NZLII Home | Databases | WorldLII | Search | Feedback

High Court of New Zealand Decisions

You are here:  NZLII >> Databases >> High Court of New Zealand Decisions >> 2023 >> [2023] NZHC 2715

Database Search | Name Search | Recent Decisions | Noteup | LawCite | Download | Help

Northlake Investments Limited v Civil Construction Limited [2023] NZHC 2715 (28 September 2023)

Last Updated: 5 October 2023

IN THE HIGH COURT OF NEW ZEALAND INVERCARGILL REGISTRY
I TE KŌTI MATUA O AOTEAROA WAIHŌPAI ROHE
CIV-2022-425-79
[2023] NZHC 2715
BETWEEN
NORTHLAKE INVESTMENTS LIMITED
Plaintiff
AND
CIVIL CONSTRUCTION LIMITED
Defendant
Hearing:
28 August 2023
Appearances:
J D McBride and A W McDonald for Plaintiff B M Cash and V Bortsova for Defendant
Judgment:
28 September 2023

JUDGMENT OF ASSOCIATE JUDGE PAULSEN

This judgment was delivered by me on 28 September 2023 at 3.00 pm pursuant to Rule 11.5 of the High Court Rules

Registrar/Deputy Registrar Date:

NORTHLAKE INVESTMENTS LTD v CIVIL CONSTRUCTION LTD [2023] NZHC 2715 [28 September 2023]

Table of Contents

Para No

Introduction
What happened

The contracts
The Covid Claim
The Stage 12 Claim
The adjudication
The final payment claim
Summary judgment principles – Northlake
Northlake’s pleading
Issue one – Was Civil required to dispute the engineer’s decisions under the dispute resolution provisions of NZS 3910:2013?
The Stage 12 Claim
The Covid Claim
Conclusion on issue one
Issue two – If Civil was required to dispute the engineer’s decisions, did it do so in the manner required?

Northlake’s position
Civil’s position
My analysis
Conclusion on issue two
Issue three – Was the adjudicator’s determination binding?
The Act
Northlake’s alternative positions
Conclusion of issue three
Issue four – Does Northlake have a claim for money had and received?
Conclusion on issue four
Summary judgment application and strike out principles – Civil
Issue five – Can the adjudicator’s determination now be challenged by Northlake?
Result

Introduction

(a) Was Civil required to dispute the engineer’s decisions under cl 13.1.1 of NZS 3910:2013?

(b) If so, did it do so in the manner required?

(c) Was the adjudicator’s determination binding on the parties?

(d) Does Northlake have a cause of action for money had and received?

(e) Can the adjudicator’s determination now be challenged by Northlake?

What happened

The contracts

The Covid Claim

  1. SRG Global Remediation Services (NZ) Ltd v Body Corporate 197281 [2022] NZCA 518 at [10]– [12].

Within 1 Month of the receipt of notice under 9.2.2 or 9.2.3 or as soon as practicable thereafter, the Engineer shall by notice in writing either confirm that the instruction or matter involves a Variation or disallow a Variation giving reasons for doing so. Unless within that time the Engineer issues a notice in writing disallowing a Variation, the instruction or matter shall be treated as a Variation.

2 Clause 5.11.10 of NZS 3910: 2013.

  1. Although Mr Cash suggested that Civil might wish to take the point that the Covid Claim could not be disallowed because the engineer had failed to issue a notice in writing within one month, there was correspondence from Civil's lawyers to the engineer dated 26 August 2020 stating that Civil took no issue with the engineer requiring more time to assess the claim.

The Stage 12 Claim

The value, if any, of each Variation shall as far as possible be determined by agreement between the Contractor and the Engineer. Failing agreement, the value shall be determined by the Engineer in accordance with 9.3. The value of each Variation when determined shall be confirmed or notified to the Contractor in writing. Where the value as determined differs from any value proposed by the Contractor, the notice shall include the Engineer’s reasons for his or her valuation.

in full and final settlement if paid within three working days. The payment was not made.

The adjudication

[The adjudicator’s] determination takes precedence over those decisions and valuations, until such time as the balance of the contractual dispute resolution process has been concluded. That is if either party embarks on that process. They have not.

The final payment claim

Summary judgment principles — Northlake

(1) The court may give judgment against a defendant if the plaintiff satisfies the court that the defendant has no defence to a cause of action in the statement of claim or to a particular part of any such cause of action.

(a) Commonsense, flexibility and a sense of justice are required.

(b) The onus is on the plaintiff seeking summary judgment to show that there is no arguable defence. The Court must be left without any real doubt or uncertainty on the matter.

4 Mount Grey Downs Ltd v Pinot Properties Ltd [2018] NZHC 3094 at [12] (footnotes omitted).

(c) The Court will not hesitate to decide questions of law where appropriate.

(d) The Court will not attempt to resolve genuine conflicts of evidence or to assess the credibility of statements in affidavits.

(e) In determining whether there is a genuine and relevant conflict of facts, the Court is entitled to examine and reject spurious defences or plainly contrived factual conflicts. It is not required to accept uncritically every statement put before it, however equivocal, imprecise, inconsistent with undisputed contemporary documents or other statements, or inherently improbable.

(f) In assessing a defence the Court will look for appropriate particulars and a reasonable level of detailed substantiation – the defendant is under an obligation to lay a proper foundation for the defence in the affidavits filed in support of the Notice of Opposition.

(g) In weighing these matters, the Court will take a robust approach and enter judgment even where there may be differences on certain factual matters if the lack of a tenable defence is plain on the material before the Court.

(h) The need for judicial caution in summary judgment applications has to be balanced with the appropriateness of a robust and realistic judicial attitude when that is called for by the particular facts of the case. Where a last-minute, unsubstantiated defence is raised and an adjournment would be required, a robust approach may be required for the protection of the integrity of the summary judgment process.

(i) Once the Court is satisfied that there is no defence, the Court retains a discretion to refuse summary judgment but does so in the context of the general purpose of the High Court Rules which provide for the just, speedy and inexpensive determination of proceedings.

Northlake’s pleading

(a) the engineer disallowed the Covid Claim and the Stage 12 Claim pursuant to the decisions and/or certifications dated 6 October 2020 (in respect of the Covid Claim) and 19 July 2021 (in respect of the Stage 12 Claim);

(b) Civil did not refer the engineer’s decisions to the engineer under cl 13.2.1 of NZS 3910:2013 or to adjudication under the Act within three months of the decisions being given;

(c) the engineer’s decisions are therefore final and binding;

(d) the adjudication under the Act was commenced outside the contractual time limits for resolving claims and was an abuse of process;

(e) the adjudicator’s determination has no effect on the engineer’s decisions;

(f) Northlake paid sums found to be owing by the adjudicator in respect of the Covid Claim and Stage 12 Claims in the amount of $591,040; and

(g) Civil is in receipt of money paid to it by Northlake to which it has no entitlement.

Issue one — Was Civil required to dispute the engineer’s decisions under the dispute resolution provisions of NZS 3910:2013?

13.1.1

No decision, valuation, or certificate of the Engineer shall be questioned or challenged more than 3 Months after it has been given or more than

1 Month after the date on which any relevant Adjudicator’s Determination is given to the parties, whichever is the later, unless notice has been given to the Engineer within that time. Every decision, valuation, or certificate of the Engineer shall be final and binding if neither party has referred it to the Engineer under 13.2.1 or to Adjudication within 3 Months after it has been given, unless notice has been given to the Engineer within that time. This subclause 13.1.1 shall not apply to a Progress Payment Schedule.

13.1.2

Every dispute or difference concerning the Contract which is not precluded by the provisions of 12.4, 12.6, 13.1.1 or 13.2. shall be dealt with under the following provisions of this Section.

13.2 Engineer’s Review 13.2.1

...

13.2.4

Every dispute or difference under 13.1.2 shall be referred to the Engineer not later than 1 Month after the provision of the Final Payment Schedule under 12.5.1, 12.5.3, or 12.5.4 or more than 1 Month after the date on which any relevant Adjudicator’s Determination is given to the parties, whichever is the later. The Engineer shall give his or her decision in writing. Except in the case of a decision under 13.2.4 the Engineer may correct or modify his or her decision by a subsequent decision in writing.

Unless the dispute or any question arising in connection with it has been referred under 13.2.3 and is awaiting a recommendation from the agreed expert, the Engineer may, at any time, in respect of any dispute or difference under 13.2.1 give a decision (in this Section called a formal decision) which states expressly that it is given under this subclause 13.2.4. The Engineer shall give a formal decision on the matter within 20 Working Days of receiving notice in writing from the Principal or the Contractor requiring him or her to give a formal decision and expressly referring to this subclause 13.2.4. Upon making a formal decision the Engineer shall forthwith send copies of it to both the Principal and the Contractor. The Engineer’s formal decision shall, subject to 13.3 and 13.4 or any Adjudication proceedings, be final and binding.

The Stage 12 Claim

The Covid Claim

5 Construction Contracts Act 2002, s 12.

For that reason, the dispute resolution machinery set out in section 13 of NZS 3910 does not apply to disputes over progress payment schedules. If the contractor is unhappy with a progress payment schedule and wants to access additional cashflow, its recourse is to refer the dispute to an adjudication under the [Act] to provide it with immediate cashflow, with its final account to be settled at the conclusion of the contract, resolving all disputed items.

(footnote omitted)

Conclusion on issue one

Issue two — If Civil was required to dispute the engineer’s decisions, did it do so in the manner required?

Northlake’s position

Civil did not otherwise escalate the dispute by way of a request for an engineer’s review of the decision under cl 13.2.1 or an adjudication within three months.

(a) notice of dispute to the engineer must be given, within either:

(i) three months of the decision, valuation, or certificate of the Engineer being given; or

(ii) one Month after the date on which any relevant Adjudicator’s Determination is given to the parties;

whichever is the later, and

(b) the dispute must be referred to either:

(i) an engineer’s review under cl 13.2.1; or

(ii) an [adjudication under the Act],

and notice of such given to the Engineer within three months of the relevant decision, valuation, or certificate of the Engineer.

(emphasis added)

Civil’s position

a No decision, valuation, or certificate of the Engineer b shall be questioned or challenged more than

  1. 3 Months after it has been given or
  1. more than 1 Month after the date on which any relevant Adjudicator’s Determination is given to the parties,

whichever is the later,

c unless notice has been given to the Engineer within that time.

a Every decision, valuation, or certificate of the Engineer b shall be final and binding if neither party has

i referred it to the Engineer under 13.2.1 or ii to Adjudication

within 3 Months after it has been given,

c unless notice has been given to the Engineer within that time.

and binding if the other two avenues for dispute resolution (under cl 13.2.1 or adjudication) are not pursued. It says, alongside referring a decision to the engineer under cl 13.2.1 or to adjudication within three months, giving notice to the engineer serves as a means to avoid the decision becoming final and binding.

  1. a party who wishes to dispute the decision of the Engineer must give notice of a dispute to the Engineer within 3 months of the decision (first

sentence);

  1. unless such a notice of dispute is given, the party must refer the dispute to the Engineer under 13.2.1 or to Adjudication within that 3 month period to avoid the decision becoming final and binding ( second

sentence).

My analysis

  1. Firm PI 1 Ltd v Zurich Australian Insurance Ltd [2014] NZSC 147, [2015] 1 NZLR 432 at [60], citing Investors Compensation Scheme Ltd v West Bromwich Building Society [1997] UKHL 28; [1998] 1 WLR 896 (HL) at 912, per Lord Hoffmann.

7 At [61].

8 At [63].

  1. Zurich Australian Insurance Ltd v Cognition Education Ltd [2014] NZSC 188, [2015] 1 NZLR 383 at [37], citing International Ore & Fertiliser Corp v East Coast Fertiliser Co Ltd [1986] NZCA 115; [1987] 1 NZLR 9 (CA) at 16.
interpretation, but I accept that given the nature of those publications they do not advance matters. I note that the guidelines attached to NZS 3910:2013 also support Northlake’s position, but they do not form part of the contract and neither counsel referred to them.

Conclusion on issue two

10 Construction Contracts Act, s 3(b).

Issue three — Was the adjudicator’s determination binding?

The Act

(a) to facilitate regular and timely payments between the parties to a construction contract; and

(b) to provide for the speedy resolution of disputes arising under a construction contract; and

(c) to provide remedies for the recovery of payments under a construction contract.

(a) must allow for any amount paid to a party to the contract under, or for the purposes of, this Part in any order or award the court, tribunal, or a member makes in those proceedings; and

(b) may make any orders that the court, tribunal or member considers appropriate, having regard to any steps taken by a party to the contract in good faith and in reliance on an adjudicator’s determination under this Part (including an order requiring a party to the contract to pay for goods and services supplied by another party to that contract in good faith and in reliance on an adjudicator’s determination).

(2) The consequences are that the party who is owed the amount (party A) may do all or any of the following:

(a) recover from the party who is liable to make the payment (party B), as a debt due to party A, in any court,—
(i) the unpaid portion of the amount; and

(ii) the actual and reasonable costs of recovery ordered against party B by that court:

...

(c) apply for the adjudicator’s determination to be enforced by entry as a judgment in accordance with subpart 2 of Part 4.

11 Construction Contracts Act, s 45(d).

12 Body Corporate 200012 v Keene [2017] NZHC 2953, [2018] NZAR 120 at [81].

  1. At [82], citing Benfield Construction Ltd v Trudson (Hatton) Ltd [2008] EWHC 2333 (TCC) at [34].
(a) The parties are bound by the decision of an adjudicator on a dispute or difference until it is finally determined by court or arbitration proceedings or by agreement made subsequently by the parties.

[15] Section 12 of the [Act] prohibits any contracting out from the provisions of that Act. I cannot see, therefore, how the more restrictive time frames for bringing a dispute under cl 13 can be superimposed on DHC’s rights under the [Act]. To allow that to occur would be in effect to allow a contracting out of that Act’s provisions insofar as they impose time limits for bringing a proceeding under that Act. In my view there is a sound argument that cl 13 does not detract from the other rights and legal remedies that DHC may have either under the [Act] or the law of contract.

... subordinates the effect of an arbitration provision where a claim is made under the Act. As a result, the statute prevails notwithstanding an agreement to arbitrate.

14 DHC Assets Ltd v Toon [2016] NZHC 140.

15 Willis Trust Company Ltd v Green HC Auckland, CIV-2006-404-809, 25 May 2006.

16 At [30].

17 At [34].

18 G K Shaw Ltd v Green [2023] NZHC 605.

judicial review of that decision. In the High Court, Isac J dismissed the application for review. While it was not the basis for his decision, the Judge considered that in circumstances where the applicant could and should have raised all its claims the first time around, it was an abuse of process to bring an “almost identical claim dressed up in different legal regalia”.19

62 It is not correct that ... [a contract administrator] who in performing his contractual function comes to a determination negates a statutory right to retain an adjudicated amount. The adjudicator’s determination remains, and brings payment of the adjudicated amount, but that is interim and subject to a different position being established in relation to payment for the relevant work or related goods and services, contractually or in proceedings. If in civil proceedings, it is decided that the contractor was entitled to $10 or $30, rather than the $20 determined by the adjudicator, that does not undo the adjudicator’s determination. It has done its work in ensuring “prompt interim progress payment on account, pending final determination of all disputes”... So also if in the manner earlier described, the contractual mechanisms result in a contractual obligation on the principal to pay the contractor or the contractor to pay the principal. The contractor’s right under the Act is to receive the adjudicated amount, but subject to final determination, and if the final determination involves the [contract administrator] determining that the contractor was entitled to $10 or

$30, rather than $20 determined by the adjudicator, the [contract administrator] is not negating the contractor’s statutory right.

(citation omitted)

Northlake’s alternative positions

19 At [45].

20 John Holland Pty Ltd v Roads and Traffic Authority of New South Wales [2007] NSWCA 140.

other dispute resolution procedures such as court proceedings, arbitration or mediation. It is not concerned with engineer’s decisions as contract administrators.

Conclusion of issue three

Issue four — Does Northlake have a claim for money had and received?

21 Napier v Torbay Holdings Ltd [2016] NZCA 608, [2017] NZAR 108 at [21].

22 National Bank of New Zealand Ltd v Waitaki International Processing (NI) Ltd [1997] 1 NZLR 724 at 728 and National Bank of New Zealand Ltd v Waitaki International Processing (NI) Ltd [1999] 2 NZLR 211 (CA) at 215.

concerned claims within established categories where the law recognises a plaintiff’s right to recovery, for example payments made under a mistake.

Although, as stated, unjust enrichment can be regarded as the rationale of (albeit not necessarily the test for) a number of restitutionary claims, it is not a prerequisite of the action for money had and received.

Money had and received and unjust enrichment are not synonyms to be used interchangeably. One may describe a species of actions falling within the law of obligations, but is not, at least yet, a cause of action. The other is a cause of action, with its own history and precedents, and even if it is now justified by the concept of unjust enrichment, it is a long way from being the cause of action that now exists in England and Wales. The two should not be confused.

A claimant must be able to point to a ground of recovery that is established by past authority, or at least is justifiable by a process of principled analogical reasoning from past authority. There is in English law “no general rule giving the plaintiff a right of recovery from a defendant who has been unjustly enriched at the plaintiff’s expense”, and the courts’ jurisdiction to order restitution on the ground of unjust enrichment is subject “to the binding authority of previous decisions”: they do not have “a discretionary power to order repayment whenever it seems ... just and equitable to do so”.

23 Martin v Pont [1993] 3 NZLR 25, 30.

  1. Sean McAnally “Money had and received: we’re sorry, will you have us back?” [2023] NZLJ 258.

25 Deutsche Morgan Grenfell Group Plc v IRC [2006] UKHL 49, [2007] 1 AC 558 at [21].

  1. Charles Mitchell, Paul Mitchell and Stephen Watterson Goff & Jones on Unjust Enrichment (10th ed, Sweet & Maxwell, London, 2022) at [1-30] (footnotes omitted).
answered on the basis the payee had every right to receive it.27 While it appears this principle will not apply in circumstances where money was paid under a judgment that was void, it will apply even if there is reason to believe that the court has made a mistake.28

Conclusion on issue four

Summary judgment application and strike out principles — Civil

The court may give judgment against a plaintiff if the defendant satisfies the court that none of the causes of action in the plaintiff’s statement of claim can succeed.

27 At [2-32]—[2-36], citing Marriott v Hampton [1775-1802] All ER Rep 631 (KB); Wilson v Ray [1839] EngR 647; (1839) 113 ER 32; and Clydesdale Bank Ltd v Schröder & Co [1912] UKLawRpKQB 80; [1913] 2 KB 1. See also P Twist, J Palmer and Marcus Pawson Laws of New Zealand, Restitution (online ed) at [10] and n 6.

28 Mitchell, Mitchell and Watterson, above n 26, at [2-38] and [2-41].

Although [the predecessor to r 12.2] refers to the causes of action “in the plaintiff's statement of claim”, [the predecessor to r 15.1] (which permits the Court to strike out a cause of action) similarly is based upon “the pleading”. Under [r 15.1] the Court does not strike out pleadings where a defect can be cured by amendment which the party is willing to make. Similarly, the residual discretion of the Court under [r 12.2] to refuse summary judgment would be properly invoked to avoid the oppression which would otherwise result if an application by a defendant for summary judgment would preempt a plaintiff exercising the right to amend the pleadings ... Indeed, use of the discretion to enable amendment is arguably more necessary in the interests of justice in the case of summary judgment than in the case of strike-out because summary judgment results in issue estoppel.

15.1 Dismissing or staying all or part of proceeding

(1) The court may strike out all or part of a pleading if it—

(a) discloses no reasonably arguable cause of action, defence, or case appropriate to the nature of the pleading; or

(b) is likely to cause prejudice or delay; or

(c) is frivolous or vexatious; or

(d) is otherwise an abuse of the process of the court.

(2) If the court strikes out a statement of claim or a counterclaim under subclause (1), it may by the same or a subsequent order dismiss the proceeding or the counterclaim.

(3) Instead of striking out all or part of a pleading under subclause (1), the court may stay all or part of the proceeding on such conditions as are considered just.

(4) This rule does not affect the court’s inherent jurisdiction.

29 Westpac Banking Corp v M M Kembla New Zealand Ltd [2000] NZCA 319; [2001] 2 NZLR 298 (CA) at [66]; and

Attorney-General v Jones [2003] UKPC 48, [2004] 1 NZLR 433 at [5].

30 At [66].

The Court is entitled to receive affidavit evidence on a striking-out application, and will do so in a proper case. It will not attempt to resolve genuinely disputed issues of fact and therefore will generally limit evidence to that which is undisputed. Normally it will not consider evidence inconsistent with the pleading, for a striking-out application is dealt with on the footing that the pleaded facts can be proved ... But there may be a case where an essential factual allegation is so demonstrably contrary to indisputable fact that the matter ought not to be allowed to proceed further.

Issue five — Can the adjudicator’s determination now be challenged by Northlake?

31 Attorney-General v McVeagh [1995] 1 NZLR 558 (CA) at 566 (citation omitted).

as Northlake did not give notice of its intention to dispute the adjudication determination within one month or at all, Northlake cannot now challenge it.

Result

O G Paulsen Associate Judge

Solicitors:

LeeSalmonLong, Auckland

Dentons Kensington Swan, Wellington


NZLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2023/2715.html