You are here:
NZLII >>
Databases >>
High Court of New Zealand Decisions >>
2023 >>
[2023] NZHC 2715
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Northlake Investments Limited v Civil Construction Limited [2023] NZHC 2715 (28 September 2023)
Last Updated: 5 October 2023
|
IN THE HIGH COURT OF NEW ZEALAND INVERCARGILL REGISTRY
I TE KŌTI MATUA O AOTEAROA WAIHŌPAI ROHE
|
|
|
|
BETWEEN
|
NORTHLAKE INVESTMENTS LIMITED
Plaintiff
|
|
AND
|
CIVIL CONSTRUCTION LIMITED
Defendant
|
|
Hearing:
|
28 August 2023
|
|
Appearances:
|
J D McBride and A W McDonald for Plaintiff B M Cash and V Bortsova for
Defendant
|
|
Judgment:
|
28 September 2023
|
JUDGMENT OF ASSOCIATE JUDGE PAULSEN
This judgment was delivered by me on 28 September
2023 at 3.00 pm pursuant to Rule 11.5 of the High Court Rules
Registrar/Deputy Registrar Date:
NORTHLAKE INVESTMENTS LTD v CIVIL CONSTRUCTION LTD [2023] NZHC 2715 [28
September 2023]
Table of Contents
Para No
|
Introduction
|
|
|
What happened
|
|
|
The contracts
|
|
|
The Covid Claim
|
|
|
The Stage 12 Claim
|
|
|
The adjudication
|
|
|
The final payment claim
|
|
|
Summary judgment principles – Northlake
|
|
|
Northlake’s pleading
|
|
|
Issue one – Was Civil required to dispute the engineer’s
decisions under the dispute resolution provisions of NZS 3910:2013?
|
|
|
The Stage 12 Claim
|
|
|
The Covid Claim
|
|
|
Conclusion on issue one
|
|
|
Issue two – If Civil was required to dispute the engineer’s
decisions, did it do so in the manner required?
|
|
|
Northlake’s position
|
|
|
Civil’s position
|
|
|
My analysis
|
|
|
Conclusion on issue two
|
|
|
Issue three – Was the adjudicator’s determination
binding?
|
|
|
The Act
|
|
|
Northlake’s alternative positions
|
|
|
Conclusion of issue three
|
|
|
Issue four – Does Northlake have a claim for money had and
received?
|
|
|
Conclusion on issue four
|
|
|
Summary judgment application and strike out principles –
Civil
|
|
|
Issue five – Can the adjudicator’s determination now be
challenged by Northlake?
|
|
|
Result
|
|
Introduction
- [1] Northlake
Investments Ltd (Northlake) and Civil Construction Ltd (Civil) entered into
construction contracts for the performance
of works by Civil at
Northlake’s development at Wanaka. The engineer to the contracts
disallowed certain payment claims by
Civil, which Civil referred to adjudication
under the Construction Contracts Act 2002 (the Act). An adjudicator issued a
determination
requiring Northlake to make payments to Civil in respect of the
disputed claims. Northlake made payment whilst disputing its liability
to do
so.
- [2] Northlake
now seeks summary judgment against Civil to recover, as money had and received,
the $591,040 it paid to Civil in respect
to two of the disputed claims. It
argues the adjudicator’s determination had “no effect” upon
decisions made by
the engineer disallowing Civil’s claims, and the
decisions are “final and binding” because Civil did not refer
them
to the engineer or to adjudication as required by the conditions of contract
within three months of the decisions being given.
- [3] Civil
resists summary judgment and makes its own application for summary judgment and
to strike out Northlake’s claim. Civil
argues the engineer’s
decisions never became final and binding because it was not required to dispute
them, but that it did
so in time in any event. Even if that was not the case,
Civil says it was entitled to refer the disputes to adjudication, the
adjudication
determination was binding and there is no basis for Northlake to
seek recovery of the amount paid pursuant to the adjudication award
as money had
and received. Civil also argues Northlake has now lost the right to dispute the
adjudicator’s determination in
subsequent proceedings because it failed to
give notice of its intention to do so in accordance with the conditions of
contract.
- [4] The case
raises issues as to the legal basis for an action for money had and received,
the interpretation of dispute resolution
provisions in cl 13 of New Zealand
Standard Conditions of Contract for Building and Civil Engineering Construction
(NZS 3910:2013),
and the relationship between those provisions and the dispute
resolution procedures in pt 3 of the Act.
- [5] More
specifically, the principal issues that were raised on the applications before
me are as follows:
(a) Was Civil required to dispute the engineer’s decisions under cl 13.1.1
of NZS 3910:2013?
(b) If so, did it do so in the manner required?
(c) Was the adjudicator’s determination binding on the parties?
(d) Does Northlake have a cause of action for money had and received?
(e) Can the adjudicator’s determination now be challenged by Northlake?
- [6] It appears
to me that the applications turn on whether, notwithstanding the
engineer’s decisions, Civil was entitled to
refer the disputes concerning
the Covid Claim and the Stage 12 Claim to adjudication under the Act, and the
adjudicator’s determination
is binding. Notwithstanding that, I have
addressed the issues as I understood counsel advanced them.
What happened
The contracts
- [7] Northlake
is undertaking a large residential land and mixed-use development close to the
Wanaka town centre. It engaged Civil
to undertake bulk earthworks and other
related civil works in respect of which the parties entered into several
contracts.
- [8] The relevant
contracts for present purposes are dated 15 August 2018 (the Bulk Works
Contract) and 17 July 2019 (the Civil Works
Contract). Both contracts included
NZS 3910:2013.
- [9] NZS
3910:2013 provides for an adaption of the payment regime contained in the
Act.1 Under it, there are provisional payment schedules issued by the
engineer in response to payment claims submitted by the contractor.
Civil could
submit payment claims for work conducted during periods of not less than one
month. The engineer, on behalf of Northlake,
was to issue a provisional progress
payment schedule. Northlake was able to notify the engineer in writing of any
amendments or deductions
it intended to make from the sum certified by him. In
the absence of any such notification, the provisional progress payment schedule
would become the final progress payment schedule and become payable by Northlake
to Civil.
- [10] NZS
3910:2013 has separate provisions dealing with the issue of final payment claims
and final payment schedules. The submission
of the final payment claim by Civil
is conclusive evidence that it had no other outstanding claims against
Northlake, except for
any item which had been referred to arbitration or to
adjudication. Upon issue of the final payment schedule, Northlake ceased to
be
liable to Civil in respect of any of its obligations under the contracts, except
in limited respects, including scheduled amounts
shown as payable on the final
payment schedule or any prior payment schedule but unpaid, and monies which had
or became payable under
cl 13, which deals with the resolution of certain
disputes. I set out the most relevant provisions in cl 13 later in this
judgment.
The Covid Claim
- [11] On
6 April 2020, Civil issued a notice to the engineer requesting that he suspend
the Civil Works Contract effective from 26
March 2020 on the basis that the
COVID-19 Level 4 lockdown restrictions necessitated the suspension.
- [12] The
engineer responded on 27 May 2020, that he would not suspend the contract and
recommended discussions between Civil and Northlake
to agree a managed
suspension of works and the consequences arising from that.
- SRG
Global Remediation Services (NZ) Ltd v Body Corporate 197281 [2022] NZCA 518
at [10]– [12].
- [13] On 31 July
2020, Civil issued its payment claim 11 to the engineer, which included costs of
complying with the Covid-19 lockdowns
(the Covid Claim). It said it was entitled
to make the claim as a deemed variation under the change in law provision in NZS
3910:20132 and also sought an extension of time due to the “net
effect of the COVID-19–Variation Claim”.
- [14] In a notice
to the engineer dated 5 August 2020, Civil asserted that it had provided all
information necessary for the engineer
to fairly assess payment claim 11 and
awaited the engineer’s progress payment schedule which, it noted, was due
on 11 August
2020.
- [15] On 11
August 2020, the engineer advised Civil that he had not yet made a decision on
the Covid Claim but would not be approving
any amount in the then current
payment claim. That same day he issued provisional progress payment schedule 11
deducting all amounts
claimed in relation to the Covid Claim.
- [16] The
parties’ respective lawyers corresponded with the engineer about the Covid
Claim, and he took his own legal advice.
On 6 October 2020, the engineer advised
that, as required by cl 9.2.4, the Covid Claim would be disallowed. That was a
reference
to cl 9.2.4 of NZS 3910:2013, which
provides:3
Within 1 Month of the receipt of notice under
9.2.2 or 9.2.3 or as soon as practicable thereafter, the Engineer shall by
notice in
writing either confirm that the instruction or matter involves a
Variation or disallow a Variation giving reasons for doing so. Unless
within
that time the Engineer issues a notice in writing disallowing a Variation, the
instruction or matter shall be treated as a
Variation.
- [17] On 10
October 2020, Civil notified the engineer that it disagreed with his decision on
the Covid Claim. The email stated it
was notice to the engineer under cl
13.1.1 of the contract and “we disagree with your decision to reject our
variation claim
and the basis for doing so entirely”.
2 Clause 5.11.10 of NZS 3910: 2013.
- Although
Mr Cash suggested that Civil might wish to take the point that the Covid Claim
could not be disallowed because the engineer
had failed to issue a notice in
writing within one month, there was correspondence from Civil's lawyers to the
engineer dated 26
August 2020 stating that Civil took no issue with the engineer
requiring more time to assess the claim.
- [18] Neither
party engaged further with the dispute resolution procedure under cl 13 of the
contract, but Civil continued to include
the Covid Claim in subsequent payment
claims, and the engineer continued to deduct those amounts in the progress
payment schedules.
The Stage 12 Claim
- [19] The
works under the Civil Works Contract included six separable portions including
Portion F, which referred to Stage 12 of the
development comprising 39
lots.
- [20] On 24 April
2020, the engineer advised Civil that the works in Portion F would no longer
proceed.
- [21] Civil
issued payment claim 1 on 24 February 2021 for preparatory works prior to Stage
12 being removed from the contract. The
amount claimed was $19,764 excluding
GST.
- [22] The
engineer sought further information from Civil in relation to the Stage 12
Claim but did not issue a progress payment schedule
in response to Civil’s
payment claim.
- [23] On 19 July
2021, the engineer advised Civil he had valued the Stage 12 Claim at $8,859 plus
GST but said Northlake asked that
Civil invoice it directly for this sum rather
than process it as a variation to the contract. It appears (although it is not
expressly
stated) the engineer valued the variation claimed under cl 9.3.4
of NZS 3910:2013, which provides:
The value, if any, of each Variation shall as far as possible be determined
by agreement between the Contractor and the Engineer.
Failing agreement, the
value shall be determined by the Engineer in accordance with 9.3. The value of
each Variation when determined
shall be confirmed or notified to the Contractor
in writing. Where the value as determined differs from any value proposed by the
Contractor, the notice shall include the Engineer’s reasons for his or her
valuation.
- [24] On 10
September 2021, Civil advised the engineer it disagreed with his decision in
relation to the Stage 12 Claim but said it
would accept the $8,859 plus
GST
in full and final settlement if paid within three working days. The payment was
not made.
The adjudication
- [25] On
28 March 2022, Civil referred the Covid Claim and the Stage 12 Claim (and other
claims also) to adjudication under ss 25 and
28 of the Act. Northlake had legal
representation and participated in the adjudication.
- [26] The
adjudicator issued his determination on 11 July 2022 and required Northlake to
pay Civil $17,718 (plus GST) with interest
of $3,284 in respect to the Stage 12
Claim, and $471,267 (plus GST) in respect to the Covid Claim.
- [27] Civil
initiated enforcement action to recover the amounts payable under the
adjudicator’s determination, following which
Northlake paid the sums in
full on 28 July 2022. On that date, Northlake’s lawyers wrote to
Civil’s lawyers stating
that Northlake did not accept it had any liability
to Civil and had instructed them to initiate a claim to have the dispute
determined
in substance. They also advised that while Northlake was
“obliged under the Construction Contracts Act to satisfy the interim
determination”, upon payment it would become a creditor of Civil in the
amounts paid.
- [28] On 9 August
2022, Northlake issued a letter to Civil that the disputes were to be referred
to arbitration under cl 13.4.2 of
NZS 3910:2013.
- [29] On 12
August 2022, Civil’s lawyers pointed out that no formal decision had been
issued by the engineer under 13.2.4, which
was a precondition to referring any
dispute to arbitration.
- [30] On 30
August 2022, Northlake’s solicitors asserted the engineer’s
decisions of 6 October 2020 (in respect to the
Covid Claim) and 19 July 2021 (in
respect of the Stage 12 Claim) were final and binding as Civil had not taken
appropriate steps
to challenge them and these decisions “cannot be
overruled by belated referrals to adjudication”. Northlake demanded
repayment of amounts paid in compliance with the adjudicator’s
determination by 6 September 2022, failing which it would file
High Court
proceedings to recover its “overpayment”.
- [31] On 2
September 2022, Civil’s lawyers disputed the demand, noting that under s
60 of the Act the determination of the adjudicator
was binding. The position
adopted by Northlake was, they asserted, an attempt to elevate the contracts
above the statutory determination
process, thereby offending s 12 of the Act
(which prevents contracting out of the Act’s provisions). They said, while
the engineer
made decisions and valuations which Civil disputed:
[The adjudicator’s] determination takes precedence over those decisions
and valuations, until such time as the balance of the
contractual dispute
resolution process has been concluded. That is if either party embarks on that
process. They have not.
The final payment claim
- [32] For
completeness, on 13 June 2022 Civil issued a final payment claim which included
the Covid Claim and the Stage 12 Claim. The
engineer issued a provisional final
payment schedule on 17 June 2022. He did not certify either the Covid Claim or
the Stage 12 Claim,
as he said both were under adjudication.
Summary judgment principles — Northlake
- [33] Northlake’s
application for summary judgment is made under r 12.2(1) of the High Court Rules
2016 which reads as follows:
(1) The court may give judgment against a defendant if the plaintiff
satisfies the court that the defendant has no defence to a cause
of action in
the statement of claim or to a particular part of any such cause of action.
- [34] The
principles that apply to a plaintiff’s summary judgment applications are
well-known and summarised by Associate Judge
Osborne in Mount Grey Downs Ltd
v Pinot Properties Ltd as follows:4
(a) Commonsense, flexibility and a sense of justice are required.
(b) The onus is on the plaintiff seeking summary judgment to show that there is
no arguable defence. The Court must be left without
any real doubt or
uncertainty on the matter.
4 Mount Grey Downs Ltd v Pinot Properties Ltd [2018] NZHC
3094 at [12] (footnotes omitted).
(c) The Court will not hesitate to decide questions of law where appropriate.
(d) The Court will not attempt to resolve genuine conflicts of evidence or to
assess the credibility of statements in affidavits.
(e) In determining whether there is a genuine and relevant conflict of facts,
the Court is entitled to examine and reject spurious
defences or plainly
contrived factual conflicts. It is not required to accept uncritically every
statement put before it, however
equivocal, imprecise, inconsistent with
undisputed contemporary documents or other statements, or inherently
improbable.
(f) In assessing a defence the Court will look for appropriate particulars and a
reasonable level of detailed substantiation –
the defendant is under an
obligation to lay a proper foundation for the defence in the affidavits filed in
support of the Notice
of Opposition.
(g) In weighing these matters, the Court will take a robust approach and enter
judgment even where there may be differences on certain
factual matters if the
lack of a tenable defence is plain on the material before the Court.
(h) The need for judicial caution in summary judgment applications has to be
balanced with the appropriateness of a robust and realistic
judicial attitude
when that is called for by the particular facts of the case. Where a
last-minute, unsubstantiated defence is raised
and an adjournment would be
required, a robust approach may be required for the protection of the integrity
of the summary judgment
process.
(i) Once the Court is satisfied that there is no defence, the Court retains a
discretion to refuse summary judgment but does so in
the context of the general
purpose of the High Court Rules which provide for the just, speedy and
inexpensive determination of proceedings.
- [35] As noted
earlier, Civil has also made an application for summary judgment and strike out.
I will deal with the relevant principles
that apply to those applications later
in this judgment.
Northlake’s pleading
(a) the engineer disallowed the Covid Claim and the Stage 12 Claim pursuant to
the decisions and/or certifications dated 6 October
2020 (in respect of the
Covid Claim) and 19 July 2021 (in respect of the Stage 12 Claim);
(b) Civil did not refer the engineer’s decisions to the engineer
under cl 13.2.1 of NZS 3910:2013 or to adjudication
under the Act within three
months of the decisions being given;
(c) the engineer’s decisions are therefore final and binding;
(d) the adjudication under the Act was commenced outside the contractual time
limits for resolving claims and was an abuse of process;
(e) the adjudicator’s determination has no effect on the engineer’s
decisions;
(f) Northlake paid sums found to be owing by the adjudicator in respect of the
Covid Claim and Stage 12 Claims in the amount of $591,040;
and
(g) Civil is in receipt of money paid to it by Northlake to which it has no
entitlement.
- [37] Northlake’s
case, then, is that as Civil failed to challenge the engineer’s decisions
within timeframes set out in
the contracts, by default those decisions are now
beyond challenge regardless of the adjudicator’s determination. This, it
says, provides the legal basis for it to recover the payments it made in
compliance with the adjudicator’s determination as
money had and
received.
Issue one — Was Civil required to dispute the
engineer’s decisions under the dispute resolution provisions of NZS
3910:2013?
- [38] Northlake’s
argument is that Civil was required to, but did not, give notice to the engineer
challenge the engineer’s
decisions and they are therefore final and
binding in terms of the contracts. This issue concerns cl 13 of NZS
3910:2013.
- [39] The
relevant parts of cl 13 are:
13.1.1
No decision, valuation, or certificate of the Engineer shall be questioned or
challenged more than 3 Months after it has been given
or more than
1 Month after the date on which any relevant Adjudicator’s
Determination is given to the parties, whichever is the later, unless
notice has
been given to the Engineer within that time. Every decision, valuation, or
certificate of the Engineer shall be final
and binding if neither party has
referred it to the Engineer under 13.2.1 or to Adjudication within 3 Months
after it has been given,
unless notice has been given to the Engineer within
that time. This subclause 13.1.1 shall not apply to a Progress Payment
Schedule.
13.1.2
Every dispute or difference concerning the Contract which is not precluded by
the provisions of 12.4, 12.6, 13.1.1 or 13.2. shall
be dealt with under the
following provisions of this Section.
13.2 Engineer’s Review 13.2.1
...
13.2.4
Every dispute or difference under 13.1.2 shall be referred to the Engineer
not later than 1 Month after the provision of the Final
Payment Schedule under
12.5.1, 12.5.3, or 12.5.4 or more than 1 Month after the date on which any
relevant Adjudicator’s Determination
is given to the parties, whichever is
the later. The Engineer shall give his or her decision in writing. Except in the
case of a
decision under 13.2.4 the Engineer may correct or modify his or her
decision by a subsequent decision in writing.
Unless the dispute or any question arising in connection with it has been
referred under 13.2.3 and is awaiting a recommendation from
the agreed expert,
the Engineer may, at any time, in respect of any dispute or difference under
13.2.1 give a decision (in this Section
called a formal decision) which states
expressly that it is given under this subclause 13.2.4. The Engineer shall give
a formal decision
on the matter within 20 Working Days of receiving notice in
writing from the Principal or the Contractor requiring him or her to
give a
formal decision and expressly referring to this subclause 13.2.4. Upon making a
formal decision the Engineer shall forthwith
send copies of it to both the
Principal and the Contractor. The Engineer’s formal decision shall,
subject to 13.3 and 13.4
or any Adjudication proceedings, be final and
binding.
The Stage 12 Claim
- [40] The
immediate difficulty Northlake faces is that the engineer did not respond to
Civil’s Stage 12 Claim (made by payment
claim of 24 February 2021) with a
progress payment schedule. Rather, on 19 July 2021, he purported to value the
claim anticipating
that Civil would invoice Northlake direct for that
sum.
- [41] However,
because no payment schedule had been issued in respect to the 24 February
2021 payment claim, under ss 22 and 23
of the Act Northlake had become liable to
pay it as a debt due to Civil. The parties could not contract out of those
provisions of
the Act.5
- [42] Northlake’s
argument that Civil was required to but did not challenge the engineer’s
decision under cl 13 therefore
falls away. For reasons that I set out in detail
in relation to issue three below, Civil was entitled to refer the non-payment of
its payment claim to adjudication under the Act and the determination was
binding on Northlake notwithstanding the engineer’s
decision.
- [43] For
completeness, I note that in the adjudication, Northlake argued that an
engineer’s email on 11 March 2021 requesting
further information
concerning the Stage 12 Claim met the requirements of a payment schedule under s
21 of the Act, but the adjudicator
rejected that submission. The submission was
not advanced before me, and if it had been, I would have rejected it
also.
The Covid Claim
- [44] The
Covid Claim was made in Civil’s payment claim 11 and the dispute referred
to adjudication concerned the engineer’s
failure to certify payment of
those amounts in his progress payment schedule. It follows, Civil contends, cl
13.1.1 does not apply
because it expressly provides, “This subclause
13.1.1 shall not apply to a Progress Payment Schedule.”
5 Construction Contracts Act 2002, s 12.
- [45] I accept
Civil’s submission. Civil issued its payment claim on 31 July 2020 in
compliance with s 20 of the Act. The engineer
responded with a provisional
payment schedule disallowing that claim on 11 August 2020. Civil referred the
dispute arising from the
payment schedule disallowing its payment claim to
adjudication. That it was entitled to do so is recognised in Northlake’s
submissions that:
For that reason, the dispute resolution machinery set out in section 13 of
NZS 3910 does not apply to disputes over progress payment
schedules. If the
contractor is unhappy with a progress payment schedule and wants to access
additional cashflow, its recourse is
to refer the dispute to an adjudication
under the [Act] to provide it with immediate cashflow, with its final account to
be settled
at the conclusion of the contract, resolving all disputed items.
(footnote omitted)
- [46] The course
Northlake submits a contractor may take in response to a disputed payment
schedule is the very course that Civil did
take in this instance. It did not
have to give notice of that dispute to the engineer under cl 13.1.1 because that
clause does not
apply to a dispute concerning a progress payment
schedule.
Conclusion on issue one
- [47] I
find that Civil was entitled to refer the disputes concerning its Covid Claim
and the Stage 12 Claim to adjudication without
giving notice challenging the
engineer’s decisions under cl 13.1.1 of NZS 3910:2013.
Issue two — If Civil was required to dispute the
engineer’s decisions, did it do so in the manner required?
Northlake’s position
- [48] Northlake’s
contention is that cl 13.1.1 has two limbs, both of which must be independently
satisfied if a party wishes
to challenge an engineer’s decision.
- [49] It says
that in respect to the Covid Claim, Civil’s email of 10 October 2020
satisfied the first — but not the second
— limb of cl 13.1.1. This
is because, having given notice to the engineer that it disputed his decision in
respect to the Covid
Claim,
Civil did not otherwise escalate the dispute by way of a request for an
engineer’s review of the decision under cl 13.2.1 or
an adjudication
within three months.
- [50] As a
result, Northlake asserts, the engineer’s decision rejecting the Covid
Claim became “final and binding”.
It notes that it was only on 28
March 2022, some 17 months after the engineer’s decision, that Civil
referred the Covid Claim
to adjudication, which Northlake says was too
late.
- [51] Northlake
interprets cl 13.1.1 as follows:
(a) notice of dispute to the engineer must be given, within either:
(i) three months of the decision, valuation, or certificate of the Engineer
being given; or
(ii) one Month after the date on which any relevant Adjudicator’s
Determination is given to the parties;
whichever is the later, and
(b) the dispute must be referred to either:
(i) an engineer’s review under cl 13.2.1; or
(ii) an [adjudication under the Act],
and notice of such given to the Engineer within three months of
the relevant decision, valuation, or certificate of the Engineer.
(emphasis added)
Civil’s position
- [52] Civil
does not accept Northlake’s interpretation of cl 13.1.1. Civil says the
only notice required to avoid the engineer’s
decision becoming final and
binding is a notice disputing the engineer’s decision given within three
months of the decision.
It says there is no requirement that a party who has
given such a notice must then escalate the dispute by way of a request for an
engineer’s review under cl 13.2.1 or adjudication, or for a further notice
that it has done so to be given to the engineer.
- [53] Civil
argues Northlake’s argument is flawed as it has had to rewrite the second
sentence of cl 13.1.1 by adding the words
“and” and “as
such” (see para [51] above) which fundamentally changes the meaning of the
sentence.
- [54] Civil also
argues that Northlake’s interpretation makes no commercial sense as it
requires a party to give notice to the
engineer that the dispute has been
referred to the engineer under cl 13.2.1 when the engineer will necessarily be
aware of that.
It says such a requirement is pointless, but also may be
draconian, when the failure to give such notice would have the effect of
the
original decision becoming binding.
- [55] Civil says
its interpretation is consistent with the words of cl 13.1.1, and to demonstrate
this, counsel set out those words
but breaking the clause down into its
constituent parts. The first sentence reads:
a No decision, valuation, or certificate of the Engineer b shall be
questioned or challenged more than
- 3
Months after it has been given or
- more
than 1 Month after the date on which any relevant Adjudicator’s
Determination is given to the parties,
whichever is the later,
c unless notice has been given to the Engineer within that time.
- [56] Adopting
the same approach to the second sentence, it reads:
a Every decision, valuation, or certificate of the Engineer b shall be final
and binding if neither party has
i referred it to the Engineer under 13.2.1 or ii to Adjudication
within 3 Months after it has been given,
c unless notice has been given to the Engineer within that time.
- [57] Civil says
the critical part of the second sentence concerns the meaning of the words
“unless notice has been given to the Engineer within that
time”. It contends those words denote an exception to the rule that
the engineer’s decision will be final
and binding if the other two avenues for dispute resolution (under cl 13.2.1 or
adjudication) are not pursued. It says, alongside
referring a decision to the
engineer under cl 13.2.1 or to adjudication within three months, giving notice
to the engineer serves
as a means to avoid the decision becoming final and
binding.
- [58] Civil then
submits that the notice to be given and referred to in the second sentence is
the same notice given under the first
sentence of cl 13.1.1; that is a notice
the engineer’s decision, valuation or certificate is disputed. It says
this must be
so for several reasons. First, because the wording at the end of
each sentence is identical and both provide for notice to be given
to the
engineer within three months. Second, because a notice of dispute under the
first sentence of cl 13.1.1 is the only notice
referred to in cl 13.1.1. Civil
says cl 13.1.1 does not, for instance, refer to a notice to the engineer under
cl 13.2.1 or a notice
to adjudicate.
- [59] Civil
submits the framework created by cl 13.1.1 is therefore:
- a
party who wishes to dispute the decision of the Engineer must give notice of a
dispute to the Engineer within 3 months of the decision
(first
sentence);
- unless
such a notice of dispute is given, the party must refer the dispute to the
Engineer under 13.2.1 or to Adjudication within
that 3 month period to avoid the
decision becoming final and binding ( second
sentence).
- [60] Civil also
argues that its interpretation is consistent with the scheme of cl 13, which
envisions that disputes can be referred
to the engineer for review after the
works are completed. It says there are good commercial reasons parties are able
to give a notice
that preserves their right to subsequently refer a dispute to
either adjudication or to the contractual dispute resolution procedure
but do
not have to do so immediately. For example, while the contract works are still
underway, referring a dispute may be both counterproductive
to maintaining good
working relationships and completing the contract works, and ultimately
unnecessary with the passage of time
and subsequent events.
- [61] Applied to
this case, Civil says that it gave notice to the engineer that it disputed his
decision within three months and it
did not become final and
binding.
My analysis
- [62] An
issue of interpretation of cl 13.1.1 arises. The proper approach to contractual
interpretation is an objective one to ascertain
the meaning the document would
convey to a reasonable person having all the background knowledge reasonably
available to the parties
at the time of the contract.6 The
contractual language must be interpreted within its overall context broadly
viewed.7 If the language used, construed in the context of the whole
contract, has an ordinary and natural meaning it will be a powerful, but
not
conclusive, indicator of what the parties meant.8
- [63] The Court
can determine questions of law on a summary judgment application including
issues of contractual interpretation. However,
it must be satisfied that the
facts are sufficiently ascertained, the matter is adequately argued and the
Court can be confident
that the point at issue turns on pure questions of law or
interpretation.9
- [64] I am not
satisfied that I am in a position to finally determine the interpretation issue
that arises because there is relevant
material I do not have before me. By way
of example, I understand that cl 13.1.1 differed from the comparable clause
in NZS 3910:2003
by including what Northlake referred to as the
“escalation requirement” in the second sentence of cl 13.1.1. I
would
have been assisted to have submissions directed to those and any other
changes, as well as evidence from experts in the industry
as to how such
contracts operate in practice and the considerations that may have a bearing on
that issue. In this regard, Civil
relied on matters relating to the management
of building contracts about which there is no evidence.
- [65] I am faced
with competing interpretations of cl 13.1.1, both of which are, at least,
plausible in my view. Counsel were not able
to refer me to any decisions where
the issue has been considered. I was referred to several articles prepared by
law firms describing
the changes introduced by NZS 3910:2013 which support
Northlake’s
- Firm
PI 1 Ltd v Zurich Australian Insurance Ltd [2014] NZSC 147, [2015]
1 NZLR 432 at [60], citing Investors Compensation Scheme Ltd v West
Bromwich Building Society [1997] UKHL 28; [1998] 1 WLR 896 (HL) at 912, per Lord
Hoffmann.
7 At [61].
8 At [63].
- Zurich
Australian Insurance Ltd v Cognition Education Ltd [2014] NZSC 188, [2015] 1
NZLR 383 at [37], citing International Ore & Fertiliser Corp v East Coast
Fertiliser Co Ltd [1986] NZCA 115; [1987] 1 NZLR 9 (CA) at 16.
interpretation, but I accept that given the nature of those publications they do
not advance matters. I note that the guidelines
attached to NZS 3910:2013 also
support Northlake’s position, but they do not form part of the contract
and neither counsel
referred to them.
- [66] That all
said, and despite Mr Cash’s very able submissions, I am not attracted to
Civil’s position on this issue.
To my mind, the intention of cl 13.1.1 is
that an engineer’s decision, valuation or certificate shall become binding
after
three months unless it has been referred to the engineer for review under
cl 13.2.1 or to adjudication. The second sentence of cl
13.1.1 appears to have
been added to ensure that, once raised, disputes are promptly resolved and to
set time limits within which
that is to occur. Importantly, and consistent with
this, upon the raising of a dispute either party has the right to make a
referral
to the engineer or to adjudication. I do not believe that it was
intended that a party can give notice of a dispute within three
months of an
engineer’s decision and then do nothing at all to advance it to a
resolution.
- [67] As I have
noted, I do not have before me evidence on matters concerning the management of
such contracts, but Civil’s argument
that it may be beneficial to leave
the resolution of disputes until the end of the works is not convincing,
particularly given the
statutory background of the Act and its emphasis upon the
speedy resolution of disputes.10 In addition, if it suits the parties
in any particular case to park a dispute, they can always agree to that
notwithstanding cl 13.1.1.
- [68] Further,
while Civil argues that on Northlake’s interpretation the words
“unless notice has been given to the Engineer
within that time”
serve no purpose, that is not so in the case where a party chooses to refer the
dispute to adjudication rather
than to the engineer for review. It appears to me
that it is in fact Civil’s interpretation that renders those words in the
second sentence of cl 13.1.1 redundant.
Conclusion on issue two
- [69] I
am not satisfied that I am able to finally resolve the interpretation issue on
this application.
10 Construction Contracts Act, s 3(b).
Issue three — Was the adjudicator’s determination
binding?
- [70] Northlake’s
position is the adjudication was both pointless and of no effect. That argument
is contrary to the Act, and
would do great violence to its scheme if accepted.
It is also contrary to case law.
The Act
- [71] Turning
first to the Act, its purposes are set out in s 3 and are:
(a) to facilitate regular and timely payments between the parties to a
construction contract; and
(b) to provide for the speedy resolution of disputes arising under a
construction contract; and
(c) to provide remedies for the recovery of payments under a construction
contract.
- [72] Section 12
is a no contracting out provision as follows, “This Act has effect despite
any provision to the contrary in
any agreement or contract.” Civil’s
position has consistently been that Northlake’s argument that the
engineer’s
decisions are binding notwithstanding the adjudication
determination attempts to elevate the contract terms above the dispute
procedures
of the Act, offending s 12.
- [73] Part 3 of
the Act sets out processes for the adjudication of disputes. Section 25 provides
that any party to a construction contract
has a right to refer a dispute to
adjudication and may exercise that right even though the dispute is the subject
of proceedings
between the same parties in a court or tribunal.
- [74] Section 26
defines the relationship between adjudication under the Act and other dispute
resolution procedures. Section 26(1)
provides that nothing in pt 3 prevents a
party to a construction contract from submitting a dispute to another dispute
resolution
procedure, whether or not that procedure takes place concurrently
with an adjudication. The examples provided of other dispute resolution
procedures are proceedings to a court or tribunal, or to mediation, but there is
no mention of decisions made by contract administrators
(such as the
engineer).
- [75] Under s
26(2), a submission of a dispute to another dispute resolution procedure while
the dispute is the subject of an adjudication
does not bring the adjudication to
an end or otherwise affect the adjudication. However, under s 26(3), an
adjudicator must terminate
adjudication proceedings if, before the adjudicator
determines the dispute, that dispute is determined under another dispute
resolution
procedure.
- [76] Section
26(4) provides that nothing in any other enactment or rule of law or any
contract affects the application of the adjudication
provisions.
- [77] Section
27(1) provides that nothing done under, or for the purposes of, an adjudication
affects any civil proceeding arising
under a construction contract.
- [78] Pursuant to
s 27(2), in any civil proceeding before a court, tribunal or a member under the
Weathertight Homes Resolution Services
Act 2006 in relation to any matter
arising under a construction contract, the court, tribunal or member:
(a) must allow for any amount paid to a party to the contract under, or for the
purposes of, this Part in any order or award the
court, tribunal, or a member
makes in those proceedings; and
(b) may make any orders that the court, tribunal or member considers
appropriate, having regard to any steps taken by a party to
the contract in good
faith and in reliance on an adjudicator’s determination under this Part
(including an order requiring
a party to the contract to pay for goods and
services supplied by another party to that contract in good faith and in
reliance on
an adjudicator’s determination).
- [79] Section 58
deals with the enforceability of an adjudicator’s determination.
Importantly, it provides in s 58(1) that,
“An adjudicator’s
determination under s 48(1)(a) is enforceable in accordance with section
59.” Section 48(1)(a)
concerns disputes as to whether an amount of money
is payable under a construction contract.
- [80] Section 59
provides for the consequences of not complying with an adjudicator’s
determination under s 48(1)(a). These are
set out in s 59(2) which
provides:
(2) The consequences are that the party who is owed the amount (party
A) may do all or any of the following:
(a) recover from the party who is liable to make the payment (party B),
as a debt due to party A, in any court,—
(i) the unpaid portion of the amount; and
(ii) the actual and reasonable costs of recovery ordered against party B by that
court:
...
(c) apply for the adjudicator’s determination to be enforced by entry as a
judgment in accordance with subpart 2 of Part 4.
- [81] Section 60
provides that an adjudicator’s determination is binding on the parties to
the adjudication and continues to
be of full effect even though a party has
applied for judicial review of the determination, or any other proceedings
relating to
the dispute between the parties has been commenced.
- [82] From this
summary of provisions of the Act, the clear legislative intention is that
parties to construction contracts have the
right to refer disputes or
differences for speedy resolution by way of adjudication, which will be binding
and enforceable subject
only to a later substantive and final determination of
the dispute by way of some other dispute resolution procedure.
- [83] The Act
also makes clear that an adjudication may proceed in tandem with other dispute
resolution procedures, such as court proceedings,
arbitration or mediation,
whether or not the adjudication process commences before or after such other
proceedings are initiated
and will only terminate if such other procedures
determine or resolve the dispute before the adjudicator does. If the adjudicator
issues a determination before a court or arbitrator has determined the dispute,
the determination will be binding on the parties
and continue to have full
effect, even if one party has issued judicial review or other
proceedings.
- [84] Northlake
argues that the position I describe in [82] and [83] is not entirely correct as
an adjudication determination can be
“overruled” by a private
agreement of the parties, and an earlier “final and binding”
agreement will also
take priority over any interim adjudication. It submits that
agreeing a contractual process by which disputes are finally resolved
is not
contracting out of the Act as a party is not thereby deprived of its right to
adjudicate, but an adjudication determination
is subordinate to the
parties’ “final and binding” agreement.
- [85] Northlake’s
stance that Civil was entitled to refer the Covid Claim and the Stage 12 Claim
to adjudication under the Act,
that it could participate fully in that process
which, no doubt, came at significant cost to both parties, but then simply
ignore
the result as pointless and of no effect, is both unreal and unappealing.
It also, in my view, renders Civil’s right to refer
the dispute to
adjudication under s 25 of the Act illusory and offends s 12. Further, if
Northlake considered the engineer’s
decisions were binding and an answer
to Civil’s claims, it could and should have raised that in its defence in
the adjudication
and the adjudicator would have been required to rule upon
it.11
- [86] I accept
Civil’s submission that the fact the parties cannot contract out of the
right to refer disputes to adjudication
under the Act is reflected in the terms
of cl 13 of NZS 3910: 2013. This provides that the time within which steps may
be taken under
the prescribed processes may run from the date of an
adjudicator’s determination instead of the date from which an
engineer’s
decision that is under challenge was issued.
- [87] That the
parties may after an adjudication enter into a final and binding agreement that
effectively supersedes the adjudication
determination is undoubtedly correct,
but beside the point. Such an agreement is entered into by way of compromise
following the
exercise of the parties rights under the Act, but does not
contract out of them.
- [88] The case
law also confirms the adjudicator’s determination was binding. In Body
Corporate 200012 v Keene, Brewer J held that an adjudicator’s
determination is a judicial decision that is binding pro tem and can be
enforced.12 He endorsed remarks of Coulson J in Benfield
Construction Ltd v Trudson (Hatton) Ltd in relation to the Housing Grants,
Construction and Regeneration Act 1996 (UK), which Brewer J described as having
similar purposes
to the Construction Contracts Act, that:13
11 Construction Contracts Act, s 45(d).
12 Body Corporate 200012 v Keene [2017] NZHC 2953, [2018]
NZAR 120 at [81].
- At
[82], citing Benfield Construction Ltd v Trudson (Hatton) Ltd [2008] EWHC
2333 (TCC) at [34].
(a) The parties are bound by the decision of an adjudicator on a dispute or
difference until it is finally determined by court or
arbitration proceedings or
by agreement made subsequently by the parties.
- [89] In DHC
Assets Ltd v Toon, the issue was whether the plaintiff should be granted
leave under s 248 of the Companies Act 1993 to pursue claims by way of
adjudication
under the Act against a company in liquidation.14 An
argument was raised that leave should not be granted as the engineer’s
decision had not been challenged in time under cl
13 of NZS 3910:2003. The
plaintiff argued that the dispute resolution provisions of the contract could
not curtail its rights to
refer the dispute to adjudication under the Act. While
it was not necessary for Duffy J to express a definitive view on the issue,
she
observed:
[15] Section 12 of the [Act] prohibits any contracting out from the
provisions of that Act. I cannot see, therefore, how the more
restrictive time
frames for bringing a dispute under cl 13 can be superimposed on DHC’s
rights under the [Act]. To allow that
to occur would be in effect to allow a
contracting out of that Act’s provisions insofar as they impose time
limits for bringing
a proceeding under that Act. In my view there is a sound
argument that cl 13 does not detract from the other rights and legal remedies
that DHC may have either under the [Act] or the law of contract.
- [90] Willis
Trust Co Ltd v Green was an application for judicial review of an
adjudicator’s determination alleging that the adjudicator had no
jurisdiction when
the parties had agreed to submit disputes to
arbitration.15 Harrison J held that s 12 of the Act is
unambiguous16 and:17
... subordinates the effect of an arbitration provision where a claim is made
under the Act. As a result, the statute prevails notwithstanding
an agreement to
arbitrate.
- [91] An
interesting case demonstrating the binding nature of adjudication determinations
is G K Shaw Ltd v Green where the applicant was unsuccessful in an
adjudication under the Act and then attempted to raise a second adjudication
proceeding
on the same facts.18 The second adjudicator held that he
lacked jurisdiction in view of the earlier determination of the claim on the
merits. The applicant
sought
14 DHC Assets Ltd v Toon [2016] NZHC 140.
15 Willis Trust Company Ltd v Green HC Auckland,
CIV-2006-404-809, 25 May 2006.
16 At [30].
17 At [34].
18 G K Shaw Ltd v Green [2023] NZHC 605.
judicial review of that decision. In the High Court, Isac J dismissed the
application for review. While it was not the basis for
his decision, the Judge
considered that in circumstances where the applicant could and should have
raised all its claims the first
time around, it was an abuse of process to bring
an “almost identical claim dressed up in different legal
regalia”.19
- [92] Northlake
relied on John Holland Pty Ltd v Roads and Traffic Authority of New South
Wales,20 but I do not consider it supports its position that the
adjudicator’s determination was of no effect. To the contrary, there
Giles
JA said, in relation to similar legislation:
62 It is not correct that ... [a contract administrator] who in performing
his contractual function comes to a determination negates
a statutory right to
retain an adjudicated amount. The adjudicator’s determination remains, and
brings payment of the adjudicated
amount, but that is interim and subject to a
different position being established in relation to payment for the relevant
work or
related goods and services, contractually or in proceedings. If in civil
proceedings, it is decided that the contractor was entitled
to $10 or $30,
rather than the $20 determined by the adjudicator, that does not undo the
adjudicator’s determination. It has
done its work in ensuring
“prompt interim progress payment on account, pending final determination
of all disputes”...
So also if in the manner earlier described, the
contractual mechanisms result in a contractual obligation on the principal to
pay
the contractor or the contractor to pay the principal. The
contractor’s right under the Act is to receive the adjudicated amount,
but
subject to final determination, and if the final determination involves the
[contract administrator] determining that the contractor
was entitled to $10
or
$30, rather than $20 determined by the adjudicator, the [contract
administrator] is not negating the contractor’s statutory
right.
(citation omitted)
Northlake’s alternative positions
- [93] Taking
a different tack, Northlake relies upon s 26(3) of the Act, which provides that
an adjudicator must terminate an adjudication
if the dispute is determined under
another dispute resolution procedure. Northlake contends that if the contract
between the parties
provides that a decision of the engineer has become binding
by reason of a party having failed to challenge it, then the statutory
process
must yield to that agreement. I do not accept this argument either. Section 26
is concerned with
19 At [45].
20 John Holland Pty Ltd v Roads and Traffic Authority of New
South Wales [2007] NSWCA 140.
other dispute resolution procedures such as court proceedings, arbitration or
mediation. It is not concerned with engineer’s
decisions as contract
administrators.
- [94] Northlake
also argues that under s 27(2) of the Act, if an adjudicator’s
determination exceeds a party’s contractual
entitlement, a court must make
allowance for that and order restitution. Section 27(2) does not create a free
standing restitutionary
remedy. It provides for the specific circumstance where
a binding but interim determination under the Act is superseded by a subsequent
decision of a court, tribunal or under the Weathertight Homes Resolution
Services Act. There has been no such decision in this case,
which, as I shall
come to below, raises a fundamental obstacle to Northlake’s claim as
presently framed.
Conclusion of issue three
- [95] I
am satisfied that the adjudicator’s determination was binding on both
Northlake and Civil.
Issue four — Does Northlake have a claim for money had
and received?
- [96] Northlake
argues the cause of action for money had and received provides a restitutionary
remedy where there has been an unjust
enrichment. It contends all that a
claimant advancing such a claim need establish is an enrichment of the
defendant, the deprivation
of the plaintiff, and the absence of any legitimate
reason for the enrichment.
- [97] I do not
accept Northlake’s submission. While the concept of unjust enrichment is
sometimes used as an organising principle
that may explain the basis for some
restitutionary claims, it is not yet a recognised cause of action in its own
right in this country.
Northlake relies upon Napier v Torbay Holdings
Ltd21 and National Bank of New Zealand Ltd v Waitaki
International Processing (NI) Ltd,22 but both cases
21 Napier v Torbay Holdings Ltd [2016] NZCA 608, [2017]
NZAR 108 at [21].
22 National Bank of New Zealand Ltd v Waitaki International
Processing (NI) Ltd [1997] 1 NZLR 724 at 728 and National Bank of New
Zealand Ltd v Waitaki International Processing (NI) Ltd [1999] 2 NZLR 211
(CA) at 215.
concerned claims within established categories where the law recognises a
plaintiff’s right to recovery, for example payments
made under a
mistake.
- [98] In
Martin v Pont, Tipping J said:23
Although, as stated, unjust enrichment can be regarded as the rationale of
(albeit not necessarily the test for) a number of restitutionary
claims, it is
not a prerequisite of the action for money had and received.
- [99] In a recent
article in the New Zealand Law Journal, Sean McAnally expressed the view, with
which I agree that:24
Money had and received and unjust enrichment are not synonyms to be used
interchangeably. One may describe a species of actions falling
within the law of
obligations, but is not, at least yet, a cause of action. The other is a cause
of action, with its own history
and precedents, and even if it is now justified
by the concept of unjust enrichment, it is a long way from being the cause of
action
that now exists in England and Wales. The two should not be confused.
- [100] Further,
even in English law I understand there is “no general principle that to
retain money paid without any legal basis
(such as debt, gift, compromise, etc)
is unjust enrichment”.25 The learned authors of Goff &
Jones on Unjust Enrichment state:26
A claimant must
be able to point to a ground of recovery that is established by past authority,
or at least is justifiable by a process
of principled analogical reasoning from
past authority. There is in English law “no general rule giving the
plaintiff a right
of recovery from a defendant who has been unjustly enriched at
the plaintiff’s expense”, and the courts’ jurisdiction
to
order restitution on the ground of unjust enrichment is subject “to the
binding authority of previous decisions”:
they do not have “a
discretionary power to order repayment whenever it seems ... just and equitable
to do so”.
- [101] Related to
this, the law will generally not order restitution where a payment has been made
pursuant to a legal, equitable or
statutory obligation owed by the claimant to
the defendant, including payment made pursuant to an order of a court or
tribunal of
competent jurisdiction. A claim to recover such payment can justly
be
23 Martin v Pont [1993] 3 NZLR 25, 30.
- Sean
McAnally “Money had and received: we’re sorry, will you have us
back?” [2023] NZLJ 258.
25 Deutsche Morgan
Grenfell Group Plc v IRC [2006] UKHL 49, [2007] 1 AC 558 at [21].
- Charles
Mitchell, Paul Mitchell and Stephen Watterson Goff & Jones on Unjust
Enrichment (10th ed, Sweet & Maxwell, London, 2022) at [1-30] (footnotes
omitted).
answered on the basis the payee had every right to receive it.27
While it appears this principle will not apply in circumstances where
money was paid under a judgment that was void, it will apply
even if there is
reason to believe that the court has made a mistake.28
- [102] Here,
Northlake made payment to Civil because the adjudicator determined it must do
so, and Civil took steps to enforce that
binding determination. At the time it
made the payment, its then lawyers acknowledged it was obliged to pay to
“satisfy the
interim determination”. Even now, Northlake accepts
that the adjudication was “perfectly valid”, which is to my
mind
irreconcilable with the case it advances that the determination is pointless and
of no effect, and that it is entitled to recover
the payment as money had and
received. The position might well be different if Northlake had the disputes
that were determined by
the adjudicator on an interim basis substantively and
finally determined in its favour in other proceedings, but it has not yet taken
that course.
Conclusion on issue four
- [103] Northlake
has not supported its claim in reliance upon, or by analogy to, established
categories of case where the law recognises
a cause of action for money had and
received. It has failed to satisfy me that Civil does not have a defence to its
claim for this
reason. Northlake’s only cause of action cannot succeed
also because I do not accept the premises upon which it is founded,
namely, that
the engineer’s decisions were final and binding and the
adjudicator’s determination was of no effect.
Summary judgment application and strike out principles —
Civil
- [104] A
defendant’s summary judgment application is made under r 12.2(2) of the
High Court Rules, which provides:
The court may give judgment against a plaintiff if the defendant satisfies
the court that none of the causes of action in the plaintiff’s
statement
of claim can succeed.
27 At [2-32]—[2-36], citing Marriott v Hampton
[1775-1802] All ER Rep 631 (KB); Wilson v Ray [1839] EngR 647; (1839) 113 ER 32; and
Clydesdale Bank Ltd v Schröder & Co [1912] UKLawRpKQB 80; [1913] 2 KB 1. See also P
Twist, J Palmer and Marcus Pawson Laws of New Zealand, Restitution
(online ed) at [10] and n 6.
28 Mitchell, Mitchell and Watterson, above n 26, at [2-38]
and [2-41].
- [105] The
position where a defendant applies for summary judgment is different from an
application by the plaintiff because a defendant
must show the plaintiff cannot
succeed on any of its causes of action.
- [106] Summary
judgment in favour of a defendant will also not be appropriate where it is
possible for a plaintiff to amend its claim
so as to remedy defects relied upon
by the defendant; it should only be used where the defendant has a clear answer
to the plaintiff’s
claim which cannot be contradicted.29 In
this respect, Elias CJ in Westpac Banking Corp v M M Kembla New Zealand Ltd
relevantly said:30
Although [the predecessor to r 12.2] refers to the causes of action “in
the plaintiff's statement of claim”, [the predecessor
to r 15.1] (which
permits the Court to strike out a cause of action) similarly is based upon
“the pleading”. Under [r
15.1] the Court does not strike out
pleadings where a defect can be cured by amendment which the party is willing to
make. Similarly,
the residual discretion of the Court under [r 12.2] to refuse
summary judgment would be properly invoked to avoid the oppression
which would
otherwise result if an application by a defendant for summary judgment would
preempt a plaintiff exercising the right
to amend the pleadings ... Indeed, use
of the discretion to enable amendment is arguably more necessary in the
interests of justice
in the case of summary judgment than in the case of
strike-out because summary judgment results in issue estoppel.
- [107] Civil also
relies upon r 15.1 of the High Court Rules. It permits the Court to strike out
all or part of a pleading in specified
circumstances as follows:
15.1 Dismissing or staying all or part of proceeding
(1) The court may strike out all or part of a pleading if it—
(a) discloses no reasonably arguable cause of action, defence, or case
appropriate to the nature of the pleading; or
(b) is likely to cause prejudice or delay; or
(c) is frivolous or vexatious; or
(d) is otherwise an abuse of the process of the court.
(2) If the court strikes out a statement of claim or a counterclaim under
subclause (1), it may by the same or a subsequent order
dismiss the proceeding
or the counterclaim.
(3) Instead of striking out all or part of a pleading under subclause (1),
the court may stay all or part of the proceeding on such
conditions as are
considered just.
(4) This rule does not affect the court’s inherent jurisdiction.
29 Westpac Banking Corp v M M Kembla New Zealand Ltd [2000] NZCA 319; [2001]
2 NZLR 298 (CA) at [66]; and
Attorney-General v Jones [2003] UKPC 48, [2004] 1 NZLR 433 at [5].
30 At [66].
- [108] The Court
will exercise its power to strike out a pleading sparingly and only in clear
cases.
- [109] I accept
the general approach in Attorney-General v McVeagh, where the Court of
Appeal said:31
The Court is entitled to receive affidavit evidence on a striking-out
application, and will do so in a proper case. It will not attempt
to resolve
genuinely disputed issues of fact and therefore will generally limit evidence to
that which is undisputed. Normally it
will not consider evidence inconsistent
with the pleading, for a striking-out application is dealt with on the footing
that the pleaded
facts can be proved ... But there may be a case where an
essential factual allegation is so demonstrably contrary to indisputable
fact
that the matter ought not to be allowed to proceed further.
Issue five — Can the adjudicator’s determination
now be challenged by Northlake?
- [110] Civil
says its application for summary judgment/strike out is simply the flipside of
the arguments that it raised in defence
of Northlake’s claim. It submits
that if the Court accepts it was entitled to take the disputes concerning the
Covid Claim
and the Stage 12 Claim to adjudication, the adjudicator’s
determination was binding on the parties until such time as there
is a final
determination by a court or tribunal or a procedure of the same nature rules
differently on the substance of the dispute.
It says this is enough for it to be
awarded summary judgment or for Northlake’s case to be struck
out.
- [111] Civil also
submits Northlake’s claim should be struck out because Northlake has now
lost the right to dispute the adjudication
determination. It says cl 13.1.1
envisions there may be a binding and enforceable adjudication determination that
affects in some
way (such as approving or overturning in full or in part) the
engineer’s decision, valuation or certificate with the effect
the
engineer’s prior decision is essentially replaced by the binding
adjudication determination. It argues the effect of cl
13.1.1 is that unless
notice of a dispute is given to the engineer within one month of the
adjudication determination, it cannot
be questioned or challenged. Civil says
that
31 Attorney-General v McVeagh [1995] 1 NZLR 558 (CA) at 566
(citation omitted).
as Northlake did not give notice of its intention to dispute the adjudication
determination within one month or at all, Northlake
cannot now challenge it.
- [112] I do not
accept this argument. There is no requirement in cl 13.1.1 for a party to give
notice to the engineer disputing an
adjudication determination. The provision is
concerned with challenges to engineer’s decisions, not adjudication
determinations.
An adjudicator’s determination cannot replace an
engineer’s decision, it simply resolves a dispute on a provisional and
interim basis pending final resolution by other means.
- [113] I am not
satisfied that Northlake has no prospect of having the disputes concerning its
liability for the Covid Claim and Stage
12 Claim finally determined, including
in this proceeding (subject to the amendment of its pleadings). It may also be
able to seek
to have those disputes determined by using the dispute resolution
procedures in the contracts, but I make no comment as to whether
that is still
the case. In these circumstances, it would be wrong to enter summary judgment
for Civil. I consider the correct approach
is to strike out Northlake’s
present cause of action, which I am satisfied cannot succeed, but grant leave
for Northlake to
amend its pleadings.
Result
- [114] Northlake’s
application for summary judgment is dismissed.
- [115] Civil’s
application for summary judgment is dismissed.
- [116] In
relation to Civil’s application for strike out, I order that
Northlake’s cause of action is struck out but with
leave reserved for it
to file an amended statement of claim within 28 days of the date of this
judgment.
- [117] The case
is to be set down for a further case management teleconference on a date to be
fixed by the Registrar. Counsel shall
file memoranda at least three working days
prior to the next conference with a full suite of proposed timetable directions
on the
matters in sch 5 to the High Court Rules 2016.
- [118] It appears
to me that both parties have had some degree of success and that costs would be
appropriately reserved. If that is
not accepted and either party seeks a ruling
on costs, then memoranda may be filed within 28 days and are to be no more than
five
pages. Any reply memoranda may be filed within 14 days thereafter. I shall
determine costs (if necessary) on the papers.
O G Paulsen Associate Judge
Solicitors:
LeeSalmonLong, Auckland
Dentons Kensington Swan, Wellington
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2023/2715.html