You are here:
NZLII >>
Databases >>
High Court of New Zealand Decisions >>
2024 >>
[2024] NZHC 2423
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Woodgate Limited v Palmerston North City Council [2024] NZHC 2423 (27 August 2024)
Last Updated: 6 September 2024
|
IN THE HIGH COURT OF NEW ZEALAND PALMERSTON NORTH REGISTRY
I TE KŌTI MATUA O AOTEAROA TE PAPAIOEA ROHE
|
|
CIV-2024-454-018 [2024] NZHC 2423
|
|
BETWEEN
|
WOODGATE LIMITED
Plaintiff
|
|
AND
|
PALMERSTON NORTH CITY COUNCIL
Defendant
|
|
Hearing:
|
13 June 2024
|
|
Appearances:
|
G J Woollaston for Plaintiff
N Jessen and O E Sinnema for Defendant
|
|
Judgment:
|
27 August 2024
|
JUDGMENT OF ASSOCIATE JUDGE PAULSEN
This judgment was delivered by me on 27 August 2024
at 4.00 pm pursuant to Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar Date:
WOODGATE LIMITED v PALMERSTON NORTH CITY COUNCIL [2024] NZHC 2423 [27 August
2024]
A preliminary issue
[5]
Background [6]
Summary judgment principles
[38]
Woodgate’s submissions [40]
The Council’s
submissions [45]
Nuisance [55]
Is there a nuisance?
[63]
Defences [94]
Implied consent
[95]
Ex turpi causa [98]
The change of use defence
[105]
Result [106]
- [1] The
plaintiff (Woodgate) is a land developer and the beneficial owner of land at
Aokautere (the Woodgate land). It wishes to develop
the land as a retirement
village. Leslie Fugle is the sole director of Woodgate. Mr Fugle has a long
connection with the Woodgate
land through his involvement with other companies
that have owned or attempted to develop it. There is a history of disputes and
litigation between those companies, Mr Fugle and the defendant (the Council)
about earthworks and drainage issues affecting the land.
- [2] The Council
is the owner of public stormwater infrastructure created as part of the
residential subdivision by Palmerston North
Industrial and Residential
Developments Ltd of land (the PNIRD land) adjoining the Woodgate land.
Stormwater is discharged from a
450 mm stormwater outflow pipe on what is called
Monaco Grove and travels for a short distance upon an intermediary strip before
entering onto the Woodgate land. Woodgate says the stormwater discharge has
caused, and continues to cause, ponding on and damage
to the Woodgate land and
is hindering its development.
- [3] Woodgate has
sued the Council in nuisance and negligence in respect to the stormwater
discharge. The application before me is
for summary judgment on the cause of
action in nuisance only. Woodgate seeks judgment as to liability and an
injunction to restrain
the Council from repeating or continuing the nuisance. It
also seeks an enquiry as to damages.
- [4] The Council
says the case is unsuitable for summary judgment and that:
(a) Woodgate has not provided sufficient evidence to establish nuisance is
occurring.
(b) There is no substantial and unreasonable interference with Woodgate’s
rights to the use or enjoyment of the land.
(c) The doctrine of natural servitude applies.
(d) In the event there is a nuisance it has several arguable defences to the
claim, namely:
(i) that relief should be withheld from Woodgate due to the principle of ex
turpi causa non oritur actio;
(ii) Woodgate gave its implied consent to the nuisance; and
(iii) the allegation of nuisance has arisen only because Woodgate wishes to
change the use of its land.
A preliminary issue
- [5] Both
parties challenged the admissibility of the other’s evidence in several
respects. Counsel did not require me to issue
rulings on these challenges but
were content that they were noted and dealt with as I considered appropriate in
my deliberations.
Many of the objections were of a technical nature, do not
affect my conclusions and I have not found it necessary to express a view
on
them. An issue of some significance, however, concerns what is advanced by
Woodgate as expert opinion evidence to which I shall
refer later in this
judgment.
Background
- [6] What
follows is necessarily only a summary of the complex and lengthy history that
has led to this litigation.
- [7] The Woodgate
land is in an area characterised by undulating land cut by gully networks. The
gullies include the Johnstone Drive
Gully, the head of which was originally
situated on the PNIRD land. This was a natural intermittent watercourse crossing
into the
Woodgate land and conveying stormwater northwards ultimately, I
understand, to the Manawatū River.
- [8] As part of
the PNIRD development, infrastructure was installed which collected and then
discharged stormwater onto Monaco Grove
near the boundary with the Woodgate
land. It was completed in about mid-2007 and the infrastructure vested
in the Council. The Council says the infrastructure was compliant with its
engineering standards for land development at the time
and was legally
established. It has been held by the Environment Court that the stormwater
discharge was a permitted activity under
relevant regional rules not requiring
resource consent.1
- [9] On 1
November 2007, the Council granted a subdivision and land use consent to Pacific
Farms Development Ltd (PFL) in respect of
the Woodgate land. Mr Fugle was a
director and shareholder of PFL. The owner of the land at the time was Aokautere
Land Company Ltd
(ALC), which later changed its name to Farm
Holdings
(4) Ltd (FH4). Mr Fugle had an involvement with this
company also, but the exact nature of the relationship at material times is
unclear.
- [10] Amongst
other things, PFL’s resource consent authorised the filling of gullies on
the Woodgate land. Unsurprisingly, the
resource consent contained conditions in
relation to existing stormwater discharges onto the Woodgate land. These
included a requirement
that PFL demonstrate how the stormwater would be captured
and catered for as follows:
(3) That prior to any filling, drainage works or other physical works within
the gullies, the MIPENZ (Geotechnical Specialist) CPEng
acceptable to Council
must provide and have approved by Council a design and full engineering plans
which include details of the
proposed filling, drainage and monitoring of these
physical works. The design and plans must include, although are not limited to,
the following:
- Demonstration
of how the existing upstream stormwater runoff and existing overland flow is
captured and how this is catered for.
...
- [11] PFL made
related applications to the Regional Council for water diversion consents which
were granted on 24 October 2007. The
consents included the condition that
“the installation of subsoil drainage and diversion of water ... shall be
undertaken in
general accordance with the application ...”. PFL’s
application said it would construct a main stormwater reticulation
system to
carry all the stormwater from the head of the Johnstone Drive Gully down to the
foot of that gully.
1 Re Manawatū-Wanganui Regional Council [2013] NZEnvC
213 at [63].
- [12] There were
delays before PFL commenced earthworks, but eventually significant quantities of
fill were deposited upon the Woodgate
land. It appears that at some stage a
stormwater detention pond was constructed immediately beneath the Monaco Grove
discharge. I
understand Mr Fugle does not accept that any stormwater detention
pond was created. Regardless, there is clear evidence of a stormwater
detention
pond on the Woodgate land that captures the stormwater discharge. It is, for
instance, shown in photographs attached to,
and referred to in, the Land
Development & Engineering Ltd (LDE) reports relied upon by Woodgate as well
as other documents.
The Council says this created a lake which backed up across
the boundary with the PNIRD land, flooding it and creating a
‘sideways’
overflow of stormwater from the pond onto what is called
Pacific Drive.
- [13] Around this
time both the Council and Regional Council sought, and were granted,
declarations from the Environment Court that
the Monaco Grove stormwater
discharge did not require resource consents and was therefore lawfully
established. From the Council’s
perspective this was relevant because PFL
had said in its application for resource consent that “[a]ll existing
legally established concentrated discharges that presently discharge into
the gullies are to be connected to and piped to the new stormwater system”
(emphasis added).
- [14] In
September 2011, ALC and PFL commenced High Court proceedings against the Council
and PNIRD. They pleaded several causes of
action, including in nuisance and
trespass relating to the stormwater discharge.
- [15] PFL’s
earthworks were not completed by 1 November 2012, the date its resource consent
was due to lapse. It appears the
reasons for this included that Mr Fugle
had interim enforcement orders issued against him by the Environment Court and
was ordered
to cease all earthworks due to non-compliance with PFL’s
consent conditions. There were subsequent interim orders and amendments
made by
the Environment Court to the enforcement orders, ultimately determining
that Mr Fugle was responsible for the works
undertaken on the site.2
The Council subsequently granted a five-year extension of the consent
until 1 November 2017.
2 See, for example, Manawatū-Wanganui Regional Council v
Fugle [2013] NZEnvC 212 at [21].
- [16] The High
Court proceedings brought by ALC and PFL went to trial but were discontinued
after a settlement was reached on 4 September
2014.3 Mr Fugle signed
the settlement agreement as agent for ALC. He says he felt pressured to do so
and there was not time for him to obtain
independent advice. As he was not a
party, this evidence raises questions as to his personal interest in the
proceeding.
- [17] The terms
of the settlement agreement included:
(a) The parties agreed to implement an “engineering solution”, which
provided for PNIRD to convey stormwater through
a 450 mm pipe on its land to a
new discharge location, where it would be collected by ALC and conveyed by a 450
mm stormwater pipe
to a contoured overflow path and then onto Johnstone
Drive.
(b) ALC acknowledged its obligation to submit an engineering design plan
demonstrating how the existing upstream stormwater runoff
and existing overland
flow would be captured and catered for.
(c) Mr Fugle and ALC were to apply to change the terms of Environment Court
enforcement orders (which prevented further works on
the Woodgate land) to
enable implementation of ALC’s obligations under the settlement
agreement.
(d) The settlement agreement bound the parties to that proceeding and their
successors in title.
(e) That all claims in the proceeding were settled and at an end.
- [18] PNIRD
subsequently completed its work under the settlement agreement, which included
re-routing the Monaco Grove discharge from
its original location to where it is
currently situated. However, ALC did not complete its work and the settlement
agreement was
therefore not fully implemented. Mr Fugle provides
several
3 HC Palmerston North CIV-2011-454-620.
reasons for this, and it is clear he must have been closely involved in
ACL’s decision not to perform its obligations.
- [19] There
followed more proceedings relating to the Woodgate land, which resulted in the
Environment Court making several enforcement
orders on 22 March 2016 against
FH4.4 FH4 was ordered to:
(a) cease all earthworks on the land;
(b) prepare and lodge an erosion and sediment control plan meeting various
technical requirements;
(c) complete applications for resource consents to undertake land disturbance
and vegetation clearance, incorporating the erosion
and sediment control plans;
and
(d) implement the resource consent upon its grant and in accordance with an
approved erosion and sediment control plan.
- [20] On 25 May
2016, FH4 entered voluntary liquidation. It was removed from the Register of
Companies in September 2017.
- [21] In October
2016, on a joint application by the Council and PNIRD, the Environment Court
made four further enforcement orders,
ordering FH4 to:5
(a) comply with the consent condition by providing a design and full engineering
plans which included details of the proposed filling,
drainage and monitoring of
physical works authorised by the consent, and a demonstration of how the
existing upstream stormwater
runoff and existing overland flow was captured and
catered for by FH4;
- Manawatū-Wanganui
Regional Council v Farm Holdings (4) Ltd [2016] NZEnvC 54. ALC had changed
its name to FH4 on 25 September 2013.
5 Palmerston
North City Council v Farm Holdings (4) Ltd [2016] NZEnvC 192.
(b) remove the stormwater detention pond and replace it with the engineering
solution as set out in the settlement agreement; and
(c) obtain a resource consent or a certificate of compliance in respect of the
implementation of the engineering solution.
- [22] Neither FH4
nor its liquidators complied with the Environment Court orders.
- [23] FH4’s
primary asset in its liquidation was the Woodgate land, which was subject to a
mortgage in favour of CTS Investments
LLC (CTS). The liquidators were unable to
sell the land and CTS did not realise its security. The liquidators disclaimed
the land
as onerous property and, on 17 November 2017, the High Court granted
CTS an order vesting the Woodgate land in its ownership.
- [24] On 5
December 2017, Woodgate was incorporated. On around 29 January 2018 it entered a
conditional sale and purchase agreement
with CTS to purchase the Woodgate
land.
- [25] Woodgate
has not settled its purchase of the land. It has plans to develop the land to
establish a retirement facility but has
not yet obtained resource consent for
that development.
- [26] On 31
January 2022, CTS filed proceedings against the Council, again relating to the
Monaco Grove discharge. In those proceedings
CTS made similar allegations
against the Council as are made by Woodgate here. CTS discontinued the
proceedings with costs awarded
to the Council.
- [27] CTS also
made a complaint to the Regional Council (now known as Horizons Regional
Council) about the Monaco Grove discharge.
The Council engaged Ridely Dunphy
Environmental (RDE) to provide an expert assessment of the erosion on the
Woodgate land. RDE’s
findings included:
- This erosion is
primarily below the dam feature and its primarily due to the nature of the
unconsolidated and unstabilised nature
of these soils from 2011 onwards;
- The discharge of
stormwater from upstream will be contributing water volume to the downstream
area of concern and as such will also
contribute to some erosion
activity.
- [28] In a
memorandum of 30 September 2022 addressing the complaint, the Regional Council
investigators found that the Council’s
stormwater discharge required minor
maintenance but that the cause of erosion on the Woodgate land was
“historic illegal earthworks”
which were never remediated.
- [29] The
Regional Council also identified a ‘cut’ made into the wall of the
stormwater detention pond which it appeared
was made within 12 months of the
investigation. This was leading to some scouring. The Regional Council
concluded:
Erosion of the recent cut in the PFL dam wall and the balance of the CTS site
are not directly attributable to the [Council] stormwater
discharge. Rather this
is due to recent and poorly executed earthworks (the PFL dam outlet) undertaken
by persons unknown or ground
conditions and in situ stormwater control related
to historic illegal earthworks activities that occurred on the CTS site, prior
to any influence from the [Council] stormwater discharge, and were never
remediated.
- [30] Mr Fugle
does not accept the content of the RDE or Regional Council reports.
- [31] In August
2022 Woodgate applied for consent to ‘retrospectively’ authorise the
previous earthworks undertaken on
the Woodgate land and to prospectively
authorise their completion. The application included:
Currently stormwater discharges onto the southern corner of the site from the
adjacent Monaco Grove stormwater system which drains
an area of approximately 60
dwellings. This water is detained at this point in such a way that the water
level is raised above the
pipe level. This enables overflow from the detention
area to informally drains [sic] across land to a gully trap in Pacific Drive.
This matter is the subject of further legal action between the landowner and the
Council. When the retirement village is constructed
it is proposed to integrate
the stormwater for the development and connect to the Monaco Grove discharge
pipe providing conveyance
to the head of Johnson Gully [sic]. This will be
addressed through a separate resource consent and a Development Agreement.
- [32] The Council
sought further information on the application and Woodgate responded:
Existing Stormwater Discharge Point: The application states that this
area area [sic] where stormwater is discharged from the upstream urban catchment
at Monaco Grove
will be excluded from the earthworks and will be addressed once a solution is
agreed with the Council. However, on further consideration,
a better approach
for neighbouring properties is to cease the ponding and overflow drain to
Pacific Drive as soon as practical and
replace it with a temporary diversion
drain through the site. This will be routed to divert stormwater away from the
active stage
of earthworks and will be detailed in the Earthworks Management
Plan.
- [33] The Council
granted the application, noting that:
[Woodgate] proposes to manage [stormwater discharge] through the site during
earthworks via a temporary diversion of this water around
the working areas with
it being discharged to the gully below with a constructed outfall.
- [34] The Council
also imposed conditions requiring Woodgate to submit to the Council an
Earthworks Management Plan (EMP) for certification
including “[d]etails of
how stormwater from the upstream residential catchment will be managed within
the site during earthworks”
and requiring Woodgate to “undertake all
earthworks authorised by this consent in accordance with the certified EMP at
all
times until the completion of the activity”.
- [35] Woodgate
provided the Council with an EMP that has since been certified. This
states:
All stormwater that enters the site at the southern boundary is to be
diverted around the earthworks by a Clean Water Diversion (CWD)
as detailed in
the approved ESCP. This CWD directs all water through the completed earthworks
on the western side of the fill area
and discharges it to the remnants of the
gully approximately 100m downstream (to the north) of the earthworks area. The
stormwater
is to flow to the CWD by either gravity or being pumped. The CWD has
been constructed in accordance with the ESCP.
...
The CWD is to remain in place and continue to function as a stormwater drain
during and upon completion of the earthworks until a
new reticulated system is
constructed as part of the next stage of the development. The size and location
of the reticulated stormwater
system is dependent upon the future
development.
- [36] The clean
water diversion (CWD) is functional and diverts stormwater that enters the
Woodgate land around the active earthworks.
However, Mr Fugle emphasises the CWD
is a temporary measure only and that its presence is obstructive to the
development of the land.
- [37] In addition
to this proceeding, Woodgate has also commenced proceedings in the Environment
Court seeking declarations and enforcement
orders requiring the Regional Council
to act against the Council in respect of the Monaco Grove discharge.
Summary judgment principles
- [38] The
relevant rule is r 12.2 of the High Court Rules 2016 which reads as
follows:
12.2 Judgment when there is no defence or when no cause of action can
succeed
(1) The court may give judgment against a defendant if the plaintiff
satisfies the court that the defendant has no defence to a cause
of action in
the statement of claim or to a particular part of any such cause of action.
(2) The court may give judgment against a plaintiff if the defendant
satisfies the court that none of the causes of action in the
plaintiff’s
statement of claim can succeed.
- [39] The
principles that apply to a plaintiff’s summary judgment application were
summarised by Associate Judge Osborne in Mount Grey Downs Ltd v Pinot
Properties Ltd as follows:6
(a) Commonsense, flexibility and a sense of justice are required.
(b) The onus is on the plaintiff seeking summary judgment to show that there is
no arguable defence. The Court must be left without
any real doubt or
uncertainty on the matter.
(c) The Court will not hesitate to decide questions of law where appropriate.
(d) The Court will not attempt to resolve genuine conflicts of evidence or to
assess the credibility of statements in affidavits.
(e) In determining whether there is a genuine and relevant conflict of facts,
the Court is entitled to examine and reject spurious
defences or plainly
contrived factual conflicts. It is not required to accept uncritically every
statement put before it, however
equivocal, imprecise, inconsistent with
undisputed contemporary documents or other statements, or inherently
improbable.
(f) In assessing a defence the Court will look for appropriate particulars and a
reasonable level of detailed substantiation –
the defendant is under an
obligation to lay a proper foundation for the defence in the affidavits filed in
support of the Notice
of Opposition.
6 Mount Grey Downs Ltd v Pinot Properties Ltd [2018] NZHC
3094 at [12].
(g) In weighing these matters, the Court will take a robust approach and enter
judgment even where there may be differences on certain
factual matters if the
lack of a tenable defence is plain on the material before the Court.
(h) The need for judicial caution in summary judgment applications has to be
balanced with the appropriateness of a robust and realistic
judicial attitude
when that is called for by the particular facts of the case. Where a
last-minute, unsubstantiated defence is raised
and an adjournment would be
required, a robust approach may be required for the protection of the integrity
of the summary judgment
process.
(i) Once the Court is satisfied that there is no defence, the Court retains a
discretion to refuse summary judgment but does so in
the context of the general
purpose of the High Court Rules which provide for the just, speedy and
inexpensive determination of proceedings.
(footnotes omitted)
Woodgate’s submissions
- [40] Woodgate
says its claim is straightforward. It does not accept any responsibility to deal
with stormwater entering its land from
the Monaco Grove pipe. It says the Monaco
Grove pipe concentrates and ejects stormwater onto its land in a manner that
occasions
or exacerbates ponding and which has caused actual damage by way of
erosion, sedimentation and scour. It contends the damage is significant,
undoubtedly an unreasonable interference with its use and enjoyment of the land
and therefore a nuisance at law. It says this is
the case whether or not the
stormwater discharge was lawfully established, despite the development history
of the land, and regardless
of how long the discharge has been
ongoing.7
- [41] Woodgate
argues that natural servitude does not assist the Council, because it is the
urbanisation (including hard surfacing/roading)
of the PNIRD land and the
ejectment of the water generated and caught via the Monaco Grove pipe that is a
significant causative component
of the ponding, erosion and scour that is
preventing use, development and reasonable enjoyment of the land. It also
contends that
the reinstatement of the pipe at its new location on Monaco Grove
significantly increased the volume and velocity of the flow of
the stormwater
discharge.
7 Bank of New Zealand v Greenwood [1983] NZHC 150; [1984] 1 NZLR 525
(HC).
- [42] Woodgate
rejects all of the Council’s positive defences. It argues the principle of
ex turpi causa can have no application when Woodgate has not played any
part in illegal or immoral conduct, and the defence does not apply to claims
based on interference with ownership rights to property.8
- [43] Woodgate
says the resource consent requiring it to control the stormwater discharge, and
the commitment to implement the CWD
during the currency of its earthworks cannot
be taken as implied consent to an ongoing nuisance.
- [44] Finally, it
says the change of use exception relied upon by the Council does not apply as
the stormwater discharge has always
constituted a nuisance, irrespective of any
change of use of the Woodgate land.9
The Council’s submissions
- [45] The
Council submits that Woodgate has not provided sufficient evidence of its claim
and that a full hearing is required to show
that the stormwater discharge
creates a nuisance. It notes that none of the authorities Woodgate relies upon
were decided by way
of summary judgment.
- [46] The Council
submits that any discharge of stormwater onto the Woodgate land is reasonable.
It relies on the Environment Court’s
decision that the discharge was
established in accordance with regional rules and did not cause erosion or
sedimentation beyond the
property boundary.10 It also relies upon the
compliance investigations by the Regional Council, which concluded that the
discharge generally complies with
the regional rules and that the issues faced
by Woodgate are largely due to the poor development history on its
land.
- [47] The Council
says Woodgate’s evidence also fails to acknowledge that stormwater from
the Monaco Grove pipe is properly discharging
a natural stormwater flow, even if
there are (unquantified) increases in volume and velocity attributable to past
development. It
says Woodgate is wrong that it has no obligation to handle
natural
8 Leason v Attorney General [2013] NZCA 509, [2014] 2 NZLR
224.
9 Barron v Louw [2018] NZHC 2275, [2018] NZAR 1668.
10 Re Manawatū-Wanganui Regional Council, above n
1.
stormwater, and when it acquired the land Mr Fugle knew the discharge had been
lawfully established and occurring for many years
prior. The Council also argues
that where a district or regional plan specifically addresses an issue, such as
the discharge of stormwater,
a court should be careful not to complicate the law
for ordinary landowners by adding an additional layer of
obligations.11
- [48] The Council
says in the context of the escape of water from property the law recognises the
principle of natural servitude, being
the duty of a lower property to accept the
natural flow of water from a higher property. It accepts the principle is
subject to limitations,
but says Woodgate’s evidence falls short of the
detailed assessment necessary for summary judgment to prove that such
limitations
apply here.
- [49] Importantly,
the Council submits there is no evidence from a stormwater engineer identifying
the natural flow of stormwater or
quantifying increases in volume or velocity
due to development of the PNIRD land, nor any geotechnical analysis addressing
the effects
of any increase in stormwater discharge as distinct from the natural
flow. The Council also says there is inadequate evidence to
establish it caused
any damage to occur on Woodgate’s land.
- [50] Further,
the Council submits that Woodgate cannot sue for interference with unlawful
uses, which it submits Woodgate’s earthworks are as they were
unconsented between November 2017 and January 2022. It contends
that post
January 2022 development of the Woodgate land is only lawful if carried out in
accordance with the conditions of Woodgate’s
consent, which requires it to
collect stormwater at its southern boundary and manage it through a
CWD.
- [51] The Council
also contends that Woodgate cannot allege nuisance in relation to the
interruption of future development plans for
a retirement village, as it does
not have a resource consent to carry out the development. Therefore, the Council
cannot interfere
with a right that does not yet exist.
- See
Cambridge Water Co v Eastern Counties Leather plc [1993] UKHL 12, [1994]
2 AC 264 at 307.
- [52] In relation
to ex turpi causa, the Council notes the law is in a state of development
and that there are aspects of the factual background which are impossible
to
ignore, particularly concerning Mr Fugle and his involvement in the failure of
PFL to take the steps required of it to control
the stormwater discharge and to
implement other erosion and sediment controls. It says it would be wrong and
unreasonable that Woodgate
succeed on its claim.
- [53] In relation
to the defence of implied consent, the Council argues that Woodgate obtained
resource consent on the condition it
would collect and manage the stormwater
discharge via the CWD. It says Woodgate cannot therefore now claim to have never
accepted
the stormwater discharge.
- [54] In relation
to the change of use defence, the Council submits if it is only because a
claimant has changed the use of land that
a pre-existing activity is said to
have become a nuisance then no action will lie. Here, it says the stormwater
discharge was lawfully
established when the Johnstone Drive Gully was in its
natural state, and it is only now an issue because of a history of broken
promises
by developers (with which Mr Fugle was associated) while changing the
use to which the land is to be put.
Nuisance
- [55] A
private nuisance is an unreasonable interference with a person’s right to
the use or enjoyment of an interest in land.
The legal standard of
unreasonableness is intended to strike a fair balance between the interests of
neighbouring occupiers of land.
- [56] In Smith
v Fonterra Co-operative Group Ltd, the Court of Appeal
said:12
- [40] There are
two types of nuisance actions: private nuisance and public nuisance, and
although the same conduct can amount to both
a public nuisance and private
nuisance, they are distinct. The key distinction between the two is the rights
they are designed to
protect. Private nuisance is concerned with protecting the
right of an occupier or owner of land to the quiet use and enjoyment of
their
land free from unreasonable interference. In contrast, public nuisance is
primarily concerned with the protection of public
rights, that is to say with
rights enjoyed by all members of the public, not specific individuals.
12 Smith v Fonterra Co-operative Group Ltd [2021] NZCA
552.
- [41] In both
private and public nuisance however, the interference with the right must be
both substantial and unreasonable before
it will be actionable. That is to say
the rights and obligations created by nuisance are not framed in absolute terms.
Not every
interference is actionable. An interference is unreasonable if in all
the circumstances “an ordinary person could not reasonably
be expected to
put up with it”. There has to be an element of give and take, live and let
live.
(footnotes omitted)
- [57] In an
action for nuisance the focus is upon the unreasonable effects of the
defendant’s conduct on the plaintiff’s
land, not the
defendant’s use of land and whether it is reasonable. In Bank of New
Zealand v Greenwood, Hardie Boys J concluded:13
It is
therefore not enough for the defendants to say that it is a normal and
reasonable thing to build a glass verandah. For that
is not the point. The point
is that the glass verandah was so built as to reflect the sun’s diffused
light across the street
into the south-facing windows opposite. To build it in
that way, so as to produce, albeit unwittingly, that result, is not in my
opinion the kind of activity which the reasonable man should be expected to
accept as part of the reciprocity of urban neighbourliness.
- [58] Proof of
physical damage to land that is material or substantial is normally sufficient
to establish that an interference is
unreasonable and thus a nuisance.14
That the defendant’s activities are authorised by planning
permission/resource consent15 or provide some public benefit will
generally not provide a defence to an action in nuisance, although that may be
relevant to the
remedy that the Court will provide.16
- [59] The escape
of water from one property to another that causes damage may constitute a
nuisance. The law, however, recognises that
in some instances a landowner must
accept the natural flow of water from higher land. This is known as the natural
servitude doctrine.
It has been said that the extent and limits of the doctrine
have not been explored definitively and
that:17
Furthermore, the relationship between planning
considerations both under the Resource Management Act 1991 and through the
requirements
of territorial authorities on the one hand and the right of natural
servitude on the other do not appear to have been fully considered
by the
courts.
13 Bank of New Zealand v Greenwood, above n 7, at
534-535.
14 St Helen’s Smelting Co v Tipping (1865) 11 HLC
642, 11 ER 1483 (HL) at 650, 1486.
15 Lawrence v Fen Tigers Ltd [2014] UKSC 13, [2014] 1 AC
822.
16 Miller v Jackson [1977] EWCA Civ 6; [1977] QB 966 (CA).
17 Body Corporate 335089 v Vero Insurance New Zealand Ltd
[2020] NZHC 2353 at [422], citing G W Hinde and others Principles of
Real Property Law (2nd ed, LexisNexis, Wellington, 2014) at 128.
- [60] In
Barron v Louw, the appellant had brought a claim in private nuisance
alleging that excess water was discharging from the respondent’s property.
The claim was dismissed in the District Court primarily on the doctrine of
natural servitude. On appeal to the High Court, Fitzgerald
J explained the
doctrine as follows:18
- [27] A precursor
issue is, however, the doctrine of natural servitude. If that doctrine applies,
and none of the exceptions to it
are triggered, then there will not be a
nuisance in the first place ...
- [28] The
doctrine of natural servitude is examined and summarised in
Hinde
McMorland and Sim Land Law in New Zealand as follows:
Before the commencement of the Resource Management Act it was clearly
established that the natural servitude as expressed in Gibbons v Lenfestey
applied in New Zealand allowing the higher owner, in the natural use of the
higher land, to concentrate and discharge on to the lower
land water that would
otherwise naturally flow there. Three principal limitations were placed upon
this right. First, the higher
owner could not, by means of an ‘artificial
structure’ such as a building or a raising of soil level, alter the
flow on to the lower land causing injury to that land. Secondly, he or she
could not so concentrate the water as to increase appreciably the burden
on the lower land by altering the volume and velocity with which the water
flowed on to the lower land, thus causing damage to the lower land which
would
not have been caused by the natural flow. Thirdly, he or she could not
introduce ‘foreign water’, that is, water which would not be
part of the natural surface water on the higher land, and insist that it be
received by the lower
landowner. Though there is some authority for the
proposition that the natural servitude applies only to rural land, and not to
urban
or suburban land, the better view is probably that it applies to all land
and that any problems in its application to non-rural land
are met by the
limitations upon the right.
- [61] The Judge
considered that, on the basis of the authorities, the central issue for her to
decide was whether structures or any
actions taken by the respondents on their
land had increased the amount of water naturally flowing to the
appellant’s property
or had directed the water in a new or harmful way
causing damage as follows:19
[52] ... For the reasons
outlined above, and recognising the doctrine of natural servitude, a defendant
will not liable in nuisance
provided that artificial structures or other actions
taken by the defendant have not caused natural surface waters (or new
“foreign”
waters) to pass onto the plaintiff’s land in a
different or increased way (from that which otherwise have been the case with
natural water flow) that causes damage.
18 Barron v Louw, above n 9.
19 Citing Bailey v Vile [1930] NZGazLawRp 93; [1930] NZLR 829 (CA) at
839–840; Wilsher v Corban [1955] NZLR 478 (SC) at 490; Dijkmans
v Howick Borough [1970] NZHC 18; [1971] NZLR 400 (SC) at 406–408; and Davis v
Lethbridge [1976] 1 NZLR 689 (SC) at 698–699.
- [62] Fitzgerald
J gave several reasons for reaching her conclusion that the respondents’
actions had not caused natural surface
waters to pass onto the land in a
different or increased way creating a nuisance. Most important was the evidence
of the respondents’
expert who had addressed the question: have any
alterations or actions by the respondents unreasonably increased the flow of
water
from the respondents’ property to the appellant’s property
than would have otherwise been the case with the natural flow
of water? The
expert found that the actions taken by the respondents and others had likely
decreased the natural flow of water that
would otherwise have passed onto the
appellant’s land.
Is there a nuisance?
- [63] I
understand the Council accepts for present purposes that Woodgate has standing
to bring an action in private nuisance against
it to protect unreasonable
interference with its use and enjoyment of the Woodgate land, despite not being
the legal owner of the
land.
- [64] There is
otherwise little common ground between these parties on factual matters.
Fundamentally the Council says Woodgate’s
application for summary judgment
cannot succeed as it is plainly arguable both that the stormwater discharge does
not unreasonably
interfere with Woodgate’s use and enjoyment of its land
and that it is not the cause of the ponding, flooding, erosion, scour
and
sediment outflow of which Woodgate complains.
- [65] As noted,
the Environment Court has held that the Monaco Grove discharge did not require
resource consent and was lawfully established.
I accept that does not of itself
mean that the discharge does not constitute a nuisance. However, before the
Court could find the
stormwater discharge was unreasonable Woodgate would need
to produce evidence concerning the volumes and rates at which stormwater
is
being discharged onto its land. Related to this, in light of Woodgate’s
assertion that urbanisation has increased both the
volume and velocity of the
stormwater and amplified its adverse effects on the Woodgate land, one would
also expect there would be
evidence to support that assertion. Such evidence
would be expected to be given
by experts in such matters but, for reasons I shall now come to, there is no
admissible expert evidence in relation to them.
- [66] Woodgate’s
case substantially relies on the evidence of David Dravitzki. Mr Dravitzki
is a Chartered Professional Engineering
Geologist with 25 years’
experience. His evidence is tendered as an expert assessment establishing that
the Woodgate land was
not unduly susceptible to erosion, scour or sediment
outflow, and that it was the urbanisation of the PNIRD land and concentration
of
water so generated that has caused significant flooding and other damage to
it.
- [67] Mr
Dravitzki’s affidavit is very brief but has attached to it two reports on
the letterhead of LDE dated 14 September 2023
and 17 May 2024. Mr Dravitzki says
he completed the reports attached to his affidavit and:
- [4] In preparing
these reports, and in affirming this affidavit, I am mindful of the requirements
to act impartially, fairly, and
independently, and to express only views and
opinions which are informed by professional metrics, observations, and
experience when
providing evidence as an expert before this court.
- [5] I refer to,
and confirm my understanding of the Code of Conduct for Expert Witnesses as it
applies in this respect.
- [68] The Council
objects to Mr Dravitzki’s evidence and argues it should not be
considered.
- [69] The
Evidence Act 2006 provides:
- Admissibility
of expert opinion evidence
(1) An opinion by an expert that is part of expert evidence offered in a
proceeding is admissible if the fact-finder is likely to
obtain substantial help
from the opinion in understanding other evidence in the proceeding or in
ascertaining any fact that is of
consequence to the determination of the
proceeding.
(2) An opinion by an expert is not inadmissible simply because it is
about—
(a) an ultimate issue to be determined in a proceeding; or
(b) a matter of common knowledge.
(3) If an opinion by an expert is based on a fact that is outside the general
body of knowledge that makes up the expertise of the
expert, the opinion may be
relied on by the fact-finder only if that fact is or will be proved or
judicially noticed in the proceeding.
(4) If expert evidence about the sanity of a person is based in whole or in
part on a statement that the person made to the expert
about the person’s
state of mind, then—
(a) the statement of the person is admissible to establish the facts on which
the expert’s opinion is based; and
(b) neither the hearsay rule nor the previous consistent statements rule applies
to evidence of the statement made by the person.
(5) Subsection (3) is subject to subsection (4).
- [70] Section 26
of the Act provides:
- Conduct
of experts in civil proceedings
(1) In a civil proceeding, experts are to conduct themselves in preparing and
giving expert evidence in accordance with the applicable
rules of court relating
to the conduct of experts.
(2) The expert evidence of an expert who has not complied with rules of court
of the kind specified in subsection (1) may be given
only with the permission of
the Judge.
- [71] The
relevant rule is r 9.43 of the High Court Rules, which provides:
9.43 Expert witness to comply with code of conduct
(1) A party to a proceeding who engages an expert witness must give the
expert witness a copy of the code of conduct set out in Schedule
4.
(2) An expert witness must—
(a) state in any written statement of the proposed evidence of the witness
served under rule 9.2 or 9.3, or at the time of giving
any oral evidence, or in
any affidavit containing the evidence of the expert witness, that the expert
witness has read the code of
conduct and agrees to comply with it:
(b) comply with the code of conduct in preparing any written statement of the
proposed evidence of the witness to be served under
rule 9.2 or 9.3 or in giving
any oral or affidavit evidence in any proceeding.
(3) The evidence of an expert witness who has not complied with subclause
(2)(a) may be offered only with the leave of the court.
- [72] The Code of
Conduct in sch 4 of the High Court Rules (the Code) begins by noting that an
expert’s duty is to assist the
court impartially within the expert’s
area of expertise. It then goes on to set out several other requirements with
which the
expert must comply.
- [73] In
Prattley Enterprises v Vero Insurance New Zealand Ltd, the Court of
Appeal noted that in deciding whether to admit expert opinion evidence the court
must be satisfied that it is likely
to obtain substantial help from the opinion
in understanding other evidence in the proceeding or in ascertaining any fact
that is
of consequence to the determination of the proceeding.20
Substantial helpfulness is an amalgam of relevance, reliability and
probative value.21
- [74] The Court
also held that ss 25 and 26 anticipate that evidence may be excluded for want of
reliability, impartiality or compliance
with the Code.22 A Judge
performs a gatekeeper function in deciding whether to admit such evidence, and
need not accept the opinion of an expert even
if uncontradicted.23
The gatekeeper function is necessary because “of the discipline it
brings to the admission and evaluation of expert
evidence”.24
- [75] In
relation to the Code and its requirements, the Court noted:
- [101] The Code
further requires that an expert witness comply with certain requirements, the
objective of which is to make transparent
the witness’s qualifications,
the facts and assumptions on which the witness has relied, the reasons for the
witness’s
opinion, and any literature or other material relied upon. These
requirements allow the opposing party and the Court to evaluate
the
expert’s expertise and opinion, initially for admissibility and ultimately
for weight:
- In
any evidence given by an expert witness, the expert witness
must—
(a) acknowledge that the expert witness has read this code of conduct and agrees
to comply with it:
(b) state the expert witness’ qualifications as an expert:
20 Prattley Enterprises Ltd v Vero Insurance New Zealand Ltd
[2016] NZCA 67 at [93].
21 At [94].
22 At [98].
23 At [94].
24 At [94].
(c) state the issues the evidence of the expert witness addresses and that the
evidence is within the expert’s area of expertise:
(d) state the facts and assumptions on which the opinions of the expert witness
are based:
(e) state the reasons for the opinions given by the expert witness:
(f) specify any literature or other material used or relied on in support of the
opinions expressed by the expert witness:
(g) describe any examinations, tests, or other investigations on which the
expert witness has relied and identify, and give details
of the qualifications
of, any person who carried them out.
- [102] The sixth
of these requirements anticipates that an expert will establish the reliability
of his or her methodology by demonstrating
that it is orthodox or otherwise
accepted within a relevant community of experts. The Code refers to
“any” literature
or other material, so recognising that it will not
be possible to reference such material in every case; some experts qualify by
experience rather than training, and allowances must be made for innovation. In
such cases reliability of methodology must be established
by means appropriate
to the circumstances. The important point for present purposes is that the Code
should not be taken to mean
that citing such material is optional. On the
contrary, a court may think it essential where methodology is in issue and the
material
ought to exist.
- [76] The
evidence of Mr Dravitzki does not comply with the Code, nor do I find it is
substantially helpful. I consider this the case
for all the following
reasons.
- [77] First, Mr
Dravitzki does not say he has read the Code and agrees to comply with it. He
says he is “mindful” of certain
requirements and “I refer to
and confirm my understanding” of the Code. That falls short of what is
required by the Code,
which is an acknowledgment that the Code has been read and
the evidence is given in compliance with it. While it might be argued
this is an
unduly pedantic approach, I disagree in circumstances where Mr Dravitzki’s
evidence does not comply with the Code
in obvious respects.
- [78] Second, one
of several “limitations” contained in the reports is that they are
prepared exclusively for Mr Fugle
in accordance with a brief given to LDE or an
“agreed scope”. The reports also state that the
“[i]nformation, opinions,
and recommendations contained within this report
can only be used for the purposes with which it was intended”. Neither the
brief nor the agreed scope referred to is disclosed.
The existence of such limitations has no place in an expert’s evidence. An
expert’s evidence is not given “exclusively”
for the person
who engages them but to assist the Court.
- [79] Third,
while Mr Dravitzki confirms he completed/prepared the reports, that does not
appear to be correct. Both reports are signed
by and stated to be prepared by a
Michael Davidson. The first report was originally an exhibit to Mr Fugle’s
first affidavit
and he said both Mr Davidson and Mr Dravitzki would confirm its
accuracy. Mr Davidson has never done so.
- [80] As Mr
Davidson, and not Mr Dravitzki, appears to have been the writer of the reports
that brings Mr Davidson’s compliance
with the Code and his qualifications,
expertise and experience in issue. There is no evidence about any of those
matters, apart from
the statement under his signature that he is an engineering
geologist. That would be insufficient to qualify him as an expert for
the
purposes of the Code even if he had sworn an affidavit.
- [81] Mr
Dravitzki does not acknowledge Mr Davidson’s role in preparing the
reports. There is also no evidence of what his review
of the reports entailed or
of the standards applying to such reviews. The reports refer to them having been
prepared in accordance
with “current standards, codes and best
practice” without identifying what they are.
- [82] Fourth, the
first report states that LDE was asked by Mr Fugle to “assess the existing
engineered fill placed on site and
potential stormwater damage to the fill
material from excess stormwater run-off”. That LDE report refers to
“[o]ur previous
detailed testing and assessment of the existing
fill” and “[o]ur observations at the site and detailed
assessment”
without providing those assessments and observations, or an
explanation of what methods or standards were applied or how the assessments
and
observations supported the reports’ conclusions. The conclusions
themselves are merely bullet points. There is therefore
insufficient information
to establish the reliability of the findings in the reports.
- [83] Fifth,
while Mr Dravitzki says he is familiar and experienced “in these areas of
analysis and research”, it is not
clear what areas he is referring to.
Certain observations and conclusions contained in the reports do not appear to
fall within the
expertise of a geologist but would, to my mind, require
expertise in civil engineering or groundwater hydrology. I include in this
the
statements that an increase of concentrated run-off was likely to have occurred
from impervious areas of the neighbouring subdivision
and that scour damage is
the result of stormwater being discharged onto the Woodgate land. Not only is it
not clear to me that Mr
Dravitzki (or Mr Davidson) is qualified to make such
assessments, there is also nothing in the reports identifying on what those
or
other conclusions are based.
- [84] Sixth, I
note the highly conditional nature of the conclusions in the reports. There are
conclusions such as “[a]n increase
of concentrated stormwater run-off is
likely to have occurred due to the collection of the stormwater from all
the impervious areas of the neighbouring subdivision” and
that “[i]t
is probable that the scour damage has been predominantly caused from the
stormwater being discharged into the site” (emphasis added). These
statements beg responses “how likely?” and “how
probable?”. There is no way to answer these questions given
the lack of
analysis in the reports.
- [85] The
language used may reflect LDE’s lack of knowledge of the site and the
circumstances and events that have given rise
to this litigation. LDE had not
been involved in previous work on the site and “[s]pecific dates of
chronological events are
unknown or limited”. The first report notes also
that it does not constitute a full review of the sequence of events or capacity
of the stormwater systems in play for which special civil engineering reviews
would be required.
- [86] The fact
the reports make no reference to the Code, the lack of any analysis, and the
nature of the disclaimers reflecting the
commercial relationship between LDE and
Mr Fugle suggests they were prepared for Mr Fugle’s purposes alone, not
intending that
they would be produced as evidence in a court proceeding. The
practice of attaching such documents to an affidavit and advancing
that as
expert opinion evidence is unsatisfactory. The standards required of an expert
witness are exacting
and the approach taken here does not have the degree of rigour or discipline
required to meet those standards.
- [87] The only
other evidence upon which Woodgate relies is given by Mr Fugle. Mr Fugle refers
to ponding on the land, particularly
during late 2023/early 2024 when attempts
were made to evacuate the stormwater detention pond. There is a dispute as to if
and when
the stormwater detention pond was established, by whom and what effect
that it has played in causing ponding and other damage to
the Woodgate land. It
is far from clear to me that the Council could be said to have caused ponding on
the Woodgate land if it would
not have occurred but for the construction on the
Woodgate land of what is effectively a dam.
- [88] In relation
to the erosion, scour and sediment outflow, Mr Fugle says that after Woodgate
obtained resource consent to undertake
preparatory earthworks, gorse and
overgrowth was removed which revealed significantly concealed ruts and erosion,
the extent of which
he cannot quantify. He believes this damage was the result
of the Monaco Grove stormwater infrastructure. He goes on to describe
the work
that has been done to remediate the land and costs associated with
that.
- [89] While Mr
Fugle appears to believe that the Council will be responsible for the costs of
this work, it is difficult to see how
this could be the case. There is no
evidence as to when this damage is said to have occurred. It would appear most
likely that it
occurred in the lengthy period that the land stood idle under
ACL/FH4’s ownership, during which period it settled its claim
with PNIRD
and the Council in respect to the stormwater discharge. In light of the terms of
that settlement, FH4 could not say the
continued stormwater discharge was a
nuisance and Woodgate cannot claim for damage that occurred to the land prior to
its ownership.
- [90] It has not
been shown, in my view, that erosion and scour damage has occurred due to
stormwater discharge or from other causes.
The Council says, and there appears
reason to believe, that the damage has occurred as a result of the poor
development history of
the site, reflected in the enforcement proceedings taken
by the Council against Mr Fugle and the companies with which he was associated.
There is also evidence that to the extent there has been any recent damage that
may have been
caused by a cut being made in the stormwater detention pond. On the evidence it
is unclear how or by whom that cut was made.
- [91] Further, it
is arguable in my view that the doctrine of natural servitude applies. The
Woodgate land and the land upon which
the Council’s stormwater
infrastructure is contained are contiguous, with the Woodgate land being the
lower land. The Johnstone
Drive Gully was one of several deep gullies that
provided drainage for stormwater flowing south to north over the PNIRD land and
then the Woodgate land. With the development of the PNIRD land the stormwater
was collected and discharged from the Monaco Grove
pipe into pre-existing
natural watercourses in the Johnstone Drive Gully.25
- [92] Woodgate
argues that natural servitude does not apply because urbanisation and hard
sealing have resulted in different or increased
flow of water causing damage. As
I have noted, the difficulty with that submission is the absence of admissible
evidence to support
it. Similarly, Woodgate submits that the relocation of the
Monaco Grove pipe means there is a new pathing/outflow which can be in
no way
commensurate with the natural water collection and flow previously occurring. To
advance that submission I would again expect
Woodgate to have provided some
expert evidence to support it but it has not.
- [93] In short,
the Council is correct that whether the discharge of stormwater onto the
Woodgate land is a nuisance is essentially
a factual enquiry, requiring findings
by the Court on matters that are genuinely disputed and, with the very limited
evidence before
me, are not amenable to resolution on this summary judgment
application.
Defences
- [94] Given
my conclusion it is unnecessary to deal with the positive defences the Council
says it will rely upon should Woodgate otherwise
establish the stormwater
discharge is a nuisance, but for completeness I will say something about
them.
25 See Re Manawatū-Wanganui Regional Council, above n
1, at [28].
Implied consent
- [95] Consent is
available as a defence to nuisance. The Council says that Woodgate consented to
the nuisance because, as part of its
application for resource consent to
complete the earthworks, it offered a condition to collect stormwater on the
southern boundary
and manage it via the CWD.
- [96] The Council
relies upon Lyttelton Times Co Ltd v Warners Ltd, where the parties had
entered into an agreement whereby the appellant’s printing premises were
to be rebuilt and the respondent
was to lease the upper floors for use as extra
bedrooms for their hotel.26 The respondent sued for nuisance due to
vibrations from the printing press which caused discomfort to hotel guests. The
claim was
dismissed as both parties had contemplated that the appellant would
continue its normal printing operations, and the respondent had
therefore
impliedly consented to any interference that might be created by that
activity.
- [97] Lyttelton
Times Co Ltd v Warners Ltd is a very different case from this one. Here the
Council and Woodgate have not entered into an agreement from which a common
intention
can be implied. It appears that Woodgate understood that the Council
would require as a condition of granting it consent for earthworks
that it
manage the stormwater, and its offer to do so cannot be taken as an intention to
forgo its rights to complain about what
it considers is a nuisance. This must be
particularly so when Woodgate’s application noted that the matter was the
subject
of legal action between Woodgate and the Council, and the CWD was not a
permanent solution and would be addressed in a subsequent
application for
resource consent for the retirement village.
Ex turpi causa
- [98] The Council
relies on the ex turpi causa principle and intends to argue that remedies
in nuisance should not be available to Woodgate because of the breach by PFL of
the terms
of its resource consent requiring it to collect the stormwater
discharge, the failure of ACL to perform the settlement agreement,
the
various
26 Lyttelton Times Co Ltd v Warners Ltd (1907) NZPCC 470,
[1907] AC 476 (PC).
enforcement orders in respect to the development that were ignored, that the
earthworks on the Woodgate land were abandoned, and
that the latest consent
issued to Woodgate requires it to manage the stormwater.
- [99] The Council
relies upon Brown v Dunsmuir, where Penlington J dismissed an appeal from
the District Court on the basis that it would be an affront to the public
conscience
if a landowner or developer who ignored bylaws and illegally
excavated and encroached on a neighbour’s land could obtain judgment
for
trespass to land against a neighbour placing soil on the developer’s land
as a protective measure.27 The Judge considered that to grant the
plaintiff a remedy for nuisance would make a mockery of a local
authority’s right to
control excavation work within its
territory.28
- [100] The common
element in all of the matters relied upon by the Council is Mr Fugle. It is
undoubtedly the case that the stormwater
discharge would not be in issue had
companies which Mr Fugle owned, controlled or was closely associated with in
respect to the development
of the Woodgate land complied with the terms of
resource consent conditions or the settlement agreement. It may also be the case
that if damage is presently occurring to the Woodgate land that it has been
caused, or at least substantially contributed to, by
those companies and Mr
Fugle through the construction of the stormwater detention pond and the failure
to undertake earthworks in
accordance with the terms of consent and/or to comply
with enforcement orders. It is easy to see why the Council says it would be
unconscionable in those circumstances for Woodgate, a company wholly owned by Mr
Fugle, to be successful on its claim.
- [101] The limits
of the ex turpi causa principle are unclear and the law is in a state of
development in this country. It was considered in Leason v Attorney
General,29 where the Court of Appeal referred to Euro-Diam Ltd
v Bathurst wherein Kerr LJ in the English Court of Appeal
said:30
The ex turpi causa defence ultimately rests on a principle of public policy
that the courts will not assist a plaintiff who has been
guilty of illegal (or
immoral) conduct of which the courts should take notice. It applies if in all
the circumstances it would be
an affront to the public conscience to grant
the
27 Brown v Dunsmuir [1994] NZHC 2033; [1994] 3 NZLR 485 (HC).
28 At 492.
29 Leason v Attorney General [2013] NZCA 509, [2014] 2 NZLR
224.
30 Euro-Diam Ltd v Bathurst [1990] 1 QB 1 (CA) at 35.
plaintiff the relief which he seeks because the court would thereby appear to
assist or encourage the plaintiff in his illegal conduct
or to encourage others
in similar acts ...
- [102] The Court
of Appeal in Leason noted that no single formulation of the correct test
to apply had emerged, and identified three different expressions of the
principle
referred to as the reliance test, the conscience approach and a
causation approach.31 It also noted that the courts will not, on the
basis of the ex turpi causa defence, refuse to enforce the rights of an
owner of property where the claim rests solely on
ownership.32
- [103] There
have, however, been several recent decisions of the Supreme Court of the United
Kingdom on the matter.33 Drawing on those authorities, the authors of
Todd on Torts suggest that the ex turpi causa principle is founded
in the need for decisions in civil proceedings to be consistent with those in
criminal proceedings.34 The authors considered the principle a rule
of law and not simply a matter for the exercise of judicial discretion, and
suggested
it requires the court to consider two key questions. Those were,
first, whether the civil claim being advanced was inconsistent with
the criminal
law in such a way that allowing the claim would undermine the integrity of the
legal system and, second, even if not
inconsistent, is the turpitude involved in
the plaintiff’s conduct such that the grant of relief by a court would be
contrary
to the public interest as opposed to the private interests of the
parties.35
- [104] It has
been held that where a summary judgment application concerns a developing area
of the law that may be a reason to send
the case to trial.36 That
said, the Council faces considerable hurdles in advancing this defence. It
relies on conduct of persons/entities that occurred
prior to Woodgate being
incorporated and acquiring the land. Counsel did not explain the legal basis for
attributing that conduct
to Woodgate. Further, Woodgate does not rely on any
illegal conduct of its own to establish its claim, nor could it be said that
any
illegal act by it was an effective cause of its loss. Woodgate’s argument
that the principle cannot be raised to defeat
its claim
31 Leason v Attorney-General, above n 29, at [115].
32 At [125].
33 Hounga v Allen [2014] UKSC 47, [2014] 1 WLR 2889; Les
Laboratoires Servier v Apotex Inc
[2014] UKSC 55, [2015] 1 AC 430; Patel v Mirza [2016]
UKSC 42, [2017] AC 467.
34 Stephen Todd and others Todd on
Torts (9th ed, Thomson Reuters, Wellington) at [20.7.8].
35 At [20.7.8].
- Westpac
Banking Corp v MM Kembla New Zealand Ltd [2000] NZCA 319; [2001] 2 NZLR 298, (2000) 14 PRNZ
631 (CA).
when it seeks to enforce rights of ownership of property appears consistent with
the view of the Court of Appeal in Leason.37 Had it been
necessary for me to decide the matter, I would have found Leason was
binding upon me and that this was not an arguable defence to the claim.
The change of use defence
- [105] This
defence is based on an assertion that the alleged nuisance arises only because
of Woodgate’s intention to change
the use of the land to construct a
retirement village. I do not see that Woodgate’s claim is dependent upon
it establishing
any particular use of the land. It says that the fact the
stormwater discharge is causing material physical damage is sufficient,
irrespective of what use it may in the future wish to put the
land.38
Result
- [106] The
application for summary judgment is dismissed.
- [107] It is
usual, but not inevitable, in such cases for costs to be reserved. I will
reserve costs, but should either party consider
that costs should be awarded and
paid at this juncture then they may file a memorandum seeking a ruling within 21
days with 14 days
for any reply. All memoranda should be limited to six
pages.
- [108] The case
is to be allocated a telephone case management conference with an Associate
Judge within the next four weeks. Counsel
shall confer and are to file a
preferably joint memorandum of timetable directions that are sought to take the
case to trial.
O G Paulsen Associate Judge
Solicitors:
Dewhirst Law, Palmerston North
Cooper Rapley Lawyers, Palmerston North
37 Leason v Attorney-General, above n 29.
38 Lawrence v Fen Tigers Ltd, above n 15, at
[55]–[56].
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2024/2423.html