|
Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 4 March 2024
|
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
|
|
2020-404-001235
[2023] NZHC 3203 |
|
BETWEEN
|
BODY CORPORATE 462460 “NIKAU APARTMENTS”
First Plaintiff
|
|
|
JEETESH MISTRY AND USHA MISTRY AND OTHERS
Second Plaintiffs
|
|
|
AUCKLAND COUNCIL [DISCONTINUED]
First Defendant
|
|
|
PRODESIGNERS ARCHITECTS LIMITED [DISCONTINUED]
Second Defendant
|
|
AND
|
TERRACON INDUSTRIES LIMITED
Third Defendant
|
|
|
Continued overpage
|
|
Hearing:
|
13 November 2023
|
|
Appearances:
|
S N Zellman and M J Cochrane for the Plaintiffs No Appearance for the Third
Defendant
|
|
Judgment:
|
14 November 2023
|
JUDGMENT OF VAN BOHEMEN J
This judgment was delivered by me on 14 November 2023 at 3 pm pursuant to r 11.5 of the High Court Rules 2016.
Counsel/Solicitors:
Grimshaw & Co, Auckland Simpson Grierson, Auckland Wotton Kearney, Auckland
Registrar/Deputy Registrar
...................................
Braun Bond & Lomas Limited, Hamilton
BODY CORPORATE 462460 v TERRACON INDUSTRIES LTD [2023] NZHC 3203 [14 November 2023]
|
FIRE DESIGNS LIMITED [DISCONTINUED]
Fourth Defendant
|
|
PETER CHARLES DUNKIN [DISCONTINUED]
Fifth Defendant
|
Plaintiffs’ claims against Terracon
(a) in accordance with the building consent for the development, including amendments to the building consent, and plans and specifications for the construction of the Nikau Apartments;
(b) with reasonable skill and care; and
(c) in accordance with the Building Code.
(a) Water entry through the planter boxes and adjacent courtyards (Defect A);
(b) Poor installation of the membrane roof (Defect B); and
(c) Waterproofing to balcony decks which did not comply with consented plans and was incomplete (Defect E).
$5,067,108.69 (excluding GST) as a result of Terracon’s breach of duty. This sum comprises:
(a) The current estimated cost of remedying Defects A, B and E:
$4,868,409.00;
(b) Consultant costs incurred in defect and damage investigation and advice regarding remedial scope: $135,179.11;
(c) Additional Body Corporate management costs incurred in relation to investigating and remedying the defects: $36,445.42;
(d) Interest in accordance with the Interest on Money Claims Act 2016:
$13,930.16; and
(e) Costs of this proceeding calculated on a 2B basis: $13,145.00.
Relevant factual background
the waterproof membrane supplier or manufacturer for roof, decks and wet areas and an approved producer statement from the waterproofing membrane licensed applicator.
Relevant design aspects of the Nikau Apartments
(a) All apartments have access either to an external concrete balcony or to a paved courtyard. A torch-on waterproof membrane is installed over the balconies, together with a floating deck system which comprises timber furrings and decking. The courtyards at ground level are also weatherproofed with a torch-on membrane system and have pavers installed over the bedding sand.
(b) The metal roof to the complex has a trapezoidal profile that discharges water into externally mounted gutters and down pipes. The roof also incorporates a torch-on membrane roof installed over a plywood substrate. The membrane roof discharges water into sumps and through scupper outlets.
(c) At ground level, there are planter boxes constructed with concrete blocks with a plastered finish. The planter boxes are weatherproofed with a torch-on membrane system and have been landscaped with a combination of shrubbery and other vegetation. As built, the planter boxes drain through outlets in the side of the planter box walls.
Terracon’s involvement in the construction of the Nikau Apartments
(a) Mr Nigel Campbell of Terracon completing, on 5 February 2014, an Auckland Council “Producer statement construction (PS3) Waterproofing” form, as “the applicator who carried out the waterproofing work”, and confirming that the waterproof membrane had been applied in accordance with the manufacturer’s specifications and technical requirements and that all work had been carried out in accordance with the Building Consent and complied with clauses “B2 Durability and E2 External Moisture” of the Building Code (the Waterproofing Producer Statement).
(b) Mr Campbell writing to Mr Mike Goedhart of MJZ “re 136 Stancombe Rd” on 3 March 2014 to confirm that:
... the screeds that have been installed to the above property and namely the decks on level one and level two do meet the minimum falls required.
(c) Two product warranties issued on 3 March 2014 by Nuralite Waterproofing Limited (the Product Warranties) for the application by Terracon of:
(i) Nuraply 3P to the decks and Nuraply 3PM to the box gutter/roof; and
(ii) Nuraply 3PG to the planters.
Due to the construction process the nib heights were less than 100mm and this area has no typical term bar. The warranty provided is for all subject areas but not to the effected nibs that are less than 100mm.
Requirements for formal proof
The plaintiffs’ evidence
(a) Graham Durkin, a chartered building surveyor, who worked for AS Jacobs, the company engaged in 2019 to investigate and provide an independent expert opinion on the defects and damage at Nikau, and to provide repair recommendations. Mr Durkin’s evidence includes a series of photographs that illustrate the Building Defects and the damage caused by the Defects.
(b) Jacob Woolgar, a chartered and registered building surveyor and director of AS Jacobs, who assesses Terracon’s responsibility for Defects A, B and E and the scope of remedial work reasonably required to rectify each defect.
(c) Paul Ranum, a registered quantity surveyor and director, who was engaged to provide quantity surveying advice and assessments in respect of the claim against Terracon.
(d) Stephen Plummer, former managing director of Scope Strata Management Limited, the body corporate manager for the Nikau Apartments between November 2020 and August 2022. Mr Plummer
3 High Court Rules 2016, r 19.4(4).
4 R v Leitch [1998] 1 NZLR 420 (CA) at 428.
summarises the history of the development of the Nikau Apartments, the discovery of water leaks into the basement carpark, the level 2 ceiling and some of the apartments, and the steps taken to address the leaks. Mr Plummer has also calculated the second plaintiffs’ respective shares of the remedial costs to fix the Building Defects according to each unit’s utility interest.
(e) Jeanette Dick, Chairperson of the Body Corporate Committee for the Nikau Apartments, who provides evidence of the expert and consultant costs incurred by the Body Corporate in investigating the Building Defects and damage and the additional administration costs incurred by the Body Corporate in relation to the Building Defects. Ms Dick also provides a schedule showing the shares of the apartment owners in meeting those costs.
(f) Michelle Arnott, an information technology manager employed by the plaintiffs’ solicitors, who provides evidence of the current registered owners of the apartments.
Did Terracon owe the plaintiffs a duty of care?
5 Bowen v Paramount Builders (Hamilton) Ltd [1977] 1 NZLR 394 at 406 .
7 Boyd v McGregor HC Auckland CIV-2009-404-5332, 17 February 2010 at [60].
8 Findlay v Auckland City Council HC Auckland CIV-2009-404-6497, 16 September 2010 at [33].
9 Bowen v Paramount Builders (Hamilton) Ltd, above n 5, at 418.
The Building Defects
Defect A – Planter boxes and adjacent courtyards
(a) The sloped concrete capping was not installed to the top of the planter block wall in accordance with the consented plans.
(b) Installation of the planter membrane did not follow the consented plans. The membrane upstand predominately finishes midway up the planter wall beneath the blockwork plaster. The membrane does not terminate beneath the concrete capping as shown on the consented plans. No termination cover flashing has been installed to provide protection at the top of the membrane upstand and to prevent water entering behind the membrane.
10 Kwak v Park [2016] NZHC 530 at [49]–[50].
11 At [65].
(c) The top of the membrane upstand has varying height finishes, and some sections of the membrane upstand terminate well below the plastered finish, meaning there is no protection to the top of the membrane upstand.
(d) The membrane upstand has extensively debonded from the wall and water has been able to enter behind the membrane.
(e) There are incomplete sections of membrane which has meant that the planter wall is not waterproof.
(f) The planter soil barrier protection system was not installed as required by the Nuralite membrane system and consented details and has resulted in blocked drainage outlets.
(g) The drainage outlets in the planter boxes were not installed in accordance with the consented plans, with floor penetrating outlets substituted with wall penetrating outlets. The membrane was not correctly dressed into the outlets. Water has entered behind the membrane at these outlet junctions.
(h) The membrane on the courtyards was incorrectly dressed into the outlets, causing water entry. In some locations the membrane on the courtyards terminates short of the drainage outlets.
(i) The chased flashing terminating Unit GA’s courtyard membrane is butt jointed with no soakers at the joints. The membrane upstand could not adhere to the aggregate tilt panel wall surface. Water has entered behind the membrane upstand at the butt joints in the flashing and at the exterior corner of the building where the membrane and chased flashing are incomplete.
comply with the Building Code, in particular cls E2.3.1, E2.3.2 and B2.3.1 and have not been constructed in accordance with the Building Consent or with plans and specifications for the construction of the Nikau Apartments. I also accept that the planter boxes and the courtyards were not constructed in accordance with industry standards or good trade practice.
Defect B – Poor installation of membrane roof
(a) The membrane leaked around the ventilation units;
(b) There are large gaps between the jointed sections of the metal chase cover flashings. The gaps between the cover flashing joints have been filled with and are reliant upon sealant which has failed and has allowed water entry.
(c) The chased cover flashings over the membrane are butt jointed and were installed with no under soakers at the flashing joints so that water can enter at these joints.
(d) Sections of metal chased flashings are missing. In some locations the top of the membrane upstand relies solely on adhesion to the masonry wall.
(e) There is no sealant to the parapet chased cap flashing.
(f) The membrane has been lapped incorrectly within the dropped catchment section of the internal gutter adjacent the scupper outlets. The installation of dropped catchment sections to every outlet appears to be a departure from the consented details. Water has ponded in dropped catchment sections of internal guttering due to the lack of fall.
(g) The membrane has been incorrectly dressed into the sump outlets.
(h) The scupper outlet has been incorrectly installed and has allowed water ingress. The scupper is not a pre-formed singular piece but has been cut in two pieces and joined together.
(i) The overflow outlet installation is a departure from the Nuralite system. The overflow size diameter is too small. If the primary outlet blocks, the overflow does not have sufficient capacity for the volume of water.
(j) Roof edge barrier rails have been directly bolted through the top of the membrane, creating a path for water entry.
(k) Membrane roof vents have not been installed to vent the roof space void, as detailed on the drawings and manufacturer specifications.
(l) There are inadequate falls in parts of the roof, resulting in water ponding.
(m) Critical roof wall junctions are reliant upon exposed sealant and are leaking.
(n) At least one cross lap in the membrane gutter has caused water to accumulate and has been restricting water discharge off the roof.
(a) water ingress resulting in damage and mould growth to internal linings;
(b) damaged timber framing, plywood substrate and insulation beneath the water ingress locations;
(c) premature deterioration of the membrane, including cracking and splitting, particularly at corner junctions and within the dropped catchment areas adjacent to the scupper outlets;
(d) corrosion of the concrete tilt panel angle brackets which were corroding where they had been subjected to regular water exposure; and
(e) potential condensation damage to the underside of the plywood substrate and timber furrings due to lack of membrane ventilation installation.
Defect C – Waterproofing to balcony decks
(a) The falls to the balcony decks do not meet the minimum requirements set out in the Building Consent details; some parts of the decks have been measured at zero-degree falls, which increases the likelihood of water entry.
(b) Only one layer of torch-on membrane has been installed to the deck surface when the consented details specified a minimum of two layers.
(c) The membrane has not been dressed up the wall or to the perimeter of the deck. Instead, the membrane terminates at the base of the wall, which has allowed water entry.
(d) There is no cover flashing or chased flashing to prevent water from entering beneath the membrane. A large volume of gravity fed moisture has entered underneath the membrane and into the building.
(e) In some locations, the membrane has not been dressed up underneath the weatherboard cladding, which has allowed water entry.
(f) Critical flashings at deck/wall junctions have not been installed.
(g) The membrane has lost adhesion with the deck surface and in some areas has started to peel back from the deck surface, allowing water entry.
(a) In some instances, off cuts of the fibre cement wall cladding were used as furrings to pack the timber decking off the balcony surface. The consented details specified H3.2 treated timber furrings. Some of the deck fixings have come loose within the fibre cement furrings.
(a) widespread water entry resulting in damaged carpets, skirting boards, and interior linings;
(b) corrosion of structural steel beams and the steel seating angles for the floor system;
(c) framing timber decay and Stachybotrys mould growth as confirmed by laboratory analysis; and
(d) water and efflorescence staining on the underside of the concrete balcony floor slabs and water staining on walls directly below the balconies.
Terracon’s liability
(a) in accordance with the Building Consent and plans and specifications for the construction of the Nikau Apartments;
(b) with reasonable skill and care; and
(c) in accordance with the Building Code.
Council liability
(a) A Council officer inspecting the construction of the planter boxes:
... should have identified that the works were not constructed in accordance with the approved plans.
(b) The deficiencies in the installation of the membrane in the courtyard:
... would have been observable to a Council building inspector during an inspection of the courtyard membranes and was something that a competent inspector would have looked at.
(c) The qualification on the Product Warranty for the decks and box gutter/roof:
... should have been a warning to the Council officer who was processing the application for the code compliance certificate to investigate further and not simply accept the Producer Statement from Terracon Industries Ltd. The product supplier was not prepared to give a warranty for its product because the waterproof membrane had not been terminated correctly in accordance with the Nuraply details.
Quantum of damages
E. Mr Woolgar also says it would be appropriate to include provisional sum allowances to deal with unforeseen defects and to include a contingency sum in the remedial cost estimate. Mr Woolgar states that:
Overall, the Nikau Apartments require extensive remedial work to comply with the Building Code. This includes a full replacement of the waterproof membranes to unit balconies, planters and courtyards and the membrane roof, as well as wall framing remediation to affected areas, full recladding of weatherboard areas and widespread passive fire work.
In my opinion , the total cost the plaintiffs will likely incur in carrying out the remedial works to fix all of the defects and damage to the Nikau Apartments complex and obtain a code compliance certificate for the remedial works will be approximately $6,986,121 plus GST. This is based on a start date onsite of 1 December 2023 and the owners vacating their apartments for the duration of the works.
(a) a five per cent contingency sum to allow for unresolved aspects of the remedial design;
(b) a 10 per cent construction contingency sum to account for the inherent risk of remediation projects;
(c) an inflation rate of 2.98 per cent adjusted by half to reflect the mid- point of the project on the basis that the costs expended in the first part
of the project will not attract inflationary pressure but the costs in the latter part of the remedial project will;
(d) professional fees of $256,655, which are roughly 3.7% of the overall anticipated construction cost, which accords with other projects of this nature and size; and
(e) an estimate for building consent fees and insurance charges of about
0.3 per cent of the recommended total budget which, Mr Ranum says, is reflective of current market premiums for similar construction projects in his experience.
Apportionment of remediation costs
$4,868,409.00.
Other costs
Body Corporate management costs
Interest via the Interest on Money Claims Act 2016
Costs of proceeding
Result and orders
|
(a) Repair costs for Defects A, B and E:
|
$4,868,409.00
|
|
(b) Consultant costs:
|
$135,179.11
|
|
(c) Body Corporate management costs:
|
$36,445.42
|
|
(d) Interest on costs to date:
|
$13,930.16
|
|
(e) Costs of this proceeding:
|
$13,145.00
|
G J van Bohemen J
- 18 -
Updated Schedule 4: Ju dgment sums sought'"
|
Unit
|
Utility Interest
|
Sum sought
|
|
GA
|
2.95%
|
$149,479.71
|
|
GB
|
2.87%
|
$145,426.02
|
|
GC
|
3.08%
|
$156,066.95
|
|
GD
|
2.69%
|
$136,305.22
|
|
GE
|
2.69%
|
$136,305.22
|
|
GF
|
2.69%
|
$136,305.22
|
|
GG
|
2.92%
|
$147,959.57
|
|
GH
|
2.95%
|
$149,479.71
|
|
GI
|
2.92%
|
$147,959.57
|
|
GJ
|
2.92%
|
$147,959.57
|
|
GK
|
2.95%
|
$149,479.71
|
|
1A
|
2.95%
|
$149,479.71
|
|
1B
|
2.92%
|
$147,959.57
|
|
1C
|
2.92%
|
$147,959.57
|
|
1D
|
2.75%
|
$139,345.49
|
|
1E
|
2.75%
|
$139,345.49
|
|
1F
|
2.75%
|
$139,345.49
|
|
1G
|
2.95%
|
$149,479.71
|
|
J H
|
3.04%
|
$154,040.10
|
|
I
|
3.00%
|
$152,013.26
|
|
1J
|
3.00%
|
$152,013.26
|
|
1K
|
3.25%
|
$164,681.03
|
|
2A
|
3.16%
|
$160,120.63
|
|
2B
|
3.21%
|
$162,654.19
|
|
2C
|
3.21%
|
$162,654.19
|
|
2D
|
3.43%
|
$173,801.83
|
|
2E
|
3.43%
|
$173,801.83
|
|
2F
|
2.79%
|
$141,372.33
|
|
2G
|
3.00%
|
$152,013.26
|
|
2H
|
3.25%
|
$164,681.03
|
|
21
|
3.68%
|
$186,469.60
|
|
2J
|
3.68%
|
$186,469.60
|
|
2K
|
3.25%
|
$164,681.03
|
|
Total excl GST
|
100%
|
$5,067,108.69
|
' Each unit’s utility interest was recorded in the affidavi( of Stephen Douglas Plummer (sworn 8 September 2023) at [36] exhibiting NIKA.01.0007.
2313111:sz
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2023/3203.html