk (in terms of promoting water ingress) features of the dwelling related to its curved walls. He and Mr Barber also decided to replace all the tiles; including on the decks, and to change staircases and the entrance foyer. The engagement did not refer to any repairs of the roofs of the dwelling.

5 The scope of pre-consent works is not clear but on 30 September 2010, Mr Barber sent invoice No 3 to Dr Linehan for $120,901.45. Given that he had undertaken to stop works until 20 September, this (and possibly earlier invoices) were presumably at least in part for work done prior to the date of the building consent.



6 I refer generally to the 2010/2011 works as being 2011 because that is how counsel describe them.

$49,000. The actual cost was $197,528, significantly less than the 2011 works, but the scope of the works was much more limited.

The experts

The Trustees’ experts

or weathertightness expert”. Mr Laurent says it is his policy wherever possible to eliminate risk rather than manage it as many of the issues they find are actually designed to fail. His evidence extended to the plans and specifications submitted with the 2016 building consent and his opinion as to the remedial works required to rectify the defects with the house. Mr Laurent does not refer to any previous experience as an expert witness.

The Council’s experts

insurers and councils in both claimant and defendant capacities. His testimony was extensive. It included testimony as to Council liability and as to remedial solutions.

My observations on the expert testimony

Summary of the Trustees’ case


(a) Balconies. This is the tiling issue already noted, where the Council accepts breach.

(b) Cladding. The key issue is that the plaster applied in 2011 was too thick. The experts agreed the Council is not liable, which in context is an agreement that the Council had breached no duty in relation to the cladding.

(c) Z Flashings. The 2010 building consent contemplated that Z flashings would be used behind horizontal joints. They were not so used. Sealant had been used instead. The Trustees say the Council should have identified this on inspection.

(d) Seal issues. There were a large number of defects listed in the schedule. I will not detail them because the experts agreed that the Council had not breached any duties in relation to them.


7 See for example Minister of Education v H Construction North Island Ltd [2018] NZHC 871 and

Bates v Auckland Council [2021] NZHC 2558.

(e) Parapets. The Trustees claim that the paint on the upper parapet bands is porous and inadequately coated, the saddle flashings have failed and are allowing moisture entry. They say the required layer of ProtectoWrap EIFS tape was not installed over the top of the parapets and that there is plaster shearing in parapet caps. The Trustees allege the Council should have identified the missing ProtectoWrap.

(f) Roof. The defects schedule notes inter alia a lack of falls (and some ponding) on the first-floor roof and on other roofs. It also notes waterproofing issues with the membrane on the first-floor roof. The Trustees claim that the Council is liable for these defects because the 2010 building consent process contemplated work would be done to the roofing in a manner that required the Council to insist upon full compliance with the requirements of the Building Code (especially as to falls, ponding and membranes). They also claim that, even if this was not the case, the Council should have noticed the extent of works actually carried out in 2011 and then required such full compliance. They say that as a consequence the Council should have required the roof to be replaced. (The Trustees accept that this would mean the roofing should have been addressed by them in 2010 or at least that they should not get a “free roof” from the Council. To adjust for this, they say it is appropriate to assess the cost of such works as at 2010/2011 applying CPI adjustments retrospectively against current costings and to include a credit for that, plus interest, against the currently assessed costs.)

(g) Tanking. The Trustees allege that, in installing a new retaining wall, an excavation in the 2011 works cut through a pre-existing membrane in order to tie the walls together and that the return wall should not have been connected as that results in moisture migrating into the house. They say the Council failed to pick this up on inspection.
the nature of any breach, and also on their argument that even with regard to the one accepted balcony tiling breach, the same quantum of damages followed. The Trustees’ closing submissions strongly suggest that claims of direct breach regarding cladding and sealing defects are not maintained but, in the absence of clear confirmation of that I make formal rulings below regarding each of the listed “defects”.
clearly extensive. The photographic and pictorial evidence is such that there is no obvious similarity between the existing house and that proposed by Mr Laurent. Mr Laurent rejected any lesser scope of works. He was particularly critical of the repairs proposed by the Council to which I will refer soon.

Summary of the Council’s case


(b) Z Flashings. The Council accepts that the building consent stipulated that Z flashings must be used and that they were not. It denies negligence. The basis for this is not clear but it can only be that the Council could not reasonably have been expected to pick this up. However, it says that, if the non-use had been noted, it would have resulted in a minor variation permitting the use of the sealant instead of the Z flashings. The Trustees’ expert Mr Flay agreed with this. The Council also says that the non-use has not been shown to have caused any damage and that the Trustees’ expert Mr Probett agreed it had not caused significant damage.

(c) Sealant. Again, the experts agreed that the Council had breached no obligation in relation to this defect.

(d) Parapets. The Council denies breach in relation to allegedly defective works on the parapets. Mr Flay and Mr Paykel agreed that the Council had not breached any obligation in this regard. Subsequently, Mr Flay altered his position based on further investigations by Mr Probett, which the Council says did not justify the change in position. Further, the Council claims that Mr Probett’s testing was supportive of its claim that there was no evidence of damage.

(e) Roof. The Council says the building application did not seek any consent as to roofing on the upper-level roof or the level two low-pitch roof surfaces (nor was any carried out). There was no reason for the Council to address those roofs. There was some relatively minor work on upstands on the first-floor roof and replacement of a small section of membrane, but the plans recorded that the existing roof membrane was to be retained. The Council says the Trustees elected not to carry out any roof works other than what amounted to maintenance or minor works as necessitated by other works for which consent was granted.
In those circumstances the Council was not under any obligation to bring the roof into full compliance with the Building Code. The Council also denies that the lack of falls and any ponding were matters the Council should have noted or acted upon in 2010/2011, submitting there is no, or insufficient, evidence to that effect. In these circumstances, the Council was not under any obligation to require the Trustees to re-roof. The Council also says that the roof has not been shown to have failed in 2011 nor at the current time. There may now be what it considers to be a relatively minor amount of ponding, but any ponding concerns can be rectified with minor works and without a completely new roof. So too, while still denying liability, the Council notes the experts agreed that any waterproofing failures could be repaired in isolation with targeted repairs.

(f) Tanking. In this regard the Council says the relevant excavation in 2010 was not included in any building consent because it did not need to be. Nor was it embraced by the relevant code compliance certificate. The Council submits there is no evidence of the alleged defect, but that, even if it exists, the Council has breached no relevant duty.
Building Code and that it has to rectify that breach. The Council accepts that targeted repairs, at a cost assessed by its expert Mr Cutfield at between $548,571 and
$581,310,8 are required and appropriate.

Extent of Council’s duty and breach

Legal considerations

A building consent authority must grant a building consent if it is satisfied on reasonable grounds that the provisions of the Building Code would be met if the building work were properly completed in accordance with the plans and specifications that accompanied the application.




8 Mr Cutfield’s initial assessment was $490,318. The sum of $581,310 reflects a possible increased scope of targeted repairs and both sums reflect the need for balustrades which had been overlooked by both parties.

to Wheeldon v Body Corporate 342525,9 Fitzgerald v IAG New Zealand Ltd,10 and s 17 of the Act, in support. Section 17 provides that all building work must comply with the Building Code to the extent required by this Act, whether or not a building consent is required in respect of that building work”.

(1) A building consent authority must not grant a building consent for the alteration of an existing building, or part of an existing building, unless the building consent authority is satisfied that, after the alteration,—

...


(b) the building will,—

(i) if it complied with the other provisions of the Building Code immediately before the building work began, continue to comply with those provisions; or

(ii) if it did not comply with the other provisions of the Building Code immediately before the building work began, continue to comply at least to the same extent as it did then comply.

(Emphasis added)

1. General repair, maintenance, and replacement

(1) The repair and maintenance of any component or assembly incorporated in or associated with a building, provided that comparable materials are used.

(2) Replacement of any component or assembly incorporated in or associated with a building, provided that—


(a) a comparable component or assembly is used; and

(b) the replacement is in the same position.


9 Wheeldon v Body Corporate 342525 [2015] NZHC 884, (2015) 16 NZCPR 829 at [160].

10 Fitzgerald v IAG New Zealand Ltd [2018] NZHC 3447 at [48].

(3) However, subclauses (1) and (2) do not include the following building work:


(a) complete or substantial replacement of a specified system; or

(b) complete or substantial replacement of any component or assembly contributing to the building’s structural behaviour or fire-safety properties; or

(c) repair or replacement (other than maintenance) of any component or assembly that has failed to satisfy the provisions of the building code for durability, for example, through a failure to comply with the external moisture requirements of the building code; or

(d) sanitary plumbing or drainlaying under the Plumbers, Gasfitters, and Drainlayers Act 2006.

2. Territorial and regional authority discretionary exemptions

Any building work in respect of which the territorial authority or regional authority considers that a building consent is not necessary for the purposes of this Act because the authority considers that—


(a) the completed building work is likely to comply with the building code; or

(b) if the completed building work does not comply with the building code, it is unlikely to endanger people or any building, whether on the same land or on other property.
contemplated by a building consent application are compliant with or exempted from compliance with the Building Code. This may arise for example where an application that does not extend to certain works is patently inadequate, or as a result of onsite inspections. But this cannot be taken so far as to place such a burden upon councils that they become underwriters of past work or of all consequences of owner oversight. A council is clearly not able to turn a blind eye towards or otherwise ignore works brought squarely to its attention even though outside the scope of a consent application but, where there is a suggestion that a consent should have extended to other external elements of a building beyond those expressly stated, the onus must be firmly on the owner to establish the existence of a duty or breach of a duty on the part of the council.

Breach as to balcony tiling defects?

Breach as to cladding?

Breach as to seal issues?

Breach as to ProtectoWrap on parapets?

the photographic evidence differently to Mr Flay. He considered the evidence to be consistent with his view that a second layer of ProtectoWrap either could still reasonably be expected to be installed or had in fact been installed.


11 Minister of Education v H Construction North Island Ltd [2018] NZHC 871.

12 See too Carter Holt Harvey v Minister of Education [2016] NZSC 95, [2017] 1 NZLR 78 at [66].

decision in Minister of Education that defects must always be removed. It was a given in that case.

Breach as to tanking?

where they should be so aware. But I am not persuaded that there was any breach of duty here.

Breach as to roofing?

13 At 790 of the Council’s file, vol 2.

have required a new roof, which in turn would have removed the defects. It is not suggested that the Council could or should have taken any steps short of requiring a new roof.

(a) The experts agreed that relevant works were only on the first-floor roof. There were no works on the top roof or the level two low-pitch roofs (and in fact no defects on the top roof). Where no works are carried out, the Council generally would have no duty to inspect in any event.

(b) The works on the first-floor roof were relatively minor and involved replacement of a small area of membrane on the flat surface of the roof and the addition of a small section of membrane lapping the horizontal surface of the roof and against the vertical surface where the roof abutted the upper wall area. Even this was barely noted on the drawings. There was also a minor amount of additional work carried out that was not referred to in the plans.
(c) It may well be that the work carried out to the first-floor roof either did comply with the Building Code (for example the falls in that area were adequate) or it amounted to maintenance or repair using comparable materials, and was work which fell under cl 1 of sch 1 of the Act. That is, no building consent was required. Alternatively, an exemption from obtaining a building consent would have been available under cl 2 of sch 1 of the Act if necessary. Mr Paykel noted that the cost of seeking a building consent might be $25,000–$30,000 for a repair that might cost $500–$600, which he considered disproportionate and inconsistent with the Act. He considered that the infilling of the roof that was required as a result of other non-roof works would also have been exempted if necessary.

(d) I am not persuaded that cl 1(3)(c) of sch 1 precluded reliance on cls 1 and 2 of that schedule. The Trustees have not established that it applies. As the Council submits, there is no or insufficient evidence, photographic or otherwise, to support the submission that the roof had failed as contemplated by cl 1(3)(c) above, or that the Council was or should have been on notice of failings in 2010/2011 such that it should have required full compliance with the Building Code. Mr Flay for the Trustees accepted, although he considered ponding at least at one location was “pretty obvious” when he inspected in 2020/2021, there was no evidence suggesting a failure by the Council to notice ponding (the lack of falls) in 2010. The evidence is that as at 2010 the roof was performing and had done so already for 13 years.

Breach regarding failure to use Z flashings?

Summary as to breach

and had regard to what I have said above about the extent of Council duties in these circumstances.

What is the appropriate measure of damages in relation to the tiling breaches?

Are the wasted costs in 2016 an appropriate measure of damages for the 2011 certification breach?

If the Council had rejected the Code Compliance Certification in 2011 on the basis that the tiling work was defective, then the only reasonable inference is that the works would have been immediately remediated at no cost to the Trustees. Because of Council’s negligence, the opportunity to require the

14 Mr Flay did later say that the contractors’ breach should have been identified earlier, but I have found that the breach was only at certification.

builder to comply with the Council’s requirements in 2011, at the builder’s cost, was not afforded to Dr Linehan.

Are repair costs the appropriate measure of damages for the 2016 consenting breach?

$1.36 million) is based on the alleged 2011 non-balcony breaches and the 2016 balcony breach. I have found against the 2011 non-balcony breaches. The claim for the full cost of repairs is therefore based solely on the Council’s negligent grant of a building consent in 2016 with regard to balcony works only.


15 Johnson v Auckland Council [2013] NZCA 662.

16 As recorded in the Council’s latest submissions.

17 North Shore City Council v Body Corporate 188529 [2010] NZSC 158, [2011] 2 NZLR 289 (Sunset Terraces).

18 Invercargill City Council v Hamlin [1996] UKPC 56; [1996] 1 NZLR 513, [1996] AC 624 (PC).

19 Ruxley Electronics and Construction Ltd v Forsyth [1996] 1 AC 344, [1995] 3 WLR 118.

Court upheld the trial Judge’s finding that the owner was entitled to damages based only on loss of amenity.

If the Council is liable for repair costs how are they assessed?

$594,648.79. The range of costs of the like-for-like scopes is between Mr Cutfield’s estimate of $771,399.30 and Mr White’s estimate of $1,127,970.14. The range of costs for the Concept Plan repairs is between $1,090,509.21 and $1,333,302.96.
of breach, I do not dismiss that possibility. I accept at least that to achieve the basic outcomes required (in this case delivering balconies that comply), other costs may be incurred and recoverable. Indeed, Mr Paykel’s targeted repairs include for example additional sections of replacement cladding. But the Court would need to be satisfied that the additional costs are reasonably necessary.
focussed on delivering a house that is defect-free. That falls well outside the present exercise.

20 Body Corporate 326241 v Auckland Council [2015] NZHC 862.

defendant proposed (with little to support it) what the Court considered to be a makeshift solution with inherent ongoing risks. There is no suggestion by the Council here that the works for which it is responsible should be carried out in anything like a makeshift manner, nor do I consider that to be the case, and the scope has been properly evidenced.
(other than, perhaps, on a very limited basis) and that it is unlikely they would do so. The Trustees say it is imperative that they properly remedy all defects in their property, and that they implement Mr Laurent’s Concept Plan. The cost of implementing that plan, as noted, is estimated by the Trustees at $1.36 million. But the Trustees’ own valuer says that, following that work, the rectified building will still have significant stigma (in large part attributable to their original purchase) and the value of the rectified building (even after the full Concept Plan redesign) will be only $854,000. That is materially less than the claimed repair cost. Ms Whitfield says the Council cannot take the point that the work will not be carried out because Dr Linehan was not cross-examined on it. She says that the Trustees intend to proceed with the Concept Plan and the property has significant sentimental value as evidenced by the substantial sums they have already paid. I note it is doubtful the Trustees intended to pay anything approaching those sums given the estimates in the two building consent applications. But the point is that, as in Ruxley, it is clearly uneconomic to effect the Concept Plan repairs. The Council is not arguing that, as a consequence, the Trustees should be limited to diminution in value, but I agree with the Council, it may be relevant to a pragmatic and fair assessment of the reasonably necessary cost of repairs for which the Council is liable, that it would be unreasonable on the Trustees’ own case to carry out the repairs on the basis claimed by them.

Quantum of “targeted repairs”

location. I also consider it reasonable, as he has allowed, that the scaffolding would not need to be in place for the entire construction period.
$598,610 which I fix as the quantum of the cost of repairs.

Other heads of damages

Stigma

house will be worth materially less than it would have been because of the stigma attached to it and claim that $104,000 of that stigma relates to the two defective works.

Resource consent costs

Removal and storage costs

General damages

Interest

21 Worldwide NZ LLC v NZ Venue and Event Management Ltd [2014] NZSC 108, [2015] 1 NZLR 1 at [23].

Also costs, particularly of building works, are never static. Interest is to apply on damages as assessed.

Contributory negligence

Legal principles

22 Carolyn Sappideen and Prue Vines (eds) Fleming’s The Law of Torts (10th ed, Brookers, Sydney, 2011) at [12.30].

simple cross-suit or to issues of causation. For that reason, I tend towards using the term “fault” rather than negligence. That fully accords with s 3.

(a) Dr Linehan failed to retain an expert weathertightness report he obtained when purchasing the property, or if he did, he did not show it to his builder or to the Council. The extent of that report is not known. At a minimum the report identified problems with water ingress into the walls, particularly around the front stairs and in respect of the easterly wall. The expert’s report may have gone further and for example identified the problem with the deck tiling. In any event the report may have been of assistance to Dr Linehan and his builder and it may also have been possible to gather more information from the writer of the report.

(b) Despite having obtained the report Dr Linehan took no steps in respect of the weathertightness issues until 2010 when there was “a large bulge containing many litres of water protruding down from the ceiling in the garage”. There is no evidence that delay contributed to or exacerbated the damage suffered. However, it does mean that Dr Linehan was facing urgent works where that should not have been necessary. He left himself with no time to conduct appropriate due diligence into the extent of work required and to secure appropriate expert assistance. He embarked instead on a rushed job.
(c) I note at this point Mr Neutze’s submission that Dr Linehan had found a screwdriver hole in the membrane in the easterly wall and determined that water ingress issues were caused by this despite his lack of qualifications to form that view and despite the original report. I consider this largely irrelevant, but it adds to the tapestry of an owner who it seems was avoiding taking steps to fully investigate the condition of his house.

(d) Dr Linehan retained Mr Barber without appropriate due diligence into his qualifications and reliability. He took Mr Barber’s own word as to his expertise. As Mr Neutze said, Dr Linehan engaged Mr Barber on a handshake. I heard no evidence from the insurer, whose involvement was obviously minimal. Clearly Mr Barber was not thorough, compliant or sufficiently expert. Ms Whitfield correctly pointed out that a client is not responsible for ensuring that design or the finished building complies with the Code, referencing Minister of Education v H Construction North Island Ltd.23 That is the responsibility of the professionals they have engaged and the client is reliant on advice given by those professionals. But an owner is still responsible for engaging expertise at an appropriate level especially with a house such as this. In this case Dr Linehan clearly failed to engage a builder who was suitably qualified, thorough or compliant, or to take reasonable steps to do so.

(e) The Council notes that Dr Linehan failed to enter into appropriate contractual arrangements with Mr Barber. I cannot see that this was causative.

(f) Dr Linehan failed to take any steps when he should have known quite quickly that Mr Barber was someone who cut corners. Dr Linehan would have known of this from the outset when Mr Barber carried out significant works without a building consent and was ordered to stop

23 Minister of Education v H Construction North Island Ltd [2018] NZHC 871 at [334].

work. It is likely Dr Linehan would have known the plans were not even available. When Mr Barber finally made application for building consent he estimated costs at a fraction of the final cost. This indicates either a complete lack of preparation or a lack of forthrightness. Again Dr Linehan should have been aware of this. Dr Linehan should also have been concerned, again at an early point, at Mr Barber’s preparedness to direct-fix tiles when he said (at the least) that was not preferable and not allowed by at least some councils. That this was too cavalier an approach for works such as this would have been evident to the reasonable owner.

(g) Further in this regard, Dr Linehan (and his builder) failed to take any account of the only expert he did engage. Dr Linehan had used Ms Simpson as a “technical exercise” to reflect the plans he and Mr Barber had discussed. He says he did not look at those plans. If that is true, he should have done so, or at least inquired of Ms Simpson or Mr Barber what the plans provided for regarding the balcony tiling. Instead, he and Mr Barber ignored the plans at least in that significant respect.

(h) Dr Linehan was intimately involved in the most critical decision, namely the decision in 2011 to fix the tiles and not to suspend them. I consider this particularly relevant. It is clear that Dr Linehan knew at all material times at least that other councils required a suspended tiling solution and that this was the preferred solution (rather than direct fixing). He was or should have been aware of the risks. Having been approached by Mr Barber to make a decision on this, I consider a reasonable owner could have inquired more fully and that even the briefest of inquiries would likely have caused him to conclude that direct fixing was not only ill-advised but in fact contrary to the Building Code, contrary to the consent, and contrary to his own plans. Again, I am not making any findings as to actionable negligence. I am considering “fault” solely for the purposes of s 3.
(i) Dr Linehan failed to obtain expert advice that a reasonable owner would have obtained, and followed, in the circumstances. An owner in Dr Linehan’s circumstances with a valuable property, long suffering from weathertightness issues, must bear a degree of responsibility for ensuring the issues are understood, appropriate experts engaged, and their advice/reports followed. He recognised the need to engage experts before buying the house and again for purposes of this litigation. It is not fanciful to think that with a fraction of the expertise he engaged for this case before and during the 2011 building project, Dr Linehan would not have been in Court.

(j) Especially relevant is the fact that, despite the sorry history of repairs, Dr Linehan continued in 2015/2016 to use and to have almost complete faith in Mr Barber and to persist with a tiling solution that had failed by that stage twice, once in 2011 and again in 2014. Interestingly Dr Linehan still did not inquire of Ms Simpson and in fact engaged a different draftsperson. At this point it must have been even clearer that Dr Linehan needed to engage consultants with special expertise in remediation. I am not persuaded that Mr Brunton provided that assistance. It was not good enough, particularly given the terms of the contract with Mr Barber, under which he was liable for all subcontractors, for Dr Linehan to rely on Mr Barber, whether Mr Barber attributed blame to the tiler or not. The Trustees should have sought expert advice before taking any further steps.
be expected to have extended to more thorough investigation, to more thorough design solutions, suitably expert builders and contractors and/or to supervision. Dr Linehan also personally made the decision to affix the tiles in 2011 even though he had been told it was not the preferred option. If Dr Linehan had taken appropriate advice and exercised more care in decisions about the works, it is likely that the 2011 building consent would have been complied with and this action would not have arisen. That was even more the case in 2016.

Judgment


(a) 50 percent of the cost of increased targeted repairs of $598,610, being
$299,305.

(b) 50 per cent of wasted costs of $197,528, being $98,764.

(c) 50 per cent of general damages of $15,000 being $7,500.

(d) Interest assessed under the Judicature Act at five per cent per annum from the date of Mr White’s assessment in the case of (a) and from the date the costs were incurred in the case of (b), down to the date of judgment.








Hinton J


NZLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2021/3234.html